Supreme Court
New South Wales
Medium Neutral Citation: Smith v Impero Pacific Group Pty Ltd t/as Impero Constructions [2024] NSWSC 1234 Hearing dates: 26 September 2024 Date of orders: 26 September 2024 Decision date: 26 September 2024 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Proceedings stayed until the plaintiff pays into Court the sum of the adjudication determination
Catchwords: BUILDING AND CONSTRUCTION – adjudication – adjudicated amount – where plaintiff commenced these proceedings seeking to quash an adjudication determination – where first defendant registered adjudication certificate – where judgment now entered against plaintiff – where first defendant seeks stay of these proceedings until plaintiff pays into Court the adjudicated amount – where plaintiff has no present ability to pay amount into Court – where plaintiff’s assets exceed her liabilities – where secured creditor in possession and about to exercise power of sale over plaintiff’s principal assets
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Cases Cited: Nazero Group Pty Limited v Top Quality Construction Pty Limited [2015] NSWSC 232
Surfabear Pty Ltd v GJ Drainage & Concrete Construction Pty Ltd [2009] QSC 308
Tombleson v Dancorell Constructions Pty Limited [2007] NSWSC 1169
Category: Procedural rulings Parties: Samantha Smith (Plaintiff/Respondent)
Impero Pacific Group Pty Ltd trading as Impero Constructions (First Defendant/Applicant)
John O’Brien (Second Defendant)Representation: Counsel:
Solicitors:
M Sheldon / J M Kadar (Plaintiff/Respondent)
F Hicks SC (First Defendant/Applicant)
ITC Law Pty Ltd (Plaintiff/Respondent)
Construction Legal (First Defendant/Applicant)
Lauderdale Construction Lawyers (Second Defendant)
File Number(s): 2024/292680
EX TEMPORE JUDGMENT (REVISED)
-
The plaintiff, Ms Samantha Smith, owns a property in Northbridge.
-
On 3 April 2020, she entered a cost plus contract with the first defendant, Impero Pacific Group Pty Ltd, to demolish the home that then existed on the Northbridge property and to construct an alternative residence.
-
The original contract value was $4.4 million. Evidently, because of a large number of variations, the contract value increased to $8.3 million.
-
On 14 March 2024, Ms Smith’s financier, Aura Loan Management Pty Ltd, exercised its “step-in” rights under a tripartite agreement between it, Ms Smith and Impero, and terminated the contract.
-
Aura is now in possession of the Northbridge property and has listed it for sale.
-
Following the exchange of a payment claim, payment schedule, adjudication application and adjudication response under the Building and ConstructionIndustry Security of Payment Act 1999 (NSW) (“the Act”), Impero now has the benefit of an adjudication determination made on 23 July 2024 that Ms Smith pay it $419,183.16.
-
On 9 August 2024, Ms Smith commenced these proceedings seeking to quash that adjudication determination.
-
The first return date of Ms Smith’s Summons was last Friday, 20 September 2024. Although Ms Smith’s solicitors have encouraged Impero’s then solicitor to proceed with the matter as quickly as possible, it has not yet served a List Response.
-
Impero recently engaged a new solicitor, and by Notice of Motion filed on 19 September 2024, now seeks an order that the proceedings be stayed until…
Keep reading for free
Create a free CaseChat account to read Smith v Impero Pacific Group Pty Ltd t/as Impero Constructio... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NSWSC 1234
- Decision Date
CaseChat Overview and Summary
The court was tasked with deciding whether to grant a stay of the proceedings under the Building and Construction Industry Security of Payment Act 1999. The first defendant argued that the stay was necessary to protect its interests, given that the plaintiff had no present ability to pay the adjudicated amount into court. The plaintiff, on the other hand, maintained that there was no basis for a stay as it had sufficient assets, despite the presence of a secured creditor poised to exercise its power of sale over the plaintiff's principal assets. The court had to balance the rights of both parties, considering the statutory framework and the practical implications of enforcing the adjudicated amount.
In determining the application, the court considered the statutory provisions and relevant case law. It found that the statutory mechanism provided for in the Security of Payment Act was designed to ensure prompt and effective enforcement of adjudication determinations. The court recognised the importance of preserving the integrity of the adjudication process and the rights of parties who had successfully obtained an adjudication determination. The court also noted the plaintiff's financial situation, including the presence of a secured creditor with a pending power of sale over the plaintiff's main asset. Ultimately, the court held that the stay was necessary to protect the first defendant's rights and ordered that the plaintiff pay the adjudicated amount into court as a condition of staying the proceedings. The court also set a timeframe for the payment and provided for potential consequences if the plaintiff failed to comply.
In summary, the court granted the first defendant's application for a stay of the plaintiff's proceedings, subject to the plaintiff paying the adjudicated amount into court within a specified period. Failure to do so would result in the continuation of the stay and potential further action by the first defendant. This decision underscored the importance of enforcing adjudication determinations and the need to balance the rights of all parties involved in the dispute.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.