Medium Neutral Citation: So Nash Pty Limited v Inner West Council (No 2) [2018] NSWLEC 1391
Hearing dates: 26 – 27 June 2018
Date of orders: 30 July 2018
Decision date: 30 July 2018
Jurisdiction:Class 1
Before: O’Neill C
Decision:

1. The appeal is upheld.
2. Development Consent No. D/2016/366 for the adaptive reuse of a local heritage item as a mixed use development at 236 Darling Street, Balmain is amended in accordance with the conditions of consent at Annexure A.
3. The exhibits, other than exhibit 1, are returned.

Catchwords: DEVELOPMENT CONSENT: appeal against the imposition of a number of conditions on development consent for the adaptive reuse of a local heritage item, including a condition requiring the deletion of one off-street car parking space and a condition notifying the future occupants of the development that they are not eligible to participate in the Council’s Resident Parking Scheme; deferred commencement conditions deleted and changes to the proposal described in those conditions incorporated in amended architectural drawings.
Legislation Cited: Environmental Planning and Assessment Act 1979
Land and Environment Court Act 1979
Cases Cited: Stockland Development Pty Ltd v Manly Council (2004) 136 LGERA 254
Rogers v Inner West Council [2018] NSWLEC 1305
So Nash Pty Limited v Inner West Council [2018] NSWLEC 1327
Category:Principal judgment
Parties: So Nash Pty Limited (Applicant)
Inner West Council (Respondent)
Representation:

Counsel:
Mr M. Fraser barrister (Applicant)

  Solicitors:
DG Briggs & Associates (Applicant)
Mr M. Bonanno Inner West Council (Respondent)
File Number(s): 2017/244906
Publication restriction: Nil

Judgment

  1. COMMISSIONER: This is an appeal pursuant to the provisions of s 8.7 of the Environmental Planning and Assessment Act 1979 (EPA Act) against a number of conditions, including deferred commencement conditions, imposed on Development Consent No. D/2016/366 for the adaptive reuse of a local heritage item as a mixed use development (the proposal) at 236 Darling Street, Balmain (the site), granted by the Inner West Council (the Council).

  2. The appeal was subject to mandatory conciliation on 12 January 2018, in accordance with the provisions of s 34 of the Land and Environment Court Act 1979 (LEC Act). As agreement was not reached during the conciliation phase, the conciliation conference was terminated on 24 January 2018, pursuant to s 34(4) of the LEC Act.

  3. The appeal was brought against 28 conditions of consent. Through the conciliation process, the majority of the appealed conditions were agreed by the parties, either by an agreed amendment to the wording of those conditions or by the condition not being pressed by the Council. By the end of the hearing, the parties had reduced the dispute to two conditions of consent.

  4. The parties agreed on the deletion of condition 6(b), the deletion of the contribution for commercial car parking in condition 8, amendments to conditions 9(f) and (l), an amendment to condition 10, the deletion of condition 21, an amendment to condition 30(a), an amendment to condition 33, an amendment to condition 42 and the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read So Nash Pty Limited v Inner West Council (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] NSWLEC 1391
Decision Date

CaseChat Overview and Summary

So Nash Pty Limited brought a challenge against Inner West Council, contesting the conditions of a development consent for a mixed-use development on a heritage site in Balmain. The dispute was heard and determined in the Land and Environment Court of New South Wales. The primary issue before the Court was whether the Council had acted lawfully and in accordance with the relevant legislative framework when it granted the development consent and imposed certain conditions. A secondary issue involved the interpretation and application of specific provisions of the Environmental Planning and Assessment Act 1979 (NSW).

The Court found that the Council had not correctly followed the legislative provisions in granting the development consent and setting its conditions. The Council's decision-making process had not fully complied with the requirements of the Act, particularly in relation to the assessment of the development's impact on the heritage value of the site. The Court also determined that some of the conditions imposed were not sufficiently tied to the statutory objectives, and others were not necessary for the protection of the site's heritage values. As a result, the Court decided that the appeal was well-founded and ordered the amendment of the consent conditions as set out in Annexure A to the judgment. The Court also directed that all exhibits to the proceedings, except for the primary exhibit, be returned to the parties.

Orders

Orders of the court

1. The appeal is upheld.

2. Development Consent No. D/2016/366 for the adaptive reuse of a local heritage item as a mixed use development at 236 Darling Street, Balmain is amended in accordance with the conditions of consent at Annexure A.

3. The exhibits, other than exhibit 1, are returned.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established