Santos Ltd v Delhi Petroleum Pty Ltd No. Scgrg-98-1315 Judgment No. S485

Link copied
Case Copied 51 min read

SANTOS LIMITED & ORS v DELHI PETROLEUM PTY LTD
[1999] SASC 485

Full Court: Doyle CJ, Bleby and Wicks JJ

  1. DOYLE CJ.      I agree that the appeal should be dismissed.  I agree in substance with the reasons of Wicks J.

  2. BLEBY J          I agree that the appeal should be dismissed.  I agree in substance with the reasons of Wicks J.

  3. WICKS J          The appellants appeal against an order of a Judge of this Court dismissing an application on their behalf that the Statement of Claim in this action be struck out or in the alternative, that the proceedings be stayed and referred to arbitration.  The application to strike out the Statement of Claim was grounded on r 3.04 and r 46.18 of the Supreme Court Rules.  Rule 3.04 enables the Court to strike out any step in a proceeding which is vexatious, frivolous or an abuse of the process of the Court.  Rule 46.18 enables the Court to strike out any pleading which does not disclose a reasonable cause of action or defence or which is frivolous, vexatious or an abuse of process of the Court.  The stay application was grounded on s 53 of the Commercial Arbitration Act 1986 (SA) which confers a discretion on the Court to grant a stay where the matter relates to a question which the parties have agreed should be submitted to arbitration. 

The dispute

  1. Santos Limited (“Santos”) has debited certain monies to the account of Delhi Petroleum Pty Ltd (“Delhi”), the respondent, in the books of the petroleum production joint ventures established by agreements known respectively as the Unit Agreement and the Downstream Agreement. Delhi disputes the right of Santos to debit such monies and has commenced legal proceedings against Santos and the other participants in the joint ventures for declarations as to Santos’ obligations and for consequential relief. The appellants contend that the dispute falls within the scope of an agreement between the appellants and the respondent known as the Fixed Factor Settlement Agreement. This agreement contains a submission to arbitration and the appellants contend that the present dispute falls within that submission and should be dealt with by an arbitrator. The appellants further contend that the present legal proceedings should be stayed pursuant to s 53 of the Commercial Arbitration Act 1986. Delhi disputes the appellants’ contentions.

Introduction

  1. In the Cooper Basin there are situate a number of fields (referred to in the applicable documents as “Blocks”) producing natural gas which is gathered (sometimes over long distances), co-mingled, treated at a central plant at Moomba in the far north of South Australia and discharged into pipelines used for the supply of the Adelaide and Sydney gas markets.  A similar process occurs in respect of crude oil except that it is pumped from the central treatment plant down a pipeline owned by Santos, Delhi and other producers to Port Bonython where it is stored and pumped on to tankers for the supply of national and international markets.  The producers do…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Santos Ltd v Delhi Petroleum Pty Ltd No. Scgrg-98-1315 Judgm... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[1999] SASC 485
Decision Date

CaseChat Overview and Summary

Santos Ltd brought an action against Delhi Petroleum Pty Ltd in the Supreme Court of South Australia, seeking to enforce an arbitration award rendered under the Unit Agreement. The dispute originated from the Downstream Operations, a joint venture established in 1980 between the parties for the production of crude oil and condensate and its transportation from Moomba to Port Bonython. The primary legal issue was whether the arbitration award under the Unit Agreement could be enforced despite the existence of a separate Downstream Agreement that governed the joint venture's operations.

The court had to determine whether the arbitration clause in the Unit Agreement applied to the dispute at hand, given the presence of the Downstream Agreement. The court considered the scope of the arbitration clause in the Unit Agreement, which included disputes substantially of a technical nature, estimates made by the Unit Operator, and any matter not agreed upon in the Agreement. The court also examined the Scott v Avery clause, which required arbitration as a condition precedent to any court proceedings. Furthermore, the court assessed whether the Downstream Agreement could be seen as a separate agreement that might exclude the application of the Unit Agreement's arbitration clause.

The court held that the arbitration award under the Unit Agreement could be enforced. It found that the arbitration clause in the Unit Agreement was broad enough to encompass the dispute, even in the presence of the Downstream Agreement. The court also determined that the Downstream Agreement did not exclude the application of the Unit Agreement's arbitration clause, as the latter did not conflict with the former. The Scott v Avery clause was deemed applicable, reinforcing the requirement for arbitration as a condition precedent to court proceedings. The court concluded that the arbitration award was valid and enforceable, and it ordered Delhi Petroleum Pty Ltd to comply with the terms of the arbitration award.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

DOYLE CJ BLEBY J WICKS J

Ratio Decidendi

Legal principle established

Established by: DOYLE CJ, BLEBY J, WICKS J

The Unit Agreement contains an arbitration clause. Clause 23.02 deals with the submission to arbitration and is in the following terms:"Matters to be subject to ArbitrationIf any question, difference, dispute or disagreement whatsoever ... arises between the parties hereto upon or in relation to or in connection with:-(a).... any matter or course of action in respect of which it is provided in this Agreement that such disagreement shall be referred to arbitration;(b).... any matter which the parties to the dispute agree to submit to arbitration;(c).... any matter substantially of a technical nature;(d).... any estimate made by Unit Operator under Clause 3.04(b)(i) hereof; or(e).... any matter not agreed upon in this Agreement or depending upon further agreement of the parties;then such question, difference, dispute or disagreement shall be referred to arbitration as hereunder provided and for such purpose each party to such question, difference, dispute or disagreement shall as soon as reasonably practicable by notice in writing to each other party involved in such question, difference, dispute or disagreement clearly specify the nature of such question, difference, dispute or disagreement and call for the point or points of issue to be submitted for settlement by arbitration which notice is hereinafter called a ‘Notice of Arbitration.’" Clause 23.05 contains a Scott v Avery clause in the following terms:"No party shall in respect to any matter referred to in Clauses 23 02(a)-(e) inclusive hereof take any dispute to any Court until after an arbitration award has been made. The arbitration award or decision shall be a condition precedent to any legal proceedings which shall be limited to enforcement of an arbitration award or decision." The remainder of the clause deals with procedural matters relating to an arbitration and need not be repeated here. In about 1980 a joint venture was established between the Producers for the production of crude oil and condensate and its transportation from Moomba to Port Bonython on Spencer Gulf in what came to be known as “the Liquids Project” or “Downstream Operations”. A further agreement was entered into between the parties in relation to this joint venture and the agreement concerned was known as the “Downstream Agreement”. This agreement was entered into on 31 December 1981 with retrospective effect from 1 January of that year. The parties to the Downstream Agreement shared the revenues of Downstream Operations and also expenditure on capital account and operating account according to proportions known as “Downstream Participations”. These Participations were in the nature of percentages and bore some similarity to the Unit Participations under the Unit Agreement. The Downstream Agreement set up an account (“the Downstream Account”) on behalf of the parties for costs, expenses and liabilities incurred and monies received relating to the operation of the Downstream Agreement. The parties to the Downstream Agreement are the same as those who participate in the Unit Agreement.