Sherrin Hire Pty Ltd v Tidd Ross Todd Ltd

Link copied
Case Copied 14 min read

FEDERAL COURT OF AUSTRALIA

Sherrin Hire Pty Ltd v Tidd Ross Todd Ltd [2014] FCA 939

Citation: Sherrin Hire Pty Ltd v Tidd Ross Todd Ltd [2014] FCA 939
Parties: SHERRIN HIRE PTY LTD (ABN 45 007 741 942) v TIDD ROSS TODD LTD, TRT (AUST) PTY LTD, PANALAM TECHNOLOGIES LIMITED and AROTAHI TRADING LIMITED
File number: NSD 379 of 2014
Judge: EDMONDS J
Date of judgment: 2 September 2014
Catchwords: PRACTICE AND PROCEDURE – applicant purchased elevated working platforms – elevated working platforms developed structural defects – originating application filed against architects and designers more than six years after first noticing defect – limitations period for negligence – when cause of action in negligence first accrued – application for summary judgment pursuant to s 31A of Federal Court Rules – whether no reasonable prospect of success
Legislation: Federal Court of Australia Act 1976 (Cth) s 31A
Limitation of Actions Act 1974 (Qld) s 10(1)(a)
Limitation Act 1969 (NSW) s 14(1)(b)
Federal Court Rules 2011
Cases cited: Christie v Purves & Ors [2007] NSWCA 182 cited
Cyril Smith & Associates Pty Ltd v The Owners – Strata Plan No  64970 [2011] NSWCA 181 cited
Dey v Victorian Railways Commissioners (1949) 78 CLR 62 cited
General Steel Industries Inc v Commissioner for Railways (NSW) (1964) 112 CLR 125 cited
Hawkins v Clayton (1988) 164 CLR 539 cited
Pullen v Gutteridge Haskins & Davey Pty Ltd [1993] 1 VR 27 followed
Spencer v The Commonwealth (2010) 241 CLR 118 cited
White Industries Aust Ltd v Federal Commissioner of Taxation (2007) 160 FCR 298 cited
Date of hearing: 14 August 2014
Place: Sydney
Division: GENERAL DIVISION
Category: CATCHWORDS
Number of paragraphs: 30
Counsel for the Applicant: Mr F Corsaro SC with Ms JA Wright
Solicitor for the Applicant: TressCox Lawyers
Counsel for the Respondents: Mr R Wilson SC
Solicitor for the Respondents: Coleman Greig

IN THE FEDERAL COURT OF AUSTRALIA

NEW SOUTH WALES DISTRICT REGISTRY

GENERAL DIVISION

NSD 379 of 2014

BETWEEN:

SHERRIN HIRE PTY LTD (ABN 45 007 741 942)
Applicant

AND:

TIDD ROSS TODD LTD
First Respondent

TRT (AUST) PTY LTD
Second Respondent

PANALAM TECHNOLOGIES LIMITED
Third Respondent

AROTAHI TRADING LIMITED
Fourth Respondent

JUDGE:

EDMONDS J

DATE OF ORDER:

2 SEPTEMBER 2014

WHERE MADE:

SYDNEY

THE COURT ORDERS THAT:

1.The interlocutory application dated 20 June 2014 be dismissed.

2.The first and second respondents pay the applicant’s costs as agreed or taxed.

Note:    Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.


IN THE FEDERAL COURT OF AUSTRALIA

NEW SOUTH WALES DISTRICT REGISTRY

GENERAL DIVISION

NSD 379 of 2014

BETWEEN:

SHERRIN HIRE PTY LTD (ABN 45 007 741 942)
Applicant

AND:

TIDD ROSS TODD LTD
First Respondent

TRT (AUST) PTY LTD
Second Respondent

PANALAM TECHNOLOGIES LIMITED
Third Respondent

AROTAHI TRADING LIMITED
Fourth Respondent

JUDGE:

EDMONDS J

DATE:

2 SEPTEMBER 2014

PLACE:

SYDNEY

REASONS FOR JUDGMENT

INTRODUCTION

  1. By interlocutory application dated 20 June 2014 the first and second respondents seek the following orders:

    (1)A declaration that…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Sherrin Hire Pty Ltd v Tidd Ross Todd Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] FCA 939
Decision Date

CaseChat Overview and Summary

The case of Sherrin Hire Pty Ltd v Tidd Ross Todd Ltd involved a dispute between the applicant, Sherrin Hire Pty Ltd, and the respondents, Tidd Ross Todd Ltd, regarding the purchase of elevated working platforms (ewps) that developed structural defects. The matter was brought before the Federal Court of Australia, where the respondents sought a declaration that the applicant's proceedings were statute-barred and an order dismissing the proceedings against them.

The primary legal issues before the court were whether the applicant's cause of action accrued within the limitation period and if there was no reasonable prospect of success for the applicant's proceedings. The court had to determine when the cause of action in negligence first accrued, which would determine whether the statutory limitation period had expired. The court also had to decide whether the application for summary judgment under section 31A of the Federal Court Rules should be dismissed or granted.

The court found that the applicant's proceedings were not statute-barred as the cause of action in negligence did not accrue until the applicant had sufficient knowledge of the structural defects in the ewps. The court determined that the cause of action accrued when the applicant had sufficient knowledge of the defects and the likely cause of those defects, which was in September/October 2008 when the applicant engaged a third party to investigate the causes of the cracking. The court held that the applicant's cause of action accrued after the limitation period had expired, but the proceedings were not statute-barred as the applicant did not have sufficient knowledge of the defects until after the limitation period had expired. The court also found that there was a reasonable prospect of success for the applicant's proceedings.

The court dismissed the interlocutory application and ordered the respondents to pay the applicant's costs as agreed or taxed. The court held that the applicant's proceedings were not statute-barred and that there was a reasonable prospect of success for the applicant's proceedings. The court's decision provided clarity on the issue of when the cause of action in negligence accrues and the application of the limitation period in cases involving structural defects in products.

Orders

Orders of the court

1. The interlocutory application dated 20 June 2014 be dismissed.

2. The first and second respondents pay the applicant’s costs as agreed or taxed.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

By interlocutory application dated 20 June 2014 the first and second respondents seek the following orders:(1)A declaration that the whole of the proceedings brought by the applicant are statute-barred pursuant to:(a)Section 10(1)(a) of the Limitation of Actions Act 1974 (Qld) and/or(b)section 14(1)(b) of the Limitation Act 1969 (NSW).(2)An order that the proceedings be dismissed as against the first, second respondents (“TRT”).PROCEDURAL BACKGROUND These proceedings, commenced by the applicant’s originating application and statement of claim (“SOC”), were filed on 14 April 2014. In the SOC the applicant seeks damages for defects in certain elevated work platforms (“ewps”). A total of 79 ewps were purchased by the applicant from the respondents to proceedings NSD 1981/2011 (“Sherrin entities”). It is alleged by the applicant in these proceedings (para 24 of the SOC) that TRT was the “primary designer”, the “primary manufacturer” and the “assembler” of the ewps (para 6 of the SOC) and TRT owed the applicant a duty to ensure that each of the ewps –(1)was designed, manufactured and/or assembled with due care and skill;(2)was fit for the purpose for which it was required;(3)was sufficiently robust to cope with reasonable operating conditions in the field; and(4)met the Sherrin Entities’ Performance Criteria (para 11 of the SOC). The defects are pleaded at para 21 of the SOC in the following terms:The Platforms on the [ewps] are defective in that:(a)they have glass-reinforced plastic (“GRP”) components that are too fragile and unsuitable for use in overhead power line work due to:(i)the moulding process resulting in the GRP having insufficient glass fibres and a heavy build of brittle, unreinforced resin underneath the fibreglass outer sheath;(ii)insufficient thickness of the top and bottom faces of the fly-boom and uneven distribution of the glass fibre around the cross-section perimeter, making the fly-boom too weak in torsion;(b)they have cracking and delamination of the insulating coating due to poorly detailed design of the cover insulation, poor selection of materials (including foam materials and filler used to build up the wall thickness of the fly boom) and poor application techniques;(c)they have cracking at the transition between the lower boom insert and the steel boom sections due to the outer sheath being too thin and, therefore, deflecting more than the insulating insert;(d)they have poor surface preparation of the steel substrate for the application of the insulating insert in the lower boom assemblies;(e)they have large cracks in the fly-booms caused at least in part by the bucket folding down too far in the stow position – a problem exacerbated by the failure to provide an engineering control, such as an interlock, to prevent incorrect levelling of the platform when it is lowered on to the deck (notwithstanding the requirement for such engineering controls imposed by workplace health and safety regulations across Australia);(f)the ribs of the top rim of the baskets have cracks and openings and discontinuities in the glue line between the ribs and the basket, creating voids that track water;(g)the caulking filler used in the basket and applied around the nylon ferrules fitted to the ribs of the basket has not bonded and is offering a path for water ingress;(h)the basket has holes drilled through the ribs to support hydraulic components, the fall arrest attachment and fall arrest lanyard, which permit water ingress; and(i)they have a boom/jacking interlock fault in that the booms can be deployed when the stabilizer controls are set to “legs” and two functions of the Danfoss control levels are operated simultaneously(collectively “the Defects”).

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

It is difficult, if not impossible, and arguably not utile to articulate the distinction in point of principle between the “no reasonable prospects” test and the test in General Steel; certainly, this is not the occasion for it. Sub-section 31A(3) makes it clear that a proceeding or part of a proceeding need not be hopeless or bound to fail for it to have no reasonable prospects of success. If I am satisfied that, by reason of the statutory limitation provisions these proceedings have no reasonable prospects of success, then I will accede to TRT’s application for dismissal of them; if not, I will dismiss TRT’s interlocutory application.CONSIDERATIONRelevant Facts The “Defects” pleaded in the sub-paras of para 21 of the SOC are of two kinds: a number plead a physical defect of ‘cracking”; one or two plead physical defects of “openings”, “discontinuities” and “paths for water ingress”; but all plead either design or manufacturing defects, or what are called “latent defects”. The alleged breach of duty of care in para 25 of the SOC is framed by reference to the latent defects namely, those “Defects” in the ewps at the time of their acquisition by the applicant due to the alleged failure of the “Designer/Manufacturer” to design and manufacture the ewps so as to ensure that the ewps did not have those “Defects”. It is not in dispute that physical defects in the form of cracks were first discovered by the applicant in at least a small number of ewps in late 2006. Between around late 2006 and around late 2007/early 2008, the applicant observed a number of instances of cracking across various ewps which led to it making inquiries of the Sherrin Entities and/or TRT in relation to those. In response, the Sherrin Entities and/or TRT informed the applicant that:(1)The cracking was superficial or cosmetic and not a structural problem; and(2)consequently the recommended method for repairing the cracking was simply to patch repair the cracks. TRT submitted, fairly in my view, that it cannot be said that by 14 April 2008 (six years before this proceeding commenced) the evidence of these physical defects in the ewps was merely “negligible”. It was not until around September/October 2008 that the frequency of cracking across a number of units within the applicant’s fleet of ewps led the management of the applicant to become concerned that the cracking may be occurring as a consequence of a design or manufacturing issue. At or around this time and as a result of these concerns, the applicant engaged a third party, GHD, to investigate the causes of the cracking. GHD provided the applicant with the findings of its preliminary investigations in two reports titled “Report for Investigation of Cracking of Travel Towers” dated January 2009 and “Investigation into Cracking of Fly Jib Boom” dated February 2009. The GHD reports suggested for the first time that the cause of the cracking was likely a structural problem due to defective design and/or manufacture.