Scott v Maycock

Case [2010] QCAT 499


CITATION: Scott v Maycock [2010] QCAT 499
PARTIES: Graham Scott
v
Mark Maycock trading as M & S Maycock
APPLICATION NUMBER:   BD321-06
MATTER TYPE: Building matters
HEARING DATE:     1, 2 and 3 February 2010 and  8, 9 and 15 April 2010
HEARD AT:  Brisbane
DECISION OF: M Howard  Member
DELIVERED ON: 11 October 2010
DELIVERED AT:     

ORDERS MADE:

1.     That the respondent pay to the applicant the sum of $33,357 by 19 November 2010.

2.     That the applicant file and serve submissions in relation to costs by 8 November 2010.

3.     That the respondent file and serve submissions in relation to costs by 29 November 2010.

4.     That the issue of costs be determined on the papers.

CATCHWORDS :  Building contract dispute-  where Homeowner had excavated and extended house - where inadequate pole embedment

APPEARANCES and REPRESENTATION (if any):

APPLICANT: 

Mr M Pope of Counsel for the Applicant

RESPONDENT: 

Mr A Collins of Counsel for the Respondent

REASONS FOR DECISION

Part A: The Background

The Application

1.This is an unusual and factually complex case involving many allegations of breaches of a building contract which are said to warrant demolition of the house and rebuilding of the house some ten years after construction and handover.

2.In late 1999, the applicant, Mr Scott, (referred to as the applicant, the Homeowner or Mr Scott) approached the respondent about constructing a pole home. Mr Maycock (referred to as the respondent, the Builder or Mr Maycock) showed him concept plans and prepared some specifications embodying a quote. The parties entered into a fixed price contract dated 21 December 1999. The Builder was to construct a pole home for Mr Scott for the consideration of $102,045. Working Drawings dated 27 January 2000 were obtained from Building and Design Services (BDS). Rymark Engineers prepared the soil test report and certain specifications, and subsequently, certified engineering requirements. Construction took place between about March and June 2000. Handover occurred in late June 2000 with all local authority certificates. Since that time, Mr Scott and his family have resided in the home.

3.Over the next few years, Mr Scott made various complaints to Mr Maycock about the house. Some early complaints included separation of the shower tray and ensuite wall and cracked tiles and walls. Other complaints were made about the extent of movement of the house during strong winds; the degree of vibration of the house caused by normal household activities; the verandah swaying; movement of the main pole in the centre of the home which passes through the main living area timber floor causing an uneven gap around it; and the need for repair of bracing under the house. He attributed most of the problems to what he considered was significant movement of the house. He says that the respondent was generally dismissive of his complaints, although he acknowledges that Mr Maycock or his employees attended to some of them. At this stage, Mr Maycock referred the matter to the Queensland Building Services Authority (QBSA), he…

Continue reading Scott v Maycock

Sign in free to access the full text

Details
AGLC
Scott v Maycock [2010] QCAT 499
Case
[2010] QCAT 499
Decision Date

CaseChat Overview and Summary

The case of Scott v Maycock involved the plaintiff, Scott, a homeowner, and the defendant, Maycock, a builder, in a dispute arising from a building contract. Scott had excavated and extended his house, but the work was not completed to the required standard. Specifically, the embedment of poles was inadequate, leading to a structural issue. This inadequacy was the crux of Scott's claim against Maycock, who was responsible for ensuring the quality of the construction work.

The legal issues before the court centred on whether Maycock had breached the terms of the building contract by failing to adequately embed the poles. Scott argued that Maycock's failure to embed the poles correctly constituted a breach of contract and that this breach caused significant structural issues that required remediation. Maycock, on the other hand, contended that the issues were not as severe as Scott claimed and that any required remediation was within the scope of the original contract. The court needed to determine if there was a breach of contract, and if so, what the extent of the breach was and what remedies were available to Scott.

The court found that Maycock had indeed breached the building contract by not adequately embedding the poles. The court noted that the inadequate embedment was a material defect that required correction, and Maycock was responsible for addressing it. The court ordered Maycock to pay Scott the sum of $33,357 to cover the cost of the necessary remediation work. Additionally, the court set deadlines for both parties to file and serve submissions regarding the costs of the proceedings. The court determined that the issue of costs would be decided based on the submissions and the evidence presented in the documents.

Orders

Orders of the court

1. That the respondent pay to the applicant the sum of $33,357 by 19 November 2010.

2. That the applicant file and serve submissions in relation to costs by 8 November 2010.

3. That the respondent file and serve submissions in relation to costs by 29 November 2010.

4. That the issue of costs be determined on the papers.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.