Land and Environment Court
New South Wales
Medium Neutral Citation: SK Group Properties Pty Ltd v Bayside Council [2024] NSWLEC 1834 Hearing dates: Conciliation conference held 19 July, 16 August, 10, 30 September, 18 October, 8 and 15 November 2024 Date of orders: 20 November 2024 Decision date: 20 November 2024 Jurisdiction: Class 1 Before: Pullinger AC Decision: The Court orders that:
(1) Leave is granted to the Applicant to amend Development Application DA-2023/225 and rely upon the amended plans and documents referred to in Condition 1 at Annexure A.
(2) Pursuant to s 8.15(3) of the Environmental Planning and Assessment Act 1979, the Applicant is to pay the Respondent’s costs thrown away as a result of amending the Development Application in the agreed sum of $35,000 within 28 days of the date of these orders.
(3) The Applicant’s written request, pursuant to cl 4.6 of the Bayside Local Environmental Plan 2021 (BLEP), seeking to vary the development standard for height of buildings as set out at cl 4.3 of the BLEP, is upheld.
(4) The Applicant’s written request, pursuant to cl 4.6 of the BLEP, seeking to vary the development standard for floor space ratio (FSR) as set out at cl 4.4 of the BLEP, is upheld.
(5) The appeal is upheld.
(6) Consent is granted to Development Application DA-2023/225 (as amended) for the demolition of existing structures and construction of a mixed-use (shop top housing) development including commercial premises on the ground level, infill affordable housing (Level 1), residential units (Levels 2-8) and two levels of basement parking, at 609 Gardeners Road, Mascot, subject to the conditions of consent at Annexure A.
Catchwords: DEVELOPMENT APPLICATION – mixed use development – shop top housing – residential apartment building – cl 4.6 written request – height of buildings – floor space ratio – agreement between the parties – orders
Legislation Cited: Environmental Planning and Assessment Act 1979, ss 4.15, 4.16, 8.7, 8.15
Land and Environment Court Act 1979, s 34
Environmental Planning and Assessment Regulation 2021, ss 27, 29, 37, 38
State Environmental Planning Policy (Housing) 2021 Chs 2, 4, Pt 2, Div 1, Sch 7A, 9, ss 8, 18, 145, 147
State Environmental Planning Policy (Resilience and Hazards) 2021, s 4.6
State Environmental Planning Policy (Sustainable Buildings) 2022, s 2.1
State Environmental Planning Policy (Transport and Infrastructure) 2021, ss 2.119, 2.120
Bayside Local Environmental Plan 2021, cll 2.3, 2.7, 4.3, 4.4, 4.6, 6.1, 6.2, 6.3, 6.7, 6.8, 6.9, 6.10, 6.11
Cases Cited: Texts Cited: Australian Standard AS 2021:2015 Acoustics - Aircraft Noise Intrusion - Building Siting and Construction
NSW Department of Planning, Apartment Design Guide (2015)
NSW Department of Planning and Environment, Planning Circular PS 20-002, May 2020
Category: Principal judgment Parties: SK Group Properties Pty Ltd (Trustee of SK Group Property Trust) (Applicant)
Bayside Council (Respondent)Representation: Counsel:
A Knox (Solicitor) (Applicant)
P Brown (Solicitor) (Respondent)
Solicitors:
Pikes and Verekers Lawyers (Applicant)
HWL Ebsworth Lawyers (Respondent)
Keep reading for free
Create a free CaseChat account to read SK Group Properties Pty Ltd v Bayside Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NSWLEC 1834
- Decision Date
CaseChat Overview and Summary
The legal issues that the Court had to decide included whether the Applicant had the right to amend the development application under the Act, whether the requests to vary the development standards were valid, and if the proposed development complied with the relevant planning legislation and local plan. Additionally, the Court had to consider whether the Applicant’s requests for variations were within the scope of the Local Environmental Plan and whether the proposed development met the objectives and criteria of the plan. The Court also needed to address whether the Applicant should be required to pay costs incurred by the Respondent due to the amendment of the development application.
In its reasoning, the Court found that the Applicant had the right to amend the development application, and the requests for variation of the development standards were valid. The Court held that the proposed development was consistent with the objectives and criteria of the Bayside Local Environmental Plan 2021. The Court concluded that the Applicant’s requests to vary the height of buildings and the floor space ratio were justified under the relevant provisions of the Local Environmental Plan. Furthermore, the Court determined that the Applicant should bear the costs incurred by the Respondent due to the amendment of the development application. Consequently, the Court granted the Applicant's requests, allowed the appeal, and granted consent to the amended development application subject to specified conditions.
Orders
Orders of the court
The Court orders that:
(1) Leave is granted to the Applicant to amend Development Application DA-2023/225 and rely upon the amended plans and documents referred to in Condition 1 at Annexure A.
(2) Pursuant to s 8.15(3) of the Environmental Planning and Assessment Act 1979, the Applicant is to pay the Respondent’s costs thrown away as a result of amending the Development Application in the agreed sum of $35,000 within 28 days of the date of these orders.
(3) The Applicant’s written request, pursuant to cl 4.6 of the Bayside Local Environmental Plan 2021 (BLEP), seeking to vary the development standard for height of buildings as set out at cl 4.3 of the BLEP, is upheld.
(4) The Applicant’s written request, pursuant to cl 4.6 of the BLEP, seeking to vary the development standard for floor space ratio (FSR) as set out at cl 4.4 of the BLEP, is upheld.
(5) The appeal is upheld.
(6) Consent is granted to Development Application DA-2023/225 (as amended) for the demolition of existing structures and construction of a mixed-use (shop top housing) development including commercial premises on the ground level, infill affordable housing (Level 1), residential units (Levels 2-8) and two levels of basement parking, at 609 Gardeners Road, Mascot, subject to the conditions of consent at Annexure A.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.