SUPREME COURT OF QUEENSLAND
CITATION:
Saipem Australia Pty Ltd v GLNG Operations Pty Ltd [2017] QSC 294
PARTIES:
SAIPEM AUSTRALIA PTY LTD
(applicant)
v
GLNG OPERATIONS PTY LTD
(respondent)FILE NO/S:
SC No 7659 of 2017
DIVISION:
Trial Division
PROCEEDING:
Application for interlocutory injunction
DELIVERED ON:
8 December 2017
DELIVERED AT:
Brisbane
HEARING DATE:
27 October 2017
JUDGE:
Holmes CJ
ORDER: 1. The application for an injunction is refused.
2. The applicant is to pay the respondent’s costs.CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT –CONSTRUCTION OF PARTICULAR CONDITIONS – SECURITY AND RETENTION FUNDS – where the applicant contracted with the respondent to build a pipeline – where cl 5.5(a) of the contract provided for the respondent to use the proceeds of performance securities to recover any debt due from, or loss resulting from default by, the applicant – where the respondent alleged that the pipeline was defective and removed the rectification work from the applicant – where the respondent sought to recover the costs of rectification from the securities – where cl. 34.6 of the contract provided that the costs of rectification work would become a debt due and payable on notice being given and could be recovered from the securities – whether the costs were recoverable immediately on being incurred
EQUITY – EQUITABLE REMEDIES – INJUNCTIONS – INTERLOCUTORY INJUNCTIONS – SERIOUS QUESTION TO BE TRIED – BALANCE OF CONVENIENCE – where the applicant contracted with the respondent to build a pipeline – where cl 5.5(a) of the contract provided for the respondent to use the proceeds of performance securities to recover any debt due from, or loss resulting from default by, the applicant – where the applicant sought an interlocutory injunction to restrain the respondent from using the security proceeds – whether s 67J of the Queensland Building and Construction Commission Act 1991 applies to unliquidated amounts so as to require notice of the proposed use of the securities and the amount of the costs within 28 days of their being incurred – whether, if so, notice was given – whether a notice given in breach of s 67J is invalid – whether the exception in s 67J(4), where work is taken out of the contractor’s hands, applied – whether there are serious questions to be tried – where the applicant contended that it would suffer reputational damage if the respondent called on the securities – where the applicant covenanted not to seek to restrain the respondent from using the security proceeds – where the balance of convenience lies.
Queensland Building and Construction Commission Act 1991 (Qld) s 67J, s 67E(3)
Beyfield Pty Ltd v Northbuild Construction Sunshine Coast [2014] QSC 12
Saipem Australia Pty Ltd v GLNG Operations Pty Ltd (No. 2) [2016] 1 QdR 254
Monadelphous Engineering Pty Ltd & Anor v Wiggins Island Coal Export Terminal Pty Ltd [2014] QCA 330
COUNSEL: R A Holt QC and P Somers for the applicant
S Doyle QC and M Lyons for the respondent
Keep reading for free
Create a free CaseChat account to read Saipem Australia Pty Ltd v GLNG Operations Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QSC 294
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
1. The application for an injunction is refused.
2. The applicant is to pay the respondent’s costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Section 67E(2) of the Act deals with inconsistencies between building contracts and the Act, while s 67E(3) deals particularly with inconsistencies between contract provisions for security and provisions of the Act. 67E Operation of pt 4A…(2) However, if a building contract, or a provision of a building contract, is inconsistent with a provision (the Act provision) of this part applying to the building contract, the building contract, or the provision of the building contract, has effectonly to the extent it is not inconsistent with the Act provision.(3) Without limiting subsection (2), a building contract is unenforceable against the contracted party for the contract to the extent that the contract provides for retention amounts or security in a way that is inconsistent with a condition to which the contract is subject under division 2.Section 67J is contained in Division 2. “Condition” includes a limitation or restriction.[1] Section 108D of the Act prevents parties from contracting out of the Act’s provisions.[1] Schedule 2 Queensland Building and Construction Commission Act. The building contract and GLNG’s claims re rectification work The contract between Saipem and GLNG for the erection of the pipeline contained provision, in cl. 5.5(a), for GLNG to“… use the proceeds of any Performance Security to recover any Loss suffered or incurred by [GLNG] as a result of [Saipem]’s default under this Contract, or to recover any debt due from [Saipem] to [GLNG].” “Loss” was defined in cl. 1.1, the definitions clause, as “any loss, cost, expense, damage or liability of any kind”. Clause 5.5(c) contained Saipem’s covenant that it would not take any steps to restrain GLNG from demanding, receiving or using payment under the performance securities, even where it disputed GLNG’s right to payment and had commenced dispute resolution proceedings. Clause 5.5(d) provided that GLNG’s right to call on any performance security in accordance with cl. 5.5 was “without loss of any other rights under the contract to receive payments of the outstanding amounts”. Clause 34.4 of the contract enabled GLNG to direct Saipem to rectify any defect. In June 2016, GLNG issued a notice alleging that the corrosion protection system for the pipeline was defective and directing Saipem to rectify it. If Saipem, given such a rectification direction, failed to comply, cl. 34.6(a) permitted GLNG, after giving notice, to remedy the defect at Saipem’s expense. Clause 34.6(b) provided:“…(b) the actual and demonstrable costs of rectification work incurred by [GLNG] under clause 34.6(a): (1) will be a debt due and payable immediately by [Saipem] to [GLNG] following Notice from [GLNG] of the costs incurred; and(2) may be recovered by [GLNG], either by setting off the relevant amount from future payments due to [Saipem] (whether under this Contract or another Agreement), or by having access to the Performance Security.” Saipem responded by denying that a valid direction had been given under cl. 34.4. By letter of 22 July 2016, GLNG gave notice under clause 34.6 that it would remedy the defects at Saipem’s expense, advising that the “actual and demonstrable costs” of doing so would be a debt due and payable immediately upon notice being given of the costs incurred, and could be recovered by GLNG from the performance security proceeds. The letter was expressed to be a notice under s 67J, although GLNG specified that it did not concede that the provision applied. On 19 August 2016, GLNG advised that it intended to call on the guarantees in respect of the costs of rectifying the defects. It gave an estimate of the costs of the initial work required at $1,500,000 but advised that it would issue notices pursuant to cl. 34.6(b)(1) setting out the actual costs of the works.