Scott t/as Fantasy Pools Brisbane v Schreiber

Link copied
Case Copied 13 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Scott t/as Fantasy Pools Brisbane v Schreiber & Anor [2022] QCAT 316

PARTIES:

Lupton scott trading as fantasy pools brisbane

(applicant)

V

rob schreiber
gem schreiber

(respondents)

APPLICATION NO/S:

BDL200-20

MATTER TYPE:

Building matters

DELIVERED ON:

30 August 2022

HEARING DATE:

24 August 2022

HEARD AT:

Brisbane

DECISION OF:

Member Cranwell

ORDERS:

1.     Rob Schreiber and Gem Schreiber are to pay Lupton Scott trading as Fantasy Pools Brisbane the amount of $15,447.94 within 28 days of the date of these orders.

2.     The counter-claim filed on 4 May 2021 is dismissed.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – REMEDIES FOR BREACH OF CONTRACT – where respondent has failed to pay applicant – where respondent claims work is defective – where lack of evidence of defective building work – where lack of evidence to establish damages

Marsh v Walter Iezzi Property Group [2021] QCAT 191

REPRESENTATION:

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)

Applicant:

Self-represented

Respondents:

Self-represented

REASONS FOR DECISION

  1. Mr Scott is a swimming pool builder who trades as Fantasy Pools Brisbane.

  2. Mr and Mrs Schreiber own a property in or near Gladstone.

  3. On 7 April 2019, Mr and Mrs Schreiber entered into a contract with Mr Scott for the construction of a swimming pool on their property.

  4. As is the case with matters that come before the Tribunal, the parties have not been able to reach agreement on certain aspects of the project.

  5. Mr Scott has lodged a claim for $11,592 in unpaid invoices, plus interest and costs.

  6. Mr and Mrs Schreiber have lodged a counter-claim for:

    Claim for Damages for Breach of Contract.  Fantasy Pools to pay the sum required for rectification of all deficiencies and damages caused by the process.  All required rectifications to be carried out by independent qualified contractors.

  7. I note at the outset that Mr and Mrs Schreiber have failed to quantify their damages, except insofar as they have provided a quote for replacing the pebble finish.

  8. I will proceed to separately examine the claim and counter-claim in turn.

Claim by Mr Scott

  1. The contract entered into between the parties provides for progress payments at certain stages.  Relevantly, the contract provides for the following payments:

    (a)Stage 5 (Completion of the internal lining and initial chemical treatment) – $20,627; and

    (b)Stage 6 (Practical Completion) – $1,000.

  2. Clause 11.7 and item 20 of the Schedule require the owner to pay progress claims within five business days of receiving a claim.

  3. Clause 11.8 provides that, subject to exceptions which are not presently relevant, the owner has no right to deduct any amount from a progress claim made under clause 11.7.

  4. Mr Scott’s evidence in his statement filed on 17 June 2020 is that the pebble interior and initial chemical treatment was completed on 21 August 2019.  While Mr and Mrs Schreiber have claimed that the work was defective, which…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Scott t/as Fantasy Pools Brisbane v Schreiber and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] QCAT 316
Decision Date

CaseChat Overview and Summary

Lupton Scott trading as Fantasy Pools Brisbane (the applicant) brought an application against Rob and Gem Schreiber (the respondents) for an amount of $11,592 in unpaid invoices, plus interest and costs. The respondents filed a counter-claim for damages for breach of contract. The matter was heard and determined on the papers. The contract entered into between the parties provides for progress payments at certain stages. The applicant completed the pebble interior and initial chemical treatment on 21 August 2019 and issued invoice 1671 for stage 5 in the amount of $20,627 on that date. The respondents paid $10,000 on or around 12 September 2019. The applicant issued invoice 1695 for stage 6 in the amount of $965 on 14 September 2019. The respondents have taken possession of the pool but have not made full payment of the contract price. The applicant is entitled to interest on the outstanding amounts. The respondents have not provided sufficient evidence to establish their counter-claim. Rob Schreiber and Gem Schreiber are ordered to pay Lupton Scott trading as Fantasy Pools Brisbane the amount of $15,447.94 within 28 days of the date of these orders. The counter-claim filed on 4 May 2021 is dismissed.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.