Schach v Dowdy Constructions Pty Ltd

Case

[2025] NSWCATCD 84

13 June 2025

No judgment structure available for this case.

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Schach v Dowdy Constructions Pty Ltd [2025] NSWCATCD 84
Hearing dates: On the papers
Date of orders: 13 June 2025
Decision date: 13 June 2025
Jurisdiction:Consumer and Commercial Division
Before: D Robertson, Principal Member
Decision:

(1)      The respondent pay the applicant’s costs thrown away by reason of the setting aside of the orders made on 19 February 2024, including the costs of and incidental to the hearing on that date, and the costs of and incidental to the respondent’s application to set aside those orders. Such costs to be as agreed or assessed.

(2)      The applicant’s application for costs is otherwise dismissed.

Catchwords:

COSTS – Proceedings resolved by consent orders – Application of Lai Qin principles

Legislation Cited:

Civil and Administrative Tribunal Act 2013 (NSW)

Civil and Administrative Tribunal Rules 2014 (NSW)

Cases Cited:

BCA Constructions Pty Ltd v Arsovski [2024] NSWCATAP 31

Bulloch v Linden Building Services Pty Ltd t/as Linden Constructions [2019] NSWCATAP 42

Nadilo v Eagleton [2021] NSWCA 232

Nichols v NFS Agribusiness Pty Ltd [2018] NSWCA 84

Re: Minister for Immigration & Ethnic Affairs; ex parte Lai Qin (1997) 186 CLR 622; [1997] HCA 6

Roberts v The Owners - Strata Plan No 4393 [2023] NSWCATAP 119

Category:Costs
Parties: Michael Schach (Applicant)
Dowdy Constructions Pty Ltd (Respondent)
Representation: Solicitors:
WMD Law (Applicant)
File Number(s): 2023/00393568 (formerly HB 23/23743)
Publication restriction: Nil

REASONS FOR DECISION

  1. The applicant commenced these proceedings on 23 May 2023 seeking orders requiring the respondent to make good three identified defects.

  2. The parties were given leave for legal representation. The applicant retained solicitors. The respondent was not at any time represented by solicitors before the Tribunal but apparently consulted solicitors “allocated” by the respondent’s indemnity insurers.

  3. The proceedings were listed for hearing on 19 February 2024. On that occasion the respondent failed to appear, and the hearing proceeded in its absence. Orders were made against the respondent requiring it to carry out work.

  4. The respondent filed an application to set aside the decision of 19 February 2024 on 19 March 2024. In that application Mr Matthew Dowdy, the director of the respondent, stated that the respondent did not receive the correspondence from the Tribunal notifying it of the hearing. The set aside application stated that notice of the hearing was sent to “our solicitors”. It is apparent from other documents on the file that the notice was in fact sent to the respondent’s registered office, which was the respondent’s accountant’s address, but apparently not passed on.

  5. On 22 April 2024 the Tribunal made orders setting aside the orders made on 19 February 2024.

  6. The proceedings were then listed for hearing before me on 22 August 2024. On that occasion orders were made by consent requiring the respondent to carry out works in accordance with details set out in a joint report of experts prepared for the purposes of the hearing.

  7. The orders also required the respondent to pay the applicant the amount of $10,000 in respect of accommodation costs for the period that the applicant was required to vacate the property to enable the work to be carried out, and a further $3,500 per week if the applicant was required to remain out of the premises for longer than three weeks.

  8. The orders provided for the parties to exchange submissions concerning the costs of the proceedings.

  9. The applicant filed submissions on 5 September 2024. The respondent filed submissions on 23 September 2024. The applicant filed submissions in reply on 3 October 2024.

  10. The applicant sought an order that the respondent pay his costs on the ordinary basis until up to 18 February 2024 and on the indemnity basis from 19 February 2024 to 22 August 2024. The applicant also sought interest on the costs he had paid. As the Tribunal does not have the power to award interest on costs, I will not further consider that part of the applicant’s submissions.

  11. The respondent opposed the orders sought and submitted that the appropriate order was that each party pay their own costs.

Relevant legislation

  1. Section 60 of the Civil and Administrative Tribunal Act 2013 (NSW) provides:

60 Costs

(1) Each party to proceedings in the Tribunal is to pay the party’s own costs.

(2) The Tribunal may award costs in relation to proceedings before it only if it is satisfied that there are special circumstances warranting an award of costs.

(3) In determining whether there are special circumstances warranting an award of costs, the Tribunal may have regard to the following-

(a) whether a party has conducted the proceedings in a way that unnecessarily disadvantaged another party to the proceedings,

(b) whether a party has been responsible for prolonging unreasonably the time taken to complete the proceedings,

(c) the relative strengths of the claims made by each of the parties, including whether a party has made a claim that has no tenable basis in fact or law,

(d) the nature and complexity of the proceedings,

(e) whether the proceedings were frivolous or vexatious or otherwise misconceived or lacking in substance,

(f) whether a party has refused or failed to comply with the duty imposed by section 36(3),

(g) any other matter that the Tribunal considers relevant.

(4) If costs are to be awarded by the Tribunal, the Tribunal may-

(a) determine by whom and to what extent costs are to be paid, and

(b) order costs to be assessed on the basis set out in the legal costs legislation (as defined in section 3A of the Legal Profession Uniform Law Application Act 2014) or on any other basis.

(5) In this section-

costs includes-

(a) the costs of, or incidental to, proceedings in the Tribunal, and

(b) the costs of, or incidental to, the proceedings giving rise to the application or appeal, as well as the costs of or incidental to the application or appeal.

  1. Rule 38 of the Civil and Administrative Tribunal Rules 2014 (NSW) provides:

38 Costs in Consumer and Commercial Division of the Tribunal

(1) This rule applies to proceedings for the exercise of functions of the Tribunal that are allocated to the Consumer and Commercial Division of the Tribunal.

(2) Despite section 60 of the Act, the Tribunal may award costs in proceedings to which this rule applies even in the absence of special circumstances warranting such an award if-

(a) the amount claimed or in dispute in the proceedings is more than $10,000 but not more than $30,000 and the Tribunal has made an order under clause 10(2) of Schedule 4 to the Act in relation to the proceedings, or

(b) the amount claimed or in dispute in the proceedings is more than $30,000.

Applicant’s submissions

  1. In summary, the applicant submitted:

  1. That the claim filed by the applicant was for an amount exceeding $30,000 and therefore rule 38 of the Civil and Administrative Tribunal Rules applied, and the successful party in the proceedings was entitled to an order for costs.

  2. Where proceedings are resolved without a hearing on the merits, there is no successful party, save for three “well established exceptions”, citing Re: Minister for Immigration & Ethnic Affairs; ex parte Lai Qin (1997) 186 CLR 622; [1997] HCA 6 (Lai Qin) at 624-625.

  3. One of those exceptions is where “both parties have acted reasonably, but a Court or Tribunal can be confident of the outcome or that a party would ‘almost certainly’ succeed.”

  4. This case falls into that category.

  5. Alternatively, a costs order may be justified pursuant to s 60 of the NCAT Act independently of the Lai Qin principles.

  6. Where s 60 applies, the Lai Qin principles “must give way to s 60 where they conflict with s 60 or where s 60 imports additional considerations or principles”, citing Roberts v The Owners - Strata Plan No 4393 [2023] NSWCATAP 119.

  7. A second exception under the Lai Qin principle is where one party has acted unreasonably, in respect of which “the Tribunal may have regard to known circumstances, not in dispute between the parties, without reviewing large swathes of evidence”, citing Nichols v NFS Agribusiness Pty Ltd [2018] NSWCA 84.

  1. The applicant set out, in paragraphs 20 to 33 of his submissions, facts which he submitted were “known circumstances which should not be in dispute”.

20   The Applicant and Respondent entered into a contract for works on 25 November 2016, Works were completed on 23 December 2017. Works included (but not limited to) renovations to the ensuite, main bathroom, balcony, awning, rear verandah, roof and installation of timber flooring.

21   In 2017/2018 remediation works were undertaken which were unsuccessful in preventing water ingress in various areas identified in the reports prepared by The Property Inspectors dated October 2023 and March 2024 and Awesim dated July 2024 and the joint report of August 2024.

22   In 2019 further remediation works were undertaken which were unsuccessful and damage from water ingress continued.

23   No works or proceedings were able to be commenced between 2020 and early 2021 due to the Covid-19 Pandemic.

24   In 2021, in response to a request by the Applicant that the Respondent attend to determine where the water ingress was coming from, the Respondent advised the Applicant to contact the Applicant’s insurer as he was unable to attend to undertake the remediation works.

25   Proceedings were commenced by the Applicant due to the failure of the Respondent to address the issues raised by him in relation to the water ingress.

26   In October 2023, the Respondent was served with the Report of The Property Inspectors, Emilio Calandro.

27   The Respondent did not file any evidence in reply apart from a number of emails without any context between himself and his insurer.

28   The Respondent did not participate in the First Proceedings or appear at the Hearing. The Applicant was successful in those proceedings, including in relation to costs.

29   The Respondent then filed the Set Aside Application contending that it was deprived of the ability to participate in, or defend the First Proceedings. It was successful.

30   A new Hearing date was allocated for 22 August 2024 (these proceedings) more than 15 months after the commencement of the proceedings.

31   As a result of the Set Aside Application, further directions were made giving the Respondent further time to file and serve expert material in reply and a direction that upon filing the expert evidence in reply, the parties were to provide a joint report.

32   The joint report identified seven (7) individual areas to be remediated:

(a)   Master Bedroom and Ensuite

(b)   Ensuite & Bathroom S bends

(c)   First Floor Timber Flooring

(d)   Main Bathroom

(e)   Roofing

(f)   External - Northern Wall

(g)   External - Back Veranda

33.   By the Hearing of these proceedings the Applicant had already incurred costs of the First Proceedings, the Set Aside Application and these proceedings.

  1. The applicant submitted that:

“[T]he respondent’s conduct before and after the commencement of these proceedings, was unreasonable and when taken as a whole, engages s 60(3)(b), (f) and (g) or the Tribunal’s general discretion in s 60(2)-(3).”

  1. The applicant identified three reasons why he submitted the respondent’s conduct was unreasonable:

  1. That the respondent “fundamentally refus[ed] to undertake any works to the property”, which the applicant submitted was “entirely analogous” to the example given by McHugh J in Lai Qin “where a defendant refuses to exercise power such that the ‘plaintiff had no reasonable alternative but to commence a litigation’”.

  2. That the respondent unreasonably prolonged the time taken to complete the proceedings - by failing to appear at the first hearing on 19 February 2024. The applicants submitted that, to the extent that the respondent’s failure to appear was due to default by its former solicitors, that was not a matter that would make it just that the applicant should bear the costs.

  3. That the respondent unreasonably defended the proceedings. The applicant submitted that the respondent consented to undertake works on the day of the hearing “which it could have agreed to over a year earlier” or “by undertaking the works proposed in the … Orders [made on 19 February and subsequently set aside]”.

  1. The applicant further submitted that, pursuant to s 60(3)(c) of the NCAT Act, the Tribunal may have regard to the relative strengths of each party’s claims, and also referred to the statement by McHugh J in Lai Qin that costs might be awarded where, although both parties have acted reasonably, one party was almost certain to succeed if the matter had been fully tried. The applicant submitted that this is not a case where the respondent could be said to have “merely mounted a ‘defence which is not likely to succeed’ or was arguable”.

  2. The applicant submitted that the respondent mounted no defence and that the expert report filed by the respondent acknowledged the defective works. The applicant maintained that the significant difference between the two experts was in respect to the methodology for repair and the costs involved. The applicant submitted that, because the experts agreed that there were seven areas of defects requiring rectification, the applicant was inevitably going to succeed if the matter had not been resolved by consent.

  3. The applicants further submitted that the respondent had effectively capitulated. The applicants submitted that in determining whether a party had capitulated “the focus… Should be on the ‘outcome’, ‘substance’ or ‘practical result’ of the consent orders… rather than the form of the relief sought”. The applicant cited the Court of Appeal decision in Nadilo v Eagleton [2021] NSWCA 232 in support of this submission.

  4. The applicant submitted in the alternative that the Tribunal should award the applicant the costs of what the applicant described as the first proceedings, more accurately described as the first hearing, and the set aside application. The applicant suggested that the principles applicable to the setting aside of a default judgment, that is that the party seeking to set aside the judgment should pay the costs thrown away, are applicable by analogy in this case.

The respondent’s submissions

  1. The respondent’s submissions were brief, extending over four pages in a relatively large font.

  2. The respondent submitted:

1. The original leak was repaired during construction with all parties happy with the outcome.

The 2nd repairs were assessed by the insuring assessor and works were completed to this scope of works and the applicant’s approvals.

2. Both parties entered discussions with the respondent stating clearly from the start that they would rectify all the issues after going through the correct processes.

The respondent’s insurer made it noticeably clear that the applicant needed to show evidence of the claim. The insurers assessor visited the site and made this clear to Mr Schach.

Months went by with the applicant not doing this.

During our first 2 NCAT meetings, the NCAT member also informed the applicant that he would need to get a report and show evidence of the claim.

After this the applicant finally conducted a report which has cause the extensive delays.

From the first phone from Mr Schach to Dowdy Constructions, Dowdy Constructions has always agreed to do the repairs, without any need for it to go to NCAT.

If Mr Schach had shown evidence of the claim from the very beginning, then the works would be already completed by now and neither party would have incurred any legal costs.

9. The initial report proved by Mr Schach was a non-invasive report showing 45 items as defects.

A second report was then conducted which was invasive and showed evidence of the claim which Dowdy Constructions had been waiting for, for months.

The report provided was not in the format of a Scott Schedule that is required by NCAT.

Dowdy Constructions engage Awesim consulting as their Expert witness report. Awesim consulting narrowed the 45 defects down to 7 main items which both the applicant and Mr Schach expert witness agreed with.

Dowdy Constructions expert witness had requested the reports a number of times from the applicants’ solicitors which delayed resolution, and he also requested that the applicant’s expert provide their findings in an actual Scott schedule.

The final result from the applicant’s witness was still not in a Scott schedule and was not received by Dowdy Constructions or by Awesim Consulting.

We were handed a copy at the hearing after we asked the applicants solicitor for a copy.

Awesim Consulting then had to go out to read the incorrect laid format report.

10.   At the start of the hearing the NCAT member and Dowdy Constructions were made aware that Mr Schach expert witness only had 1 hr before he had to leave to catch a flight.

Dowdy Constructions Expert witness was engaged to allow the entire day as per the NCAT order.

Dowdy Constructions requested that we try to resolve the issues in an outside meeting room as now they had the evidence for the claim and as stated always intended to carry out the works.

  1. The respondent’s submissions included the following explanation for its failure to appear on 19 February 2024:

7. The hearing dates had been changed a number of times by Mr Schach and when the final date was posted out it was sent to Dowdy Constructions accountant and not directly to Dowdy Constructions. Dowdy Constructions email and phone number are for public display online and know by Mr Schach and his legal team.

Dowdy Constructions also did not receive a phone from the court on the day of the hearing when it was evident he was late.

The applicant’s submissions in reply

  1. In his submissions in reply the applicant asserted that the facts stated in the respondent’s paragraph 2 were not accurate. The applicant stated:

(a)   The Applicant had been seeking assistance and for the works to be undertaken by the Respondent from 2020 until May 2023 when the proceedings were commenced. At all times, the Respondent was evasive, unable to be contacted and failed to attend to the necessary rectification.

(b)   This matter was a claim for defective works and as such, there was no requirement for the Applicant to prove to the Respondent’s insurer that there were defective works.

(c)   It was only after the Directions Hearing on 5 October 2023 and the continued failure of the Respondent to attend to investigate the continual water ingress that the Applicant incurred legal costs including the costs of the report writer.

  1. The applicant maintained that he had been obliged to commence proceedings when he did in order to avoid the expiry of the warranty period (as specified in s 18E of the Home Building Act 1989 (NSW)).

  2. In response to paragraph 10 of the respondent’s submissions, the applicant submitted:

(a)   The experts had met in conclave prior to the hearing in order to prepare the joint report.

(b)   The expert for the Respondent had not read the joint report prior to the Hearing notwithstanding that he had been back in Australia (after going overseas before the report had been finalised) for at least 3 days and required additional time in the morning of the Hearing to prepare;

(c)   Agreed on most points with minimal matters to be resolved in respect to the proposed Scope of Works;

(d)   The Respondent sought to negotiate a settlement with the Applicant;

(e)    The evidence required to be adduced from the expert on behalf of the Applicant would have only taken 1 hour due to the contents of the joint report.

Consideration

  1. Although the respondent did not in its submissions address the question whether rule 38 applied, it is clear that the amount claimed or in dispute in the proceedings did exceed $30,000. That is clear from the Joint Report of the experts in which the respondent’s expert estimated the cost of rectification of the agreed defects at over $95,000.

  1. Because rule 38 applies, s 60 is not applicable and, as the proceedings have been resolved without a hearing, the governing principles are those outlined by McHugh J in Lai Qin. The caveat expressed by the Appeal Panel in Roberts v The Owners - Strata Plan No 4393 concerning the application of those principles where s 60 applies, has no relevance.

  2. The application of the Lai Qin principles in circumstances where rule 38 applies were considered extensively by the Appeal Panel in BCA Constructions Pty Ltd v Arsovski [2024] NSWCATAP 31 at [85]-[121]. Like these proceedings, that appeal involved the question whether an order for costs should be made when the proceedings had been resolved by consent by the making of a work order.

  3. The Appeal Panel referred to Bulloch v Linden Building Services Pty Ltd t/as Linden Constructions [2019] NSWCATAP 42 which concerned the allocation of costs where an owner had brought proceedings under the Home Building Act seeking damages of approximately $140,000 for the cost of rectifying defective work performed in breach of s 18B of the HB Act. Both parties had engaged building experts, who conferred prior to the hearing and prepared a joint report. The parties agreed to a consent work order based on the joint report and a further report by an engineer engaged by the owner. In that case, the Appeal Panel stated, at [21]-[22]:

21 In this case it is apparent from the Senior Member’s reasons that, on the basis of the material before him, he was not satisfied, however, without hearing evidence, that the homeowners would be almost certain to succeed. We agree with the builder that the mere fact consent orders are entered into is insufficient to establish that one party would be almost certain to succeed if the matter went to hearing. While there may be circumstances, as in the Gregory matter, where that outcome may have been inevitable, as McHugh J stated, those cases are rare.

22 The fact that the consent orders contain an agreed scope of works does not, in our view, indicate that the Senior Member was bound to accept that, had the matter proceeded to hearing, matters would not have been contested and a similar outcome would have been reached. It was, of course, not permissible for the Senior Member to try a hypothetical action between the parties.

  1. In BCA Constructions v Arsovski the Appeal Panel held, at [110]-[111]:

110   It is not sufficient that the Tribunal is almost certain that a work order of some type would have been made. If that were the applicable test, then any consent order for any work in proceedings where the amount claimed or in dispute exceeded $30,000 would result in an order for costs in favour of the owners, irrespective that, had the proceedings been heard to finality, the owners were likely (or even certain) to have failed on substantial issues which may have resulted in the owners not being awarded costs.

111 Rather, the appropriate enquiry is that “even if both parties have acted reasonably, one party was almost certain to have succeeded if the matter had been fully tried so that the party should obtain the costs of the action” (emphasis added) (Kiama Council v Grant [2006] NSWLEC 96 at [80]).

  1. As the Court of Appeal noted in Nichols v NFS Agribusiness, it is not appropriate for the Tribunal in considering the question of costs to conduct a hypothetical trial of the action. Nor is it appropriate for the Tribunal to engage in a detailed consideration of the evidence in order to resolve disputed issues of fact.

  2. It is clear from the respondent’s submissions, brief as they are, that the respondent disputes the proposition that it consistently (or “fundamentally”) refused to contemplate the rectification of defective work at the applicant’s property. The respondent asserts that it was prevented from doing so by the need for a report for the benefit of its insurance company and the failure of the applicant to provide a detailed report. That issue has not been explored fully and it would not be appropriate to speculate about the issues which may have brought about that situation.

  3. The respondent maintains that it was only 7 of 45 defects alleged by the applicant’s expert which were agreed by the respondent’s expert and formed the basis of the work order.

  4. The applicant did not, in his reply submissions, specifically take issue with that proposition.

  5. I was made aware at the hearing on 22 August 2024 that the applicant’s expert was only available for a short period on that day. I was not party to any further discussions and have no basis to speculate concerning the impact that may have had on the respondent’s decision to resolve the proceedings.

  6. The applicant’s submissions do not provide any reasoned explanation of why, if the matter had gone to a contested hearing, the applicant must have succeeded, not only in obtaining orders in his favour but also an order for costs.

  7. The bald assertion that the respondent’s defence was unreasonable does not advance the applicant’s case. The only reason it is said to have been unreasonable is because the respondent agreed to rectify seven items. It may be noted that the orders made on 19 February 2024 which were set aside required the applicant to prepare further evidence concerning issues of water ingress referred to in six numbered items in the applicant’s expert report and required the respondent to repair 39 other items.

  8. It cannot be said that the consent orders reflect the case that the applicant was maintaining in February 2024 and accordingly it cannot be said that the respondent acted unreasonably in defending the case that the applicant was maintaining.

  9. For the same reasons, that is that the applicant did not succeed in establishing the whole of the case he had been maintaining, it is not possible to say that the respondent capitulated by agreeing to the consent orders made on 22 August 2024.

  10. For the foregoing reasons, I am not persuaded that it is appropriate to make an order that the respondent pay the applicant the costs of the proceedings.

  11. Nevertheless, I do consider that the applicant should receive the costs thrown away by reason of the respondent’s failure to appear on 19 February 2024 and the application to set aside the orders made on that occasion.

  12. As I have noted above, it does not appear that the notice of hearing was sent to any solicitors retained or formerly retained by the respondent. Rather, as the respondent’s costs submissions acknowledge, the notice was sent to the registered office of the respondent, which is the office of its accountants. It is incumbent on any company to ensure that documents sent to its registered office are received by the appropriate officer or employee and dealt with.

  13. The respondent’s director, Mr Matthew Dowdy, was careless to say the least in stating in the set aside application that the notice was sent to the solicitors. It may be noted that he attached to the set aside application a statutory declaration in which he verified that the information provided on the application form was true and correct. Although it is not appropriate in this decision to question whether the set aside application would have been granted if Mr Dowdy had not provided the false information that the notice had been sent to his solicitors, I am reinforced in my conclusion that the respondent should pay the costs thrown away by reason of its non-attendance at the hearing on 19 February by the fact that the respondent made a false statement in the set aside application and that Mr Dowdy verified that false statement in his statutory declaration.

  14. The respondent has not sought to suggest that there was any reason beyond carelessness or inattention that led to the notice of hearing not coming to the attention of its director. Whether the fault lay with the respondent’s accountant, or with the respondent itself, the applicant should not bear the costs of the abortive hearing or the respondent’s application for the indulgence of having the decision set aside.

  15. Accordingly, I will order that the respondent pay the applicant’s costs thrown away by reason of the setting aside of the orders made on 19 February 2024, including the costs of and incidental to the hearing on that date, and the costs of and incidental to the respondent’s application to set aside those orders. Such costs to be as agreed or assessed.

  16. I will otherwise dismiss the applicant’s application for costs.

ORDERS

  1. My orders are:

  1. The respondent pay the applicant’s costs thrown away by reason of the setting aside of the orders made on 19 February 2024, including the costs of and incidental to the hearing on that date, and the costs of and incidental to the respondent’s application to set aside those orders. Such costs to be as agreed or assessed.

  2. The applicant’s application for costs is otherwise dismissed.

**********

I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.


Registrar

Decision last updated: 25 September 2025

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

4

Statutory Material Cited

2

Nadilo v Eagleton [2021] NSWCA 232