South Sydney City Council v Hexiva Pty Limited

Link copied
Case Copied 19 min read
Reported Decision: 120 LGERA 146

Land and Environment Court


of New South Wales


CITATION: South Sydney City Council v Hexiva Pty Limited [2001] NSWLEC 172
PARTIES:

APPLICANT
South Sydney City Council

RESPONDENT
Hexiva Pty Limited
FILE NUMBER(S): 40047 of 2001
CORAM: Talbot J
KEY ISSUES: Injunctions and Declarations :- mandatory fire safety orders.
LEGISLATION CITED: Environmental Planning and Assessment Act 1979 s 121B(1) - 6, s 124
Local Government Act 1993 s 132
CASES CITED: ACR Trading Pty Ltd & Anor v Fat-sel Pty Ltd & Anor (1987) 11 NSWLR 67;
Crimmins (as executrix of estate of Crimmins dec'd) v Stevedoring Industry Finance Committee [1999] 167 ALR 1;
Pyrenees Shire Council v Day & Anor (1998) 192 CLR 330;
Warringah Shire Council v Sedevcic (1987) 10 NSWLR 335
DATES OF HEARING: 06/07/01, 26/07/01
DATE OF JUDGMENT:
08/02/2001
LEGAL REPRESENTATIVES:


APPLICANT
Mr A M Hawkes (Solicitor)
SOLICITORS
Pike Pike & Fenwick

RESPONDENT
Mr R Wechsler
SOLICITORS
N/A


JUDGMENT:

    IN THE LAND AND Matter No. 40047 of 2001
    ENVIRONMENT COURT Coram: Talbot J
    OF NEW SOUTH WALES Decision Date: 2 August 2001

    South Sydney City Council
    Applicant
    v
    Hexiva Pty Limited

    Respondent

    REASONS FOR JUDGMENT


    1. The respondent is the owner of a five storey residential flat building containing bachelor flats over a basement carpark. The building was erected pursuant to a development consent issued in 1962.

    2. On 26 May 1998 the council issued a notice of proposed order to the respondent pursuant to s 132 of the Local Government Act 1993. Representations were made by the respondent following which a final order was issued on 24 July 1998.

    3. Following further correspondence and argument between the parties the council issued a further notice of proposed order on 13 January 1999. The respondent again took advantage of the opportunity to make representations in regard to the proposed order.

    4. On 25 March 1999 a final order was served on the respondent company pursuant to s 121B(1) – 6 of the Environmental Planning and Assessment Act 1979 (“the EP&A Act”).

    5. The respondent submitted a development application in respect of the building on 3 June 1999. The council determined the development application by way of approval on 28 August 1999.

    6. The respondent lodged an application for a construction certificate on 13 July 2000 and the certificate was issued on 29 December 2000.

    7. These class 4 proceedings were commenced by application filed on 28 March 2001. The applicant claims relief by way of a declaration that the respondent has failed to comply with the order dated 25 March 1999 and an order that the respondent comply with the terms of that order.

    8. The approved development of the property, when carried out, will convert existing bachelor apartments into one bedroom apartments and one two bedroom apartment, with balconies to be added to each apartment. The development work has not commenced.

    9. Some parts of the fire order have been complied with and the council has agreed with…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read South Sydney City Council v Hexiva Pty Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2001] NSWLEC 172
Decision Date

CaseChat Overview and Summary

South Sydney City Council has brought proceedings against Hexiva Pty Limited concerning compliance with a fire safety order issued under the Environmental Planning and Assessment Act 1979 (NSW). The primary issue before the court was whether Hexiva Pty Limited had failed to comply with a series of mandated fire safety improvements at premises located at 5 Tusculum Street, Potts Point. The Council argued that Hexiva Pty Limited had not undertaken the specified works within the stipulated timeframes, thereby breaching the terms of the order.

The court was required to determine the extent of Hexiva Pty Limited's non-compliance and to set specific timeframes for the respondent to complete the required works. The Council claimed that the failure to comply with the order not only posed a significant risk to the safety of the building's occupants but also undermined the regulatory framework designed to protect public safety. Hexiva Pty Limited, on the other hand, contended that it had made substantial efforts to comply and that the Council's claims were overstated. The court needed to weigh the evidence presented by both parties and determine the appropriate legal remedies and orders to ensure compliance with the statutory requirements.

After considering the evidence, the court found that Hexiva Pty Limited had indeed failed to comply with the order in several respects. The court was satisfied that the respondent had not undertaken the required works within the specified timeframes and had not maintained the necessary fire safety standards. The court detailed specific periods within which the respondent must complete each mandated work, ranging from immediate actions to be taken to works to be completed within 18 weeks from the date of the order. Additionally, the court provided for alternative works to be completed in lieu of certain specified tasks, ensuring that the final outcome would meet the required safety standards.

Orders

Orders of the court

45. Having regard to the whole of the circumstances and after taking into account the evidence of the witnesses called by both parties and the written and oral submissions made, the Court proposes to make formal orders as follows:-

1. A declaration that the respondent has failed to comply with an order dated 25 March 1999 served upon it by the applicant pursuant to s 121B(1) - 6 of the EP&A Act with respect to the premises known as 5 Tusculum Street, Potts Point.

46. The Court makes the following orders:-

2. That the works required to be undertaken within premises known as 5 Tusculum Street, Potts Point by the following paragraphs of the Fire Safety Order issued by South Sydney City Council under s 121B(1) - 6 of the EP&A Act and dated 25 March 1999 be undertaken by the respondent within the periods specified below, such periods to be calculated as from the date of this order:-

Par 1.1 12 weeks

Par 1.2 1 week

Par 1.3 12 weeks

Par 1.4 18 weeks

Par 1.5 18 weeks

Par 1.6 8 weeks

Par 1.9 6 weeks

Par 1.10 8 weeks

Par 2.1 Immediately and to be maintained at all times

Par 2.2 Immediately and to be maintained at all times

Par 2.3 Immediately and to be maintained at all times

Par 2.4 6 weeks

Par 3.1 18 weeks

Par 4.1 18 weeks

Par 4.2 2 weeks

Par 4.3 2 weeks

Par 4.4 2 weeks

Par 4.5 2 weeks

Par 4.6 8 weeks

Par 5.2 8 weeks

Par 5.3 8 weeks

3. That in lieu of the works required under Order 1.11 dated 25 March 1999, the respondent shall do the following works agreed with council on 6 July 2001 within 18 weeks from the date of this order:-

(a) Remove the existing fire door currently positioned at the top of the stair flight connecting the basement carpark and the exit door at ground floor level (fire exit discharge level);

(b) Provide a fire door set complying with AS1905 to the existing opening at the bottom of the stair landing;

(c) Provide a fire door set complying with AS1905 to separate the basement carpark from the laundry and the required fire isolated stair of the carpark level (where the existing steel gate is currently positioned);

(d) Provide additional signage to direct building occupants to the final exit door of the building;

(e) Provide additional signage to the back of the new fire door at the bottom of the stairs to indicate that it is not an exit door;

(f) Remove all storage materials inside the fire stair;

(g) Submit to council an alternative building solution to determine equivalence with the Deemed to Satisfy Clause D2.4 of the BCA, in accordance with the assessment methods specified in A0.9 of the BCA; and

(h) Install a smoke door to the laundry entry.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established