Sanwa Home Australia (formerly Balfield) Pty Ltd v Eamon Pty Ltd
[1992] HCATrans 106
•
' <
"I
~
| IN THE HIGH COURT OF AUSTRALIA | • |
| Office of the Registry |
Brisbane Nos B4 and Bll of 1992 B e t w e e n -
SANWA HOME AUSTRALIA (formerly
BALFIELD) PTY LTD
Applicant
and
EAMON PTY LTD
First Respondent
RADOR PTY LTD
Second Respondent
BLACKEDGED PTY LTD
Third Respondent
Applications for special leave
to appeal
| Sanwa | 1 | 10/4/92 |
DEANE J
DAWSON J
McHUGH J
TRANSCRIPT OF PROCEEDINGS
FROM BRISBANE BY VIDEO LINK TO CANBERRA
ON FRIDAY, 10 APRIL 1992, AT 10.58 AM
Copyright in the High Court of Australia
| MR w. SOFRONOFF, QC: | May it please the Court, I appear with |
my learned friend, MR J. SULLIVAN, in application
B4 of 1992, and with my learned friend,
MR S.L. DOYLE, in application B11 of 1992.
(instructed by Morris Fletcher & Cross)
| MR P.A. KEANE, OC: | May it please the Court, I appear with |
my learned friend, MR P.L. O'SHEA, for the
respondents in both applications. (instructed by
Corrs Chambers Westgarth)
| DEANE J: Very well. | What is the convenient way of dealing |
with these matters?
| MR SOFRONOFF: | May I sketch the facts, Your Honour. |
| DEANE J: | You can take it that we have, with some difficulty |
in relation to the second one, read the documents.
So we are acquainted with the facts. Would you suggest we deal with them together?
| MR SOFRONOFF: | Yes, if it pleases the Court, that would be |
convenient.
DEANE J: Very well.
| MR SOFRONOFF: | Your Honours, could I then touch upon the |
facts very briefly. Among the grounds of defence raised by the applicant purchaser at the trial was
that the vendor owed obligations to fulfil certain
rezoning obligations and they were called the
rezoning points during the proceedings andreference is made in the reasons to that.
His Honour the learned trial judge concluded, on a
construction of the contract, that the time for
completion had not yet arrived, and so the time for
fulfilment of those obligations had not yet arisen,
but His Honour nevertheless went on to consider
whether or not there was anything in those points.
Honour held against the applicant on two of them Relevantly there were three such points, and His and concluded that, as to the third, it was hypothetical given his finding as to one of the other two. The matter went on appeal to the Full Court,
and the Full Court also concluded that, the time
for completion not having arisen, it was premature
to consider whether the rezoning obligations had
been or had not been fulfilled by the vendor.
Could I take Your Honours to book B4, at page 94, where Mr Justice McPherson, who delivered the only
judgment, said - referring to the rezoning
obligations and certain other obligations that are
not material:
| Sanwa | 2 | 10/4/92 |
But in any event these obligations, if
that is what they really are, are expressed in
ell 4(a) and 26 in terms that require their
performance either "by the date forcompletion" or "prior to completion" of the
relevant contracts. Until, therefore, a fresh
date for completion is fixed and has arrived,
it is not in law possible for the purchaser to
assert that the vendors are in breach, or that
they are unwilling, unable, or not ready to
perform the contracts in accordance with their
terms.
Otherwise, Their Honours dismissed the appeal.
The matter then would have gone back to
Acting Justice Robin, for the purpose of making the
final order, but His Honour's commission as an
acting judge of the Supreme Court had expired andso it went before Mr Justice Byrne.
Mr Justice Byrne made the usual sort of specific
performance order, that is, one which involved the
exchange of documents for money. Before His Honour
the point was taken that the applicant purchaser
maintained a right to assert that the rezoning
obligations had not been fulfilled. His Honour
declined to cause the order to reflect that
assertion or contention of the purchaser, but
instead directed that the vendor, by its
solicitors, send a letter to the purchaser. That
letter, Your Honours, appears in book Bll and it is
the last document in the book. The particular matter that His Honour required the plaintiff's
solicitors to write, to communicate, is that in the
first paragraph:
The plaintiffs acknowledge that the
defendant's rights pursuant to special
conditions 4 and 5 -
those that contain the rezoning obligations - of each of the contracts are unaffected by the
absence of any express reference to the
plaintiffs' obligations thereunder in the
order of Byrne J.
And then the plaintiffs went on to say that their
position, of course, as is the fact, was to the
contrary.
DAWSON J: Well, what is the effect of that letter?
| MR SOFRONOFF: | Your Honours, His Honour was concerned to |
ensure that nothing he did affected the position of
the applicant purchaser, whatever that might, at
the end of the day, be determined to be, in respect
| Sanwa | 3 | 10/4/92 |
of the fulfillment of the rezoning obligations.
The Full Court - - -
| DAWSON J: | But does it mean that the order was subject to |
compliance with conditions 4 and 5?
MR SOFRONOFF: Yes, in our submission. His Honour, we
submit, clearly intended it to be so because of his
requirement that the letter be sent.
| DAWSON J: | Why could he not put that in the order? |
| MR SOFRONOFF: | I do not know, Your Honour. | In any event, |
the order was made which called for exchange on
3 February. On that day the parties met, but settlement did not take place. My client declined to complete. It, on that day, did not raise any
particular ground for that, but later raised the
ground, which is not germane to present
proceedings, relating to whether a release of
mortgage had been properly signed. The parties met again on, I think, 15 March, and again my client
took a point which, suffice it to say it does not
bear examination and, at the invitation of my
client, finally, the parties met again on 11 March
for settlement and on that day my client finally
determined - or rather said it would not proceed
and revealed its hand, as it were, with respect to
the three town planning points, the rezoning
points.
The vendors then brought an application for
what is called a Morgan v Brisco order before
Mr Justice de Jersey. My client brought an application for leave to be discharged from the
contract. Mr Justice de Jersey dismissed my client's application, because although it was
submitted to him that the rezoning obligations had
not been fulfilled and that that entitled my client
to get out of the contract, His Honour was of the
view that my client had not evinced any intention,
in any event, to settle the contract, and was not in a position, therefore, to call for performance.
His Honour then turned to the question of the
Morgan v Brisco order, pursuant to which the vendor
would be at liberty to deposit the documents of
title and transfer in court, whereupon my client
would be ordered, within four days or so
thereafter, to pay the money. It was submitted to
His Honour that such an order ought not be made in
circumstances where there was a live issue that the
town planning obligations, the rezoningobligations, had not been fulfilled. That was the
issue that the Full Court had left open and,
indeed, had said could not, as a matter of law, be
raised at that point. His Honour, however,
| Sanwa | 4 | 10/4/92 |
declined to accede to that submission and made the
order.
My client appealed to the Court of Appeal, and
it is the decision of the Court of Appeal
dismissing that appeal that is the subject of
application Bll. Their Honours of the Court ofAppeal concluded that whether or not that issue remained alive, the court had power to order specific performance of the contract. Could I take
Your Honours, please, to page 31 of Book Bll, the
last paragraph on the page. After having
considered my client's contention with respect to
whether the points were still alive, whether what
Acting Justice Robin decided about them left them alive, and the opposing contentions, Their Honours
said:
It is unnecessary to determine whether or not the appellant is estopped as the
respondents contend. There is another ground
upon which this appeal must fail.
Irrespective of whether or not any particular
issue has been finally determined against the
appellant (subject to the ultimate disposition
of the proceedings in the High Court), the
Court has ordered that the contracts be
specifically performed and carried into
execution. The orders of Byrne Jon 19 December 1991 and de Jersey on
13 March 1992 are merely ancillary orders to
give effect to that decree in the changing
circumstances which have emerged. Thosecircumstances do not include any change in the
position with respect to the validity and
efficacy of the Order in Council -
that is to say, the rezoning matter:
Whether or not any particular issue has
been decided in favour of the respondents so that the appellant cannot again raise it,
(subject to the outcome of the proceeding in
the High Court) the Court has ordered both
parties to perform the contract under its
control. Its power includes power to make an
order dissolving the decree of specific
performance and terminating the contract at
the instance of either party if it is
established that it would be just to do so in
the circumstances. Unless that is
established, it has power to make such orders
to carry the contracts to completion as arejust in all the circumstances: cf Johnson v
Agnew (1980) AC 367. That was the power which
Byrne J exercised when he fixed a date for completion and made orders with respect to the
| Sanwa | 10/4/92 |
exchange of documents and money. As has been exercise by de Jersey Jin the different
noted, there was no appeal from his orders.
circumstances which were established before
him.
Your Honours, in our submission, what has resulted
is that whereas the Full Court had acknowledged
that the rezoning obligations were matters which
the applicant could not, as a matter of law, raiseat that stage because the time for completion on
construction of the contracts had not arrived yet,
and whereas Mr Justice Byrne was at pains to ensure
that that position was not affected by the order
that he made, the Court of Appeal has determined
that notwithstanding that at some later date it
might be determined that my client is right, that
it is receiving less than it contracted for, that
it nevertheless has to fulfil the contract byreceiving title, such as it is - - -
DEANE J: Are Their Honours not saying that the supreme
court keeps control of its orders and you can go
back if you have proper grounds to get the order
varied?
MR SOFRONOFF: Their Honours are saying that.
Mr Justice de Jersey was asked by us to make an
order in terms that allowed the rezoning points to
be dealt with before the obligation to pay money
arose. His Honour declined to do that. That was
part of the appeal to the Court of Appeal, and the
court's conclusion, we submit, is that although, of
course, in some proceedings at some stage my client may agitate the rezoning points, it will all be too
late, because the contract will have been
completed. It will have paid the money. It will
have received the land.
| DEANE J: Their Honours do not seem to have understood the |
matter as you put it, because it says:
The appellant's only attempt at such an
exercise, the application which it made to
de Jersey Jon 11 March 1992, failed and there
has been no appeal.
MR SOFRONOFF: That was the application, Your Honours, for
discharge of the contracts. His Honour did not
consider the rezoning points on that application
although they were put before him becauseHis Honour concluded that the applicant was not in
a position to assert a failure by the respondent to
fulfil its obligations in circumstances where the
applicant was not itself ready to pay the money in
| Sanwa | 6 | 10/4/92 |
any event. There has not been any appeal against
that finding and that conclusion.
So our submission in short, Your Honours, is this: specific performance orders are made by
courts in order to enforce the obligations of both
parties to the contract. The orders are made in order to carry out the terms agreed upon by the
parties to the contracts. Those orders are not
made to compel one party to fulfil its part of thebargain in circumstances where it may later be adjudged the other party has not fulfilled its
obligations. That is the position, we submit, that
has obtained here in circumstances where the
documents having been deposited last Monday, my
client came under an obligation to pay the money.
And yet, if its contentions are correct, the
rezoning points have not yet finally been
determined, and it may be the case and a court may
find it to be the case, that the vendor has not
fulfilled its obligations.
That, Your Honours, is the ground for special
leave that we raise at page - - -
DEANE J: That is in the second matter?
| MR SOFRONOFF: | Yes, Your Honours, in the second matter at |
pages 62 and 63 in paragraph 9. In our submission,
the effect of this judgment is that it is authority
for the proposition that the court has power to
make an order compelling both parties to complete a
contract as long as there is in existence a
contract that has not been discharged by the
parties or by the court, and we say that that
arises from Their Honours' conclusion at page 32 at
about point 3:
Its power includes power to make an order
dissolving the decree of specific performance
of either party if it is established that it and terminating the contract at the instance would be just to do so in the circumstances. Unless that is established -
that is, that it is just to terminate the
contract -
it has power to make such orders to carry the
contracts to completion.
DEANE J: Well, your proposition can be put two ways: one
is that no matter how badly one party to a contract
behaves and how delaying its conduct is, the court
can never order specific performance while he has
any point at all that he can raise against
completion; or alternatively, your argument is
| Sanwa | 7 | 10/4/92 |
that in the circumstances of this case a discretion miscarried. Well now, is it the first or is it the
second?
MR SOFRONOFF: It is neither, with respect. It is more like
the first proposition that Your Honour put. We would put it in these terms: notwithstanding that
a defendant may be wrongly seeking to evade its
obligations under the contract, or could I - - -
DEANE J: Assume, for example, the case of an ordinary
purchase of a house where the contract was due for
completion in January, and the vendor did not
complete March, June, November, and the next
January, having promised completion, the purchaser turns up, having sold his home, dependent on the new home, is refused completion, goes to court for
specific performance and some obscure point is
raised by the vendor, is your submission that the
court lacks jurisdiction in those circumstances tosay, "This is a case where we will order specific
performance of the contract, but you can still
raise your point if you want to."?
| MR SOFRONOFF: | Your Honour, the question would not arise in |
that fashion. If, let us say, there was an
application for summary judgment seeking specific
performance of the agreement and the obscure point
was raised by way of raising a triable issue, it
would either be a triable issue or it would not.
If it was a triable issue, that could not be
determined there and then by the judge in chambers,
there would be a trial, at the end of which there
would be an order for specific performance if the
plaintiff succeeded.
DEANE J: So, your point is that the court would lack
jurisdiction to make an order for specific
performance, leaving open if subsequent rescission
| MR SOFRONOFF: | If it was not clear that the point raised by |
the respondent in resisting the order was a bad
one, and in this case, in our submission, it was
not clear. Mr Justice de Jersey, when asked to determine the point on the application for leave to
discharge the contract, called it - I think the
words were - "a complicated legal and factual
dispute" which was not suitable to be determined in
chambers before him. That is the sort of point
that it was and it would not require a very long
delay in order to have a trial about it to see
whether my client's contentions are right or not.Or, alternatively, the order we proposed His Honour make was that the purchase moneys be ordered
to be payable upon the filing of an affidavit by
| Sanwa | 8 | 10/4/92 |
the vendor that it had fulfilled its obligations
with liberty to apply. We, of course, would have immediately applied and have had that issue
determined. Whether they had indeed fulfilled
their obligations, namely the re-zoning ones, the
order could have been limited to giving liberty to
apply only with respect to those matters if it was
thought that general liberty would be too great a
liberty for this defendant in these circumstances
and, in my submission, one could see why a court
might think that. But this point was a point which
undoubtedly had been raised at the trial, which the
Full Court determined was premature for consideration and which the defendants have sought
to be dealt with in a final and determinative way
and, in our submission, the court does not have
power to preclude it, without hearing the
respondent, from getting that determination. To do otherwise, we submit, is to go further than - the
cases say, go further than merely enforcing the
contract and to risk trampling on one party's
rights.
McHUGH J: But, in Bll your appeal was against the stay
order, application for a stay, was it not?
| MR SOFRONOFF: | No, Your Honour. | In Bll the appeal was |
against Mr Justice de Jersey's making of a Morgan v
Brisco order. We applied to His Honour for a stay;
His Honour refused that. We applied de novo to the Court of Appeal for a stay. The point was taken that there was no jurisdiction or might be no
jurisdiction in the Court of Appeal to entertain an
application de novo. To avoid controversy, the Court of Appeal treated it as an appeal from the
refusal of a stay, granted a short stay, heard the
appeal within a short time of a week or so and
dismissed it shortly after that. That is why there
might be a reference in the record to an appeal
against a stay, Your Honour.
| DEANE J: | And was your client in breach of the supreme |
court's order at the time it applied to
Justice de Jersey?
| MR SOFRONOFF: | His Honour must have - could I answer it |
descriptively, Your Honour. The order was for settlement on 3 February. The reason my client did not settle on 3 February is because its solicitor
said, one of eight releases of mortgages had been
signed by only one attorney for a bank when two
ought to have signed. That is a matter that is
hotly contested. There is a trial about it. That
is to be heard on 30 April. That still has
consequences because of interest provisions and
presumably the trial will go ahead. That was the
reason there was no settlement on 3 February. The
| Sanwa | 9 | 10/4/92 |
question whether my client wrongly declined to
settle will be determined at that trial, and it is
a credit case.
On the second occasion there was a date for
settlement proposed, not pursuant to a court order, but the parties got together and my client declined
to settle on a ground that, I concede, was not
tenable. On the third occasion my client proposed the date for settlement, declined to settle, and
ultimately said the reason it declined to settle
was the failure to fulfil the town planning
obligations. So in those circumstances, in our submission, it may be determined on 30 April, the
date of the trial, that my client was in breach of
the order, but we will not know that until thecourt hears the evidence.
Your Honours, those are the submissions on the
application for special leave from the decision of
the Court of Appeal in application Bll. Could Ideal with the - - -
DAWSON J: Could I just take you back to Mr Justice Byrne's
order. If the effect of the letter was that that
order was conditional upon compliance with theconditions, does that then carry right through?
| MR SOFRONOFF: | In our submission, yes. His Honour |
Mr Justice Byrne was a member of the Full Court
that heard the appeal, the first appeal, and we
submit that His Honour was peculiarly positioned to
understand why such a qualification was necessary.
Of course, it left the plaintiff in a position to
assert the contrary: that my client was estopped,
that the grounds were bad, that they had been
determined to be bad by Acting Justice Robin, and
that that had at some stage to be determined. But
we submit my client has been denied - - -
DAWSON J: But then Justice de Jersey's order would be also
subject to the same condition because it was merely working out, as it were, or implementing
Justice Byrne's order.
| MR SOFRONOFF: | It ought to have been but in plain terms it |
is not, because on its face it allows the vendor
liberty to deposit the documents of title andtransfer in court, whereupon my client becomes
ordered to pay the purchase price within a fixed
number of days. So there is no room there.
| DAWSON J: | Why is there not? | Why can you not now suggest |
that Justice de Jersey's order was subject to that
condition or qualification?
| Sanwa | 10 | 10/4/92 |
| MR SOFRONOFF: | We asked him to express that to be the case |
and His Honour expressly declined to do that.
Could I find the page at which His Honour does
that?
DAWSON J: Whether or not he declined to do so, the argument
is still available that nevertheless your
obligations are subject to that qualification now.
| MR SOFRONOFF: | Yes, it is. |
| DAWSON J: | The argument is available. |
MR SOFRONOFF: It is available but, in our submission, it
would have to fail because His Honour was pressed
with precisely that submission. It was rejected.
That was made the subject of a ground of appeal and
the decision of the Court of Appeal can only be
understood on the basis that they declined toaccept that submission. Indeed, the terms of the
reasons in the Court of Appeal, and the reasons of
Mr Justice de Jersey, are such that it leaves no
doubt that they were of the view that, irrespective
of this proposition of my client's, it was to
settle. It was to pay the money.
| DEANE J: | And if you look at Justice de Jersey's judgment at |
page 4, on his findings, this is very much the sort
of case that I put to you in terms of the vendorjust taking points for the sake of taking them.
MR SOFRONOFF: That was the vendor's submission that the
purchaser was taking points, and there is no doubt
that that - - -
DEANE J: That is His Honour's finding.
| NR SOFRONOFF: | Yes. |
DEANE J: In other words, your client is playing a game of
ducks and drakes with the orders of the supreme court?
MR SOFRONOFF: His Honour said that, but - - -
| DEANE J: | He found that? |
| MR SOFRONOFF: | His Honour found that. | we do not challenge, |
we cannot now challenge that my client is an
extremely reluctant purchaser who, if it is able
lawfully to avoid settling the contract, would doso.
DEANE J: There is nothing wrong with that?
| MR SOFRONOFF: | No. |
| Sanwa | 11 | 10/4/92 |
DEANE J: But there is something wrong with a conduct as
described by Justice de Jersey in the second
paragraph on page 4?
| MR SOFRONOFF: | There is. We would submit that His Honour |
was wrong in drawing that conclusion. The only evidence His Honour heard was from my client's
solicitor who said that he attended on the first
settlement, without any money from his client, and
saw that the release had not been signed. That was
the evidence that His Honour heard. His Honour
also heard, or saw evidence in affidavit form, as
to my client's attitude on the second and third
occasions for settlement. In our submission,
His Honour was wrong in concluding that, with
respect to the rezoning obligations which were
proved on affidavit material before him to at least
be alive if not correct, His Honour was not
entitled, we submit, to conclude that with respect
to those points my client had no bona fide belief
in their validity.
Your Honours, with respect to that last matter
I dealt with, my learned junior reminds me that the
rezoning points were taken by my client at the
trial before Acting Justice Robin in the Full
Court, until the matter was not argued because of the approach adopted by the Full Court and my
client's acceptance of that approach; at
settlement on 10 March, that is the last occasion
for settlement, before Mr Justice de Jersey and in
the Court of Appeal, and in those circumstances, inour submission, my client is in a strong position
to agitate that His Honour was wrong in concluding
that, with respect to that point, leaving aside
other points, my client was playing ducks and
drakes.
Could I turn then, Your Honours, to the first
application, the original application in B4.
Your Honours, the affidavit raises a number of grounds of special leave. I propose to make submissions about only one of them and that appears
at page 113, paragraph 6(a) -
DEANE J: If I might say so, that is a rather wise course in
that the approach of building 15 or 20 points of
law in a case is thought by some to be attractive
to this Court. It has quite a contrary result when
you look at a case and it is said to involve this
point, this point, this point, this point and this
point. You almost, invariably, get the feeling, "Oh for heavens sake it is not a suitable vehicle
to raise all of those" .
| MR SOFRONOFF: | Thank you, Your Honour. | My client would not |
wish to raise anything but the best points.
| Sanwa | 12 | 10/4/92 |
Your Honours, under the contracts - there were
three interrelated contracts - the original date
for completion was 29 March 1991. The contract,
however, was varied and the variation appears at
page 83 of book B4.
The variation related to when completion would
occur and Mr Acting Justice Robin, and the Full
Court - and we do not challenge this - concludedthat the variation did relate to when completion
might occur, the parties having agreed that it
would not occur on 29 March.
If Your Honours look at the first clause, in
the middle of page 83, the first obligation, we
submit, which arises, is that:
1. Your clients -
the vendors -
are to satisfy the purchaser's solicitors that the vendors have attended to and finalised all
outstanding matters within their control in
relation to the rezoning ..... by 5 pm the 28th
day of March, 1991 -
The second clause then obliges the vendors to
provide documents evidencing those facts. The
third clause entitles Sanwa, the applicant, to
consider for 14 days whether it is reasonably
satisfied. Your Honours will notice the word
"reasonably" in brackets. That was a word that was
added by agreement between the parties. It is a
word that is missing in paragraph 1 which relates
to the satisfaction of the purchaser's
solicitors.Then clause 4 provides for a timetable.
If Your Honours turn over the page you will
see that clause 8 provides that:
Time shall remain of the essence.
The learned trial judge found that the purchaser's
solicitors, under clause 1, need only be satisfied
honestly, not reasonably. And His Honour concluded - and this was not upset on appeal - that the
plaintiff had not established that the solicitor
was dishonest in forming the view that he was not
satisfied that all things that could be done had
been done. That finding, as I say, was not
satisfied on appeal but nevertheless it was held
that the purchaser could not terminate the contractfor failure of the vendor to satisfy the
purchaser's solicitors of those matters by 5 pm on
28 March.
| Sanwa | 13 | 10/4/92 |
If Your Honours would go to page 91, as we
will see, over the page, His Honour
Mr Justice McPherson concluded that time was of the
essence of the matters in the variation agreement.
In the middle of the page, then:
Nor is it, in my opinion, possible for the
purchaser to assert an independent right to
determine the varied contract arising from
failure to fulfil the conditions contained in
paras 1 and 3 of the variation agreement -
1 being the solicitor and 3 being Sanwa.
Even if, contrary to the trial judge's
findings on this point, Sanwa could be said to
have been acting reasonably -
His Honour had held that it was not acting reasonably and that is not challenged -
when on 9 April 1991 it expressed its non-
satisfaction with the matters specified in
para 1 of that agreement, it thereby acquired
no right to put an end to the contract. The variation agreement itself did not confer any
such right, whether in express terms or
otherwise. Such a right may sometimes be implied from the mere presence in a contract
of the words "subject to ... ". But no such words appear in the agreement of 8 March 1991.
Indeed, none of the provisions of the first
four paragraphs of that agreement is expressed
in language appropriate to a contractual
condition. The purchaser was given no right to determine the contract if the terms of the
relevant paragraphs were not fulfilled.
If Your Honours skip down two thirds of the way
down the page, the end of the middle paragraph, the
last sentence, that is where His Honour concludes that: By virtue of para 8 time was to remain of the
essence of that date for completion, as well,
no doubt, as of the other dates specified inthe variation agreement.
Your Honours, the result, in our submission, of
that conclusion is that although one expects,
according to orthodox authority, that if time is of
the essence for the fulfilment of some task or
condition in a contract, then the other party, theinnocent party, may, if that condition is not
fulfilled, terminate it.
| Sanwa | 14 | 10/4/92 |
The effect of this conclusion is, we submit,
that before that can arise there must be some
express or implied words to the effect that you
thereby get a right to terminate. We submit that that is not the law but if that is the law it
signifies a substantial departure from what has
been understood to be the law since Hoad v Swan was
decided in 1920 and has been accepted ever since.
This ground, as I say, is set out at page 113,
paragraph 6(a).
| DEANE J: | I am not sure I quite follow how that fits into |
the overall case. The finding was that Sanwa was not acting reasonably and we assume that that is so
for the purpose of this argument.
| MR SOFRONOFF: | Yes. |
| DEANE J: | Can you explain to me where the argument leads. |
| MR SOFRONOFF: | Yes. There were relevantly, under the |
variation agreement, two matters to occur, time
being of the essence of the occurrence of those.
The first is that the purchaser's solicitor must be
honestly satisfied that certain things had
happened, and he must be satisfied of those thingsbefore 5 pm on 28 March.
The second matter is that Sanwa had to be
reasonably satisfied, not just honestly, by some
other date or within some other period. We say nothing about that. The conclusion was that Sanwa was not reasonable in the view that it came to, and
we say nothing about that. But we succeeded at the
trial with respect to the first matter, that the
solicitor was not honestly, if unreasonably or
irrationally - he was honestly dissatisfied that
the vendor had done the things within its power and
control.
The vendor having failed to satisfy him by the
time stipulated, time being of the essence, my
client was entitled to terminate the contract,
which it did, or rather I should say, which it
purported to do. Mr Acting Justice Robin concluded that it had not, that it had let time slip by
without acting and that by the time it acted on, I
think, 11 June, a couple of months later, a month
and a half later, it was too late.
We would seek to challenge that latter finding
on any appeal, but of course it does not throw up
any special point. The point that is thrown up is whether it is correct to say that in the absence of
words which expressly or implicitly give rise to a
right to terminate, then the mere statement that
party A must do something by a particular date,
| Sanwa | 15 | 10/4/92 |
time is of the essence, does not give rise to a
right to terminate.
| DEANE J: | What if one reads these variation provisions on |
the basis that clause 1 is not a free standing
independent provision, but is a proceduralmechanism leading into clause 3?
| MR SOFRONOFF: | We submit that it does not make any |
difference and, indeed, I would wish my submissions
to be understood as, put at their lowest, that -
put on the basis of the worst case from my client'spoint of view - they are machinery provisions; they
all work together and they work together in order
to achieve a date for completion. Time, however,
remains of the essence of the fulfillment of thematters stated therein.
DEANE J: But that would lead to the implied specification
in the active clause 3 of, what, 11 April? Now, if
you had 11 April in the critical clause 3, would
you not have to read clause 8 as referring, not to29 March, but to 11 April?
| MR SOFRONOFF: | No, Your Honours, we would submit the time |
within which the matters in those clauses are to be
attended to is, in each case, of the essence, and
we say that because there are two alternativeways - the parties having abandoned the certain
date for completion, 29 March - a new completion
date can be arrived at. One is by this machinery, which would arrive, I think, at a date of June 11,
60 days from April 11. The other is, if that clause fails to operate, then the parties might
agree, in the absence of anything else, they would
be put to the position that only a reasonable time
for completion is required, it would be implied.But that does not mean that clause 1 does not mean
what it says - - -
| DAWSON J: | I wonder about that because, really, the more |
reasonable interpretation would be that the vendors
had to place all the materials before the
purchaser's solicitors by that date, whereby he
could satisfy himself, rather than that he should
satisfy himself because he could simply delay
satisfying himself beyond the date.
| MR SOFRONOFF: | Yes. | Your Honours, as to that, his client |
might be in breach in the sense of preventing the
performance of a contract by its agent.
Alternatively, the operation of the term might be
frustrated. Could I say, however, that that construction that Your Honours put was the one that
commended itself to Acting Justice Robin in the
Full Court. We would have to overturn that construction in order to succeed on the appeal
| Sanwa | 16 | 10/4/92 |
ultimately. We contend that the clause read as separate provisions, or read as one machinery
provision in order to settle a new date,
nevertheless provide for times and clause 8 of thevariation agreement provides that those times are
essential times.
DAWSON J: But you cannot be in breach of the time provision
in the sense that you have no control over what
happens to take you over the time limitation, can
you?
MR SOFRONOFF: It is akin, in our submission, to a
provision, for example, that says one of the
parties shall do his best to get the minister'sconsent by 23 March and he has to do his best to
get that consent, but ultimately the obtaining of
the consent is not within his control, perhaps,
nevertheless the failure of that time may lead tothe consequence that time is of the essence, the
contract might be terminated.
DAWSON J: Well, you can hardly say that the party is in
breach, in those circumstances, can you
Mr Sofronoff?
| MR SOFRONOFF: | No, that is correct. |
| DAWSON J: | It is only on breach that the right to terminate |
would arise.
MR SOFRONOFF: That, however, does not arise here for two
reasons: one is, he, the solicitor in this case,
was dissatisfied; did receive the material and was
not satisfied by it, as the trial judge concluded,
the onus being on the plaintiff to show dishonesty;
and secondly, the Full Court concluded, and we
adopt this conclusion, that the times referred to
each of them are of the essence. That was at that
passage I showed to Your Honours earlier.
| DAWSON J: But the vendors did complete all they had to do |
within the time limited, did they not?
| MR SOFRONOFF: | It depends how one views clause 1; if it only |
throws up an obligation to provide materials within
time for him to consider them by 5 pm on 28 March,yes; if they had an obligation to satisfy him,
then, no. We submit that latter is the correct construction.
DEANE J: But they did provide materials which, on the
findings below, would have satisfied any solicitor
acting reasonably.
MR SOFRONOFF: | Yes, we challenge that, but that is the finding and the Full Court agreed. |
| Sanwa | 17 | 10/4/92 |
DEANE J: Yes, I understand your challenge to it, except if
one construes clause 1 the way you would favour, it
provides pretty strong reasons for reading it
simply as something leading into clause 3 in terms
of consequences.
MR SOFRONOFF: | Your Honours, 28 March is the significant date, we submit, because the 29th was the old |
| essential date for completion. | |
| DEANE J: | I follow that. |
| MR SOFRONOFF: | And so, the position is that the parties have |
agreed that by close of business on the day
preceding the old day of completion,
notwithstanding that the re-zoning and other
obligations had not by then been fulfilled, when
they would have had to have been before, it is
sufficient if, leaving aside fulfilment, the vendor
has at least done everything in its power to ensure
that they are completed in a timely fashion by the
bureaucracy, and satisfied the purchaser's
solicitor of that fact. That was the obligation
that was substituted for the original obligation of
actual fulfilment of the obligations by the day
after. And so, against that background, we submit, the construction that we contend for is the
preferable one.
Your Honours, unless there is anything else,
those are our submissions.
DEANE J: Thank you, Mr Sofronoff. Yes, Mr Keane.
| MR KEANE: | May it please the Court, would it be convenient |
if we dealt with the two applications in the same
order in which they are dealt with by our learned
friends?
| DEANE J: | You take them in whatever order you like. |
| MR KEANE: | As Your Honours please. | If then we may proceed |
to the second application, that is B11, could we
draw the Court's attention to the observations made
by the Court of Appeal last Monday, 6 April, which
appear in the book B11 at pages 46 to 48. We apprehend that it is useful to draw the Court's
attention to these matters in relation to our
learned friend's argument on the second application
that there is a question as to whether his client
is getting that which they have bargained for
because the town planning points are still in
dispute.
We draw Your Honours' attention to what is
recorded there from the President of the Court of
Appeal, speaking for the court, because it
| Sanwa | 18 | 10/4/92 |
demonstrates that - and this is particularly so at
page 47, the first long paragraph on the page,
which demonstrates that when the matter of the
appeal came on for argument the present applicant
sought to have the court not determine the validity
of the town planning points, on the footing that
the material was not before the court, the time wasnot right for determination of those points; and
preferred not to have them determined at all,
notwithstanding our agitation that they should be
determined, or at least could be so.
We draw Your Honours' attention to the balance of page 47 and the concluding remarks of the court
because, Your Honours, in our respectful
submission, an opportunity to have the town
planning points determined was foregone
deliberately, then what was sought to happen was
that submissions were sought to be made to agitate
those points again, the Court of Appeal having
reached the conclusion that the judgment of
Mr Justice de Jersey was sustainable without
reference to whether the town planning points were
good or not.
If we may develop those observations a little
further in relation to the other side's
opportunities to have the town planning points
determined, but their almost religious reluctance
to have the substance of them aired, may we say
that the town planning points, critical as a matter
of substance to their contentions, were raised inthe original notice of appeal to the Full Court,
which appears in the first application book at
pages 76 to 77, that is application book B4,
paragraphs 5 to 12. If we might ask Your Honoursto note particularly paragraph 12, because
Your Honours will appreciate that in reading the
judgment of the Full Court no reference is made to
any contention that the present applicant
justifiably terminated the contract on 12 June by reason of the non-satisfaction of conditions 4 and
5, the town planning points.
Your Honours, it has been said by our learned
friend several times that the Full Court concluded
that those points could not be raised. With
respect, that misstates the position. The Full Court concluded that unless time were of the
essence, those points could not succeed as grounds
justifying the rescission on 12 June.
The position is that, on the appeal before the
merit they are clearly covered by the privative
Full Court, those points were not argued,
clause relied upon by Acting Justice Robin and, in
| Sanwa | 19 | 10/4/92 |
relation to what Mr Justice de Jersey made of them,
he expressed the view that he regarded
Acting Justice Robin's treatment of the points,
made at length, after full argument, as being
sufficient to enable him to proceed on the footing
that there was nothing in them.
Your Honours, we submit in relation to the
second argument, or the second application, that
Your Honours do not have the benefit of any
discussion of these points by either of the
appellate courts below. The reason Your Honours do not have that is because they have been
deliberately foregone, on both occasions in which
they could have usefully been agitated,
particularly in relation to the first occasion
because,on that occasion, if the other side had
been able to make out its contention, albeit it one
that it made in the alternative, that completion
on 10 or 11 June was of the essence and the town
planning points were good, then they would have
succeeded in establishing their counter claim to
have the contracts declared rescinded on the 12th,
which, of course, is the contention that is sought
to be made in paragraphs 4 and 6 of the draft
notice of appeal in the first application, that
is B4.
Your Honours will see that if Your Honours
turn to the first application book, that is B4, at
pages 130 to 132 of the record, and Your Honours
are still in the position where Your Honours have
heard not a word of the merit of these points.
Your Honours are in the same position in thatregard as the Full Court and as the Court of Appeal
and, as Your Honour the presiding judge observed,
there may be nothing wrong with a party taking
points in its own interest if they are lawfully
available, but there is, with the greatest respect,
something wrong in a party seeking special leave
who has deliberately put it out of the way of the appellate courts before whom the matter has come to
determine the point.
Might we say one thing further about that.
That is in relation to the orders of
Mr Justice Byrne. Those orders required completion
on 3 February. Prior to 3 February, the letter
of 19 December was sent. It was made very clear in
that letter that the respondents' contention was
that the respondents had complied, in all respects,with its obligations in relation to the town
planning matters. Nothing further was done about
that. No further proceedings were taken before completion and in that time the present applicant
stood by while the respondents put themselves in a
position to complete, and that involved not simply
| Sanwa | 20 | 10/4/92 |
getting the documents together, Your Honours, but
it involved the destruction of the hotel which
stood on the property. Your Honours, that is all we wish to say about B11. In relation to the argument in respect of B4,
if we may address the merit of that argument. The
argument depends upon a construction favourable to
the applicant of a contract which one would venture
to hope is unique in its critical terms. All four
judges who have thus far considered this question
have rejected the construction contended for by the
other side, we submit correctly. We submit that they were correct in taking the view that
Mr Rudkin's position, under clause 1, was
preliminary to Sanwa's determination which was
itself a mechanism to fix a date for completion.
And we submit that it is implicit, particularly in clause 3, that there be no right to determine, or
indeed no right to do anything at all, conferred
implicitly upon Mr Rudkin, or upon the solicitors,
by clause 1 of the document.
Your Honours, in relation to the matter of
merit, we would mention as well, with respect, that
Hoad v Swan was a clear case of breach of timely
performance of a promissory obligation.
Your Honours, there is one further matter in
relation to B4, and that is, that even if it be
correct that matters which occurred or
non-satisfaction which occurred on 28 March could
somehow be taken as a matter of construction to
entitle the applicant to determine the contract as
the applicant now wishes to contend, there are
findings which have not been attacked to the effect
that the essential character of time in respect ofthose matters was lost by reason of the applicant's
conduct after 29 March.
We draw Your Honours' attention in that regard
to the discussion of the point in relation to
Havenbar v Butterfield and Mehmet v Benson at
pages 89 to 90 in application book B4. The discussion commences strictly, I suppose, with
respect, at the bottom of page 88 in the lastparagraph, but it takes up the present point on
page 89 above the citation of Mehmet v Benson and
Havenbar v Butterfield and continues at the bottom
of 89 in the paragraph which commences:
Of the application of those principles,
the present transaction provides an ample
illustration. Once 29 March 1991 had arrived and passed, the purchaser not only failed to
take steps to communicate an election to
rescind by reason of non-fulfilment of the
| Sanwa | 21 | 10/4/92 |
original contractual conditions by the
specified completion date, but it continued to
take affirmative and active steps that fully
acknowledged the continuing existence of the
contract.
Your Honours, Acting Justice Robin expressed
similar views at pages 37 point 7 to 39 point 2,
which we do not take Your Honours to at the moment.
We make the point because, with respect, our
learned friend's contentions and the contentionsthey seek to agitate in the notice of appeal, which
would go forward if leave were granted, are doomed,
with respect, to fail because whatever success they
may have on the construction argument, there areconcurrent findings which, as we say with respect,
are not attacked, that any essential character that
may have attached to Mr Rudkin's exercise was lost
by the other side's conduct. Your Honours, unless
there is something that Your Honours wish to raise
with us, those are our submissions.
| DEANE J: | Thank you, Mr Keane. | Yes, Mr Sofronoff? |
| MR SOFRONOFF: | Your Honours, could I address only on the |
submission that we abandoned before the Full Court
or elsewhere: the contentions that we had been
seeking to raise relating to the town planning
points. The position before the Full Court was that it emerged in debate during argument that if
the date for completion was, as my client asserted
it to be, still 29 March, then on any view the
rezoning obligations had not been fulfilled on any
view because they were, on the plaintiff's own
case, fulfilled view later.
So it was not necessary to argue their
fulfilment if that was the conclusion the court
came to. If the court came to the conclusion that the contract was an open one, then it was not
necessary to argue them because in the event, the time for completion had not arrived. Because of that discussion during argument, the points were not argued before the Full Court and, as appears
from the last page of the reasons of the Full
Court, the court came to the conclusion that the
contract was an open one and the points did not
arise or, rather, the obligations had not yetarisen for fulfilment.
If the point had been abandoned, we submit it
would have clearly emerged from the reasons that they had been abandoned. If the points had been
abandoned, it is inexplicable why Mr Justice Byrne
would have directed the sending of the letter that
he did direct.
| Sanwa | 22 | 10/4/92 |
Before the Court of Appeal, I was invited to
say what was my client's position with respect to
making submissions about the rezoning points. My
submission was that the appeal did not·properly
throw them up for consideration, although they
could be dealt with ultimately within a short time,
that is to say, days or weeks if the court couldfind an opportunity. Alternatively, if the court
was against that, we could be ready within 24
hours. The court said that if they required submissions on it, they would let us know.
In the event, they held against us, dismissed
the appeal without recourse to those matters, but in the course of doing so, they made reference to the fact that if those submissions had been made
and had been successful, that might have helped.
So we put the written submissions in that
Their Honours refer to in the paper that
Your Honours were taken to, where the president
refers to further submissions having been made.
We submit that we continually reserved those
points. We sought to raise them before Mr Justice de Jersey. That did not work, and we
did not abandon them before the Full Court or the
Court of Appeal. That is all I wanted to addressupon, Your Honour.
DEANE J: Thank you, Mr Sofronoff. These two applications
for special leave to appeal have been heard
together. As regards the first of them, the Court is of the view that the prospects of an appeal
succeeding on the question of the construction ofthe variation agreement which would lie at the forefront of such an appeal is insufficient to
warrant a grant of special leave.
As regards the second application for special
leave to appeal, the Court considers it would be
quite inappropriate to grant special leave to appeal in all the circumstances of this case.
MR KEANE: | Your Honours, we would ask for orders for costs in relation to each application. |
DEANE J: Mr Sofronoff?
| MR SOFRONOFF: | I can say nothing about that, Your Honour. |
| DEANE J: Very well. | The application is refused in each |
case with costs.
| Sanwa | 23 | 10/4/92 |
The Court would like to compliment counsel on
both sides for the manner in which they have
identified the real points in complicated
applications, and we are appreciative of it.
AT 12.03 PM THE MATTER WAS ADJOURNED SINE DIE
| Sanwa | 24 | 10/4/92 |
Key Legal Topics
Areas of Law
-
Contract Law
-
Civil Procedure
Legal Concepts
-
Appeal
-
Breach
-
Contract Formation
-
Jurisdiction
-
Remedies
-
Statutory Construction
0
0