Skilled Group Limited

Case

[2016] FWCA 952

12 FEBRUARY 2016

No judgment structure available for this case.

[2016] FWCA 952
FAIR WORK COMMISSION

DECISION


Fair Work (Transitional Provisions and Consequential Amendments) Act 2009

Sch. 3, Item 16 - Application to terminate collective agreement-based transitional instrument

Skilled Group Limited
(AG2015/6977)

SKILLED RAIL SERVICES EMPLOYEE COLLECTIVE AGREEMENT

Industries not otherwise assigned

COMMISSIONER HAMPTON

ADELAIDE, 12 FEBRUARY 2016

Application for termination of the Skilled Rail Services Employee Collective Agreement.

[1] This decision concerns an application by Skilled Group Limited pursuant to Item 16 of Schedule 3 of the Fair Work (Transitional Provisions and Consequential Amendments) Act 2009 (the Transitional Act), and as a consequence, s.225 of the Fair Work Act 2009 (the FW Act). The application seeks to terminate the Skilled Rail Services Employee Collective Agreement.. 1

[2] The Agreement is a collective agreement-based transitional instrument for the purposes of the Transitional Act 2 with a nominal expiry date of 25 March 2014.

The relevant legislation

[3] Item 16 of Schedule 3 of the Transitional Act provides:

    16 Collective agreement-based transitional instruments: termination by the FWC
    (1) Subdivision D of Division 7 of Part 2-4 of the FW Act (which deals with termination of enterprise agreements after their nominal expiry date) applies in relation to a collective agreement-based transitional instrument as if a reference to an enterprise agreement included a reference to a collective agreement-based transitional instrument.
    (2) For the purpose of the application of Subdivision D to an old IR agreement, the agreement’s nominal expiry date is taken to be the end of the period of the agreement.”

[4] Subdivision D of Division 7 of Part 2-4 of the FW Act states:

    225 Application for termination of an enterprise agreement after its nominal expiry date

    If an enterprise agreement has passed its nominal expiry date, any of the following may apply to the FWC for the termination of the agreement:

      (a) one or more of the employers covered by the agreement;
      (b) an employee covered by the agreement;
      (c) an employee organisation covered by the agreement.

    226 When FWA must terminate an enterprise agreement

    If an application for the termination of an enterprise agreement is made under section 225, the FWC must terminate the agreement if:

      (a) the FWC is satisfied that it is not contrary to the public interest to do so; and
      (b) the FWC considers that it is appropriate to terminate the agreement taking into account all the circumstances including:

        (i) the views of the employees, each employer, and each employee organisation (if any), covered by the agreement; and
        (ii) the circumstances of those employees, employers and organisations including the likely effect that the termination will have on each of them.

    227 When termination comes into operation

    If an enterprise agreement is terminated under section 226, the termination operates from the day specified in the decision to terminate the agreement.”

[5] This application was accompanied by a statutory declaration of Ms Jenna Cuthbertson, Regional HR Manager – WA/SA/NT, which addressed the relevant criteria established by s.226 of the FW Act.

[6] Ms Cuthbertson has confirmed to the Commission that the Agreement does not cover any employee and there are no circumstances where any employee would be covered by the Agreement in the future. This arises, for the most part, from the acquisition of the employer by another business and changes in, or conclusion of, the project activity concerned.

[7] I am satisfied that the termination of the Agreement would not be contrary to the public interest. I am also satisfied that the termination is appropriate having regard to the likely effect of that action and the circumstances of the employees and the employer.

[8] The termination will take effect from midnight on Friday 12 February 2016.

COMMISSIONER

 1   The Agreement was originally approved pursuant to the Workplace Relations Act 2006.

 2 Item 2(5)(c)(i) of Schedule 3.

Printed by authority of the Commonwealth Government Printer