Selkirk v The Owners - Strata Plan No 2661

Link copied
Case Copied 107 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Selkirk v The Owners – Strata Plan No 2661 [2024] NSWCATCD 71
Hearing dates: 27 June 2024, last submissions received 23 August 2024
Date of orders: 30 December 2024
Decision date: 30 December 2024
Jurisdiction:Consumer and Commercial Division
Before: D Robertson, Principal Member
Decision:

(1) Pursuant to s 106(5) of the Strata Schemes Management Act 2015 (NSW) (the Act) order the respondent to pay the applicant $98,374.29 compensation for breach of s 106 of the Act within 28 days of the date of this decision.

(2) Pursuant to s 232 of the Act, direct that the respondent is not to pay any compensation awarded to the applicant from levies to which the applicant has been required to contribute.

(3) Pursuant to s 232 of the Act, direct the respondent, within two months of the date of this decision, to engage a suitably experienced, qualified, licensed and insured contractor to undertake repairs to the brick walls in the bathroom of Lot 5 in Strata Plan No 2661 sufficient to ensure that tiling and/or a waterproof membrane can be applied to the walls.

(4) Pursuant to s 232 of the Act, direct the respondent, within two months of the date of this decision, to engage a suitably experienced, qualified, licensed and insured contractor to carry out investigations in relation to the kitchen side of the wall dividing the kitchen from the bathroom of lot 5 in Strata Plan No 2661 with a view to determining the nature and causation of any defects in that wall and devising an appropriate rectification scope.

(5)   Each party may file, and serve upon the other party, submissions of no more than five pages, with any evidence in support, seeking orders in relation to the costs of the proceedings (including costs incurred in relation to the proceedings before Senior Member Tyson) within 28 days of the publication of these orders.

(6)   Each party may file and serve submissions in response to submissions filed pursuant to order (5) above, of no more than five pages, with any evidence in support, within a further 14 days.

(7)   Submissions in reply to submissions filed and served pursuant to Order (6) above, of no more than three pages, may be filed and served within a further 7 days.

(8) Any submissions filed pursuant to Orders (5) or (6) above must include submissions concerning whether an order should be made pursuant to s 50 of the Civil and Administrative Tribunal Act 2013 (NSW) dispensing with a hearing of the relevant application.

(9)   If any submissions are filed pursuant to Orders (5) to (7) above, the parties are to prepare and provide to the Tribunal an indexed, tabbed and paginated bundle containing all submissions and evidence filed pursuant to those orders within 56 days of the publication of these orders.

Catchwords:

LAND LAW – strata title – duties of owners corporation – duty to maintain and repair common property – claims for…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Selkirk v The Owners - Strata Plan No 2661 and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] NSWCATCD 71
Decision Date

CaseChat Overview and Summary

The case of Selkirk v The Owners - Strata Plan No 2661 involved a dispute between the applicant, a lot owner, and the owners corporation, regarding the maintenance and repair of common property. The applicant sought compensation for the breach of the duty to maintain and repair common property, as well as directions for the owners corporation to undertake specific rectification works. The dispute was heard and determined by the Civil and Administrative Tribunal in New South Wales.

The key legal issues before the Tribunal were whether the applicant’s losses were reasonably foreseeable as a result of the owners corporation’s contravention of its duty under section 106 of the Strata Schemes Management Act 2015 (NSW). Additionally, the Tribunal had to determine whether the applicant’s actions in proceeding with works affecting the common property without the approval of the owners corporation had the consequence that subsequent losses were not suffered as a result of the owners corporation’s contravention of section 106.

The Tribunal held that the applicant’s losses were indeed reasonably foreseeable as a result of the owners corporation’s contravention of its duty under section 106. The Tribunal found that the lot owner’s raising of justifiable objections to the owners corporation’s proposed repair works did not amount to an explicit refusal of access, and therefore did not mean that the losses sustained by the lot owner were not suffered as a result of the owners corporation’s contravention of section 106. However, the Tribunal also found that the lot owner’s actions in proceeding with works affecting the common property without the approval of the owners corporation did have the consequence that subsequent losses were not suffered as a result of the owners corporation’s contravention of section 106. The Tribunal subsequently ordered the owners corporation to pay the applicant $98,374.29 in compensation for the breach of section 106, and directed the owners corporation to engage a suitably experienced, qualified, licensed and insured contractor to undertake specific rectification works.

Orders

Orders of the court

(1) Pursuant to s 106(5) of the Strata Schemes Management Act 2015 (NSW) (the Act) order the respondent to pay the applicant $98,374.29 compensation for breach of s 106 of the Act within 28 days of the date of this decision.

(2) Pursuant to s 232 of the Act, direct that the respondent is not to pay any compensation awarded to the applicant from levies to which the applicant has been required to contribute.

(3) Pursuant to s 232 of the Act, direct the respondent, within two months of the date of this decision, to engage a suitably experienced, qualified, licensed and insured contractor to undertake repairs to the brick walls in the bathroom of Lot 5 in Strata Plan No 2661 sufficient to ensure that tiling and/or a waterproof membrane can be applied to the walls.

(4) Pursuant to s 232 of the Act, direct the respondent, within two months of the date of this decision, to engage a suitably experienced, qualified, licensed and insured contractor to carry out investigations in relation to the kitchen side of the wall dividing the kitchen from the bathroom of lot 5 in Strata Plan No 2661 with a view to determining the nature and causation of any defects in that wall and devising an appropriate rectification scope.

(5) Each party may file, and serve upon the other party, submissions of no more than five pages, with any evidence in support, seeking orders in relation to the costs of the proceedings (including costs incurred in relation to the proceedings before Senior Member Tyson) within 28 days of the publication of these orders.

(6) Each party may file and serve submissions in response to submissions filed pursuant to order (5) above, of no more than five pages, with any evidence in support, within a further 14 days.

(7) Submissions in reply to submissions filed and served pursuant to Order (6) above, of no more than three pages, may be filed and served within a further 7 days.

(8) Any submissions filed pursuant to Orders (5) or (6) above must include submissions concerning whether an order should be made pursuant to s 50 of the Civil and Administrative Tribunal Act 2013 (NSW) dispensing with a hearing of the relevant application.

(9) If any submissions are filed pursuant to Orders (5) to (7) above, the parties are to prepare and provide to the Tribunal an indexed, tabbed and paginated bundle containing all submissions and evidence filed pursuant to those orders within 56 days of the publication of these orders.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.