Shao v AG Advanced Construction Pty Ltd

Link copied
Case Copied 29 min read

SUPREME COURT OF VICTORIA

COURT OF APPEAL

S APCI 2018 0046

WENLI SHAO Applicant
v
AG ADVANCED CONSTRUCTION PTY LTD (ACN 089 153 597) Respondent

---

JUDGES: WHELAN, KYROU and McLEISH JJA
WHERE HELD: MELBOURNE
DATE OF HEARING: 25 February 2019
DATE OF JUDGMENT: 30 April 2019
MEDIUM NEUTRAL CITATION: [2019] VSCA 93
JUDGMENT APPEALED FROM: [2018] VSC 116 (Daly AsJ)

---

BUILDING AND CONSTRUCTION – Major domestic building contract – Termination by owner under Domestic Building Contracts Act 1995 s 41 – Builder entitled to reasonable price – Defects – Whether termination under s 41 extinguishes damages claim for defective work – Shevill v Builders Licensing Board (1982) 149 CLR 620; McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457, applied – Whether costs of rectifying defects to be calculated in builder’s reasonable price under s 41(5) – Builder paid more than reasonable price – Whether owner entitled to refund – Domestic Building Contracts Act 1995 s 53(2)(b) and (f).

ADMINISTRATIVE LAW – Appeals – Victorian Civil and Administrative Tribunal Act 1998, s 148 – Appeal allowed – Whether to exercise power of Tribunal to order refund – Whether to remit proceeding to Tribunal – Victorian Civil and Administrative Tribunal Act 1998 s 148(7)(b) and (c).

---

APPEARANCES: Counsel Solicitors
For the Applicant Mr R Andrew Oldham Naidoo Lawyers
For the Respondent Mr P D Corbett QC with
Mr C M Fenwick
Portfolio Law

WHELAN JA

KYROU JA
McLEISH JA:

  1. Section 41 of the Domestic Building Contracts Act 1995 (‘the Act’) gives a building owner the right to end a major domestic building contract if that contract has not been completed within one and a half times the period during which it was required to have been completed.  The right arises if the reason for the increased time was something that could not have been reasonably foreseen by the builder when the contract was made.  If the owner exercises this right, the builder is entitled under the section to a reasonable price for the work carried out to that point.

  1. The present appeal concerns the rights of the building owner who gives notice under the section and, in particular, the relationship between the builder’s statutory right of recovery and any statutory or contractual claim the owner might have for damages by reason of defects in the building work. 

  1. The applicant seeks leave to appeal from orders made in favour of the respondent builder by an associate judge in the Trial Division.  By those orders, the associate judge allowed an appeal from orders made by the Victorian Civil and Administrative Tribunal (‘the Tribunal’) and set aside an order that the respondent pay to the applicant the sum of $93,153.  The associate judge declined to make further orders in respect of the fact that the applicant had paid the respondent an amount exceeding the ‘reasonable price’ the Tribunal had assessed.

  1. For reasons set out below, leave to appeal should be granted and the appeal should be allowed so that…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Shao v AG Advanced Construction Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] VSCA 93
Decision Date

CaseChat Overview and Summary

The case of Shao v AG Advanced Construction Pty Ltd was before the Supreme Court of Victoria. The plaintiff, Shao, engaged AG Advanced Construction to construct a house. Disputes arose over the quality of the work, leading to Shao terminating the contract under the Domestic Building Contracts Act 1995. Shao sought damages for defects and a refund for overpayment. The builder, AG Advanced Construction, argued that the termination extinguished the damages claim and that the costs of rectifying defects should be considered in calculating the reasonable price.

The central legal issues were whether the termination under section 41 of the Act extinguished the damages claim for defective work and whether the costs of rectifying defects should be included in the reasonable price calculation under section 41(5). Additionally, the court had to determine if Shao was entitled to a refund for overpayment under section 53(2)(b) and (f) of the Act. Furthermore, the court considered whether to exercise its power under the Victorian Civil and Administrative Tribunal Act 1998 to order a refund or remit the proceeding back to the Tribunal.

The court found that the termination under section 41 of the Act did not extinguish the damages claim for defective work. It applied the principles from Shevill v Builders Licensing Board and McDonald v Dennys Lascelles Ltd to conclude that the termination did not preclude the damages claim. The court also ruled that the costs of rectifying defects should not be included in the reasonable price calculation under section 41(5). As the builder was paid more than the reasonable price, Shao was entitled to a refund under section 53(2)(b) and (f) of the Act. The Supreme Court allowed the appeal, ordering a refund to Shao, and did not remit the proceeding to the Tribunal.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.