| CITATION: | Sand & Surf Design Pty Ltd v Surrey & Anor [2014] QCATA 225 |
| PARTIES: | Sand & Surf Design Pty Ltd (Applicant/Appellant) |
| v | |
| Kevin Surrey Alexis Surrey (Respondents) |
| APPLICATION NUMBER: | APL209-14 |
| MATTER TYPE: | Appeals |
| HEARING DATE: | 12 August 2014 |
| HEARD AT: | Brisbane |
| DECISION OF: | Senior Member Oliver Member Dr Cullen |
| DELIVERED ON: | 22 August 2014 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. Insofar as leave to appeal is necessary it is granted. 2. The Tribunal’s decision of the 17 April 2014 is set aside. 3. It is declared that the contract entered into between the parties dated 23 June 2013 was lawfully terminated by the applicant on 28 October 2013. |
| CATCHWORDS: | BUILDING CONTRACTS – TERMINATION – where contrary to the terms of the contract homeowners disturbed the building site – whether concrete footing system compromised – where findings of fact that footing system “disturbed” – whether warranties under the building contract and the Domestic Building Contracts Act invalidated – where obligation of builder to comply with law under the contract – where builder issued a Notice of Variation to replace the footing system – whether reasonable to issue notice – where homeowners alleged the conduct of the building was repudiatory – whether the homeowners termination of the contract was lawful in the circumstances – where tribunal failed to have regard to all of the evidence on termination. Queensland Civil and Administrative Tribunal Act 2009 (Qld)s 146 Foran v Wight (1989) 168 CLR 385 |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Self represented by Mr Ferguson |
| RESPONDENTS: | Self represented |
REASONS FOR DECISION
The applicant is a registered builder. Mr Ferguson is a director of the applicant and dealt with the respondents. On 23 June 2013 the applicant and the Surreys entered into a Master Builders Residential Building Contract for the applicant to construct a residential dwelling at 55 Forbes Road, Sandy Creek. A deposit was paid and work commenced in July 2013.
Following some initial earthworks and preparation of the building pad, the applicant set about constructing a footing system for the house. The footing system was comprised of a number of concrete piers with metal casting support brackets. The brackets were to take stumps upon which the flooring system would be constructed with bearers and joists. The pier footing system was completed by the end of July. Subsequent to this, in late August, the applicant says that the Surreys brought machinery onsite to undertake further earthworks.
The machine(s) worked inside the timber profiles setting out the job and around the pier footing system. Mr Ferguson was concerned that the presence of machinery around the concrete piers may have compromised the integrity of the concrete footings. There was a dispute about this and ultimately the respondents purported to terminate the building contract on 17 October 2013. This was followed by the Applicant’s purported termination on 28 October 2013.
Soon after the purported terminations,…
Keep reading for free
Create a free CaseChat account to read Sand & Surf Design Pty Ltd v Surrey & Anor and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] QCATA 225
- Decision Date
CaseChat Overview and Summary
The court examined whether the homeowners' actions in disturbing the building site constituted a breach of contract. It was found that the footing system was indeed disturbed, which led to the invalidation of warranties under both the building contract and the Domestic Building Contracts Act. The court also considered the builder's obligation to comply with legal requirements as stated in the contract. The builder had issued a Notice of Variation to address the disturbed footing system, which the court assessed for reasonableness. Additionally, the homeowners argued that the builder's conduct amounted to repudiation, justifying their termination of the contract. The court found that the tribunal had not adequately considered all evidence regarding the termination.
The court concluded that the homeowners' termination of the contract was lawful given the builder's failure to comply with the contract and legal obligations. The tribunal's decision was set aside, and it was declared that the contract was lawfully terminated by the homeowners on 28 October 2013. The court granted leave to appeal and set aside the tribunal's decision, highlighting the importance of considering all relevant evidence when assessing contract termination.
Orders
Orders of the court
1. Insofar as leave to appeal is necessary it is granted.
2. The Tribunal’s decision of the 17 April 2014 is set aside.
3. It is declared that the contract entered into between the parties dated 23 June 2013 was lawfully terminated by the applicant on 28 October 2013.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.