Supreme Court
New South Wales
Medium Neutral Citation: Shoal Bay Developments Pty Ltd v Registrar-General of NSW [2021] NSWSC 764 Hearing dates: 24 June 2021 Date of orders: 24 June 2021 Decision date: 24 June 2021 Jurisdiction: Equity Before: Darke J Decision: Orders made to effect a severance of land from a community scheme.
Catchwords: LAND LAW – Community title – all interested parties consent to variation of community scheme – the Court must be satisfied that completion of staged scheme or continuation of scheme is impracticable – community scheme planned to proceed in three stages – a wick drainage system was installed inconsistently with development consent during stages one and two – not practically feasible to physically rectify wick drainage system – unsuccessful attempt to modify development consent in relation to drainage system – development of stage three unable to be undertaken in a way that complies with development consent – held that the completion and continuation of scheme impracticable – orders made varying the scheme
Legislation Cited: Community Land Development Act 1989 (NSW), ss 70(1)(a), 70(1)(b), 71
Community Land Management Act 1989 (NSW), s 15, Schedule 2
Cases Cited: Community Association DP270212 v Registrar-General [2004] NSWSC 961
Neighbourhood Association DP 285249 v Watson [2008] NSWSC 876
Category: Principal judgment Parties: Shoal Bay Developments Pty Ltd (First Plaintiff/First Cross-Defendant)
Snoogal Pty Ltd (Second Plaintiff/Second Cross-Defendant)
Registrar General of NSW (First Defendant/Third Cross-Defendant)
Community Association DP 270468 (Second Defendant/Cross-Claimant)
Port Stephens Council (Third Defendant/Fourth Cross-Defendant)Representation: Counsel:
Solicitors:
Mr N Eastman with Mr J Farrell (Plaintiffs/First and Second Cross-Defendants)
Mr S Prent, solicitor (First Defendant/Third Cross-Defendant)
Mr G Farland (Second Defendant/Cross-Claimant)
Mr R Boadle (Third Defendant/Fourth Cross-Defendant)
David A Vitnell (Plaintiffs/First and Second Cross-Defendants)
Office of the Registrar-General of NSW (First Defendant/Third Cross-Defendant)
JS Mueller & Co Lawyers (Second Defendant/Cross-Claimant)
Local Government Legal (Third Defendant/Fourth Cross-Defendant)
File Number(s): 2019/373618 Publication restriction: None
Judgment – EX TEMPORE
-
These proceedings concern the land contained in Deposited Plan 270468. The land is located in the vicinity of Nelson Bay, and forms part of the development known as the Lagoons Estate. Deposited Plan 270468, which was registered on 1 February 2006, effected a subdivision of land pursuant to a community plan within the meaning of the Community Land Development Act 1989 (NSW) (“the Act”). A community development contract was registered with the community plan subdivision. It is a development contract within the meaning of the Act.
-
The development contract provides for a proposed staged development of the land in accordance with a development consent granted by order of the Land and Environment Court on 3 December 2021. That consent has been the subject of modifications in 2005 and 2013. The consent, as originally made and as modified, required the construction of what is described as a wick drainage system.
-
The plaintiffs are the owners of Lot 114 in Deposited Plan 270468 (“Lot 114”). Lot 114 was intended to be developed as part of Stage 3 of the development. That has not occurred. Lot 114…
Keep reading for free
Create a free CaseChat account to read Shoal Bay Developments Pty Ltd v Registrar-General of NSW and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] NSWSC 764
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the completion and continuation of the community scheme was impracticable, given the developer's inability to rectify the inconsistencies with the development consent and the associated difficulties in obtaining consent modifications. The court needed to balance the interests of the developer, the community title owners, and the public interest in ensuring that developments comply with approved consents.
The court found that the completion and continuation of the scheme was impracticable. The inconsistencies with the development consent could not be physically rectified, and the developer had been unable to modify the consent to accommodate the deviations. Furthermore, the development of stage three could not be undertaken in a way that complied with the development consent. The court was satisfied that the scheme could not be completed or continued in a manner that adhered to the approved consents, making it impracticable to do so.
The court made orders varying the community scheme to reflect the impracticability of completing and continuing the scheme in accordance with the approved development consent. The variation allowed for the continuation of the community title development despite the inconsistencies with the development consent.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi