SARAH CIVIL PTY LTD V STORK ICM AUSTRALIA PTY LTD
Civil
LANDER J
On 20 February 1998 the plaintiff issued a summons with a statement of claim annexed claiming damages for breach of contract against the defendant in the sum of $3,115,658.85.
It is alleged in the statement of claim that the plaintiff and defendant entered into a contract on 17 January 1996 the terms of which required the plaintiff to carry out certain building works being earthworks and civil building works at Ballera in the State of Queensland. All of the work was carried out in Queensland.
It is claimed that work commenced on the site in March 1996 and continued until, I think, January 1997.
The plaintiff claims that the defendant has failed to make a number of payments which the defendant was obliged to make under the contract. The claims are for payments for Schedule of Rates; Day Works; Extra Works; Back Charges; Wages and On Costs Claims; and Insurance Claims.
On 18 March 1998 the defendant filed an application seeking orders that these proceedings be stayed until further order or that the proceedings be removed or transferred from this Court to the Supreme Court of Queensland pursuant to the provisions of the Jurisdiction Of Courts (Cross Vesting) Act 1987.
It is with that application that I am presently concerned.
A number of affidavits have been filed by both the defendant in support of its application and the plaintiff in answer to the application.
I shall set out the relevant facts.
The plaintiff is incorporated in this State and carries on its business from this State. The defendant is incorporated in Victoria and its administration centre is in that State. Both parties’ connection with Queensland arises out of the head contract and the sub contract.
The defendant entered into a head contract with Santos Limited on 21 November 1995 pursuant to which the defendant agreed to design and construct a gas treatment facility in South West Queensland at Ballera, which is about 1,000 kilometres west of Brisbane. It entered into a sub contract with the plaintiff pursuant to which the plaintiff was to carry out earthworks and civil works. The sub contract sum was $5,082,748.07 which sum was based on a Schedule of Rates and Estimated Quantities set out in a Bill of Quantities which was attached to the sub contract.
On the same day as the defendant issued this application it also issued proceedings in the Supreme Court of Queensland against the plaintiff. A week later it filed its statement of claim in those proceedings.
The claim brought by the defendant in the Supreme Court of Queensland could have been brought in the proceedings in this State by way of counterclaim. That was frankly admitted by Mr Manly who appeared for the defendant on this application.
The claim is for the sum of $861,468 together with interest. The claim is made under four heads. The sum of $168,848 is claimed for moneys paid pursuant to a…
Continue reading SARAH CIVIL PTY LTD v STORK ICM PTY LTD (Applicant) No. SCGR...
Sign in free to access the full text
- AGLC
- SARAH CIVIL PTY LTD v STORK ICM PTY LTD (Applicant) No. SCGRG-98-2448 Judgment No. 6713 Number of Pages - 8 Procedure - Cross Vesting [1998] SASC 6713
- Case
- [1998] SASC 6713
- Decision Date
CaseChat Overview and Summary
The court's decision hinged on the broader considerations of justice and fairness in the litigation process. While acknowledging that the defendant would face some inconvenience if the proceedings continued in South Australia, the court found that the plaintiff would face greater inconvenience and increased costs if the matter was transferred to Queensland. Given that the defendant would still need to manage the case from Victoria, the court concluded that the balance of convenience favored keeping the proceedings in South Australia. The court also noted that the plaintiff, having performed its obligations under the subcontract in Queensland, had a legitimate interest in having the matter heard in the state where it conducted its business. Ultimately, the court's ruling reflected a pragmatic approach to balancing the interests of both parties, emphasizing that the decision should not be driven solely by the defendant's preference for a different jurisdiction.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.