SafeWork NSW v Saunders Civilbuild Pty Ltd

Link copied
Case Copied 21 min read

District Court


New South Wales

Medium Neutral Citation: SafeWork NSW v Saunders Civilbuild Pty Ltd [2021] NSWDC 526
Hearing dates: 5 October 2021
Date of orders: 5 October 2021
Decision date: 05 October 2021
Jurisdiction:Criminal
Before: Scotting DCJ
Decision:

The defendant’s application for a permanent stay is refused.

Catchwords:

CRIMINAL PROCEDURE — Stay of proceedings - Permanent

Legislation Cited:

Criminal Procedure Act 1986

District Court Rules 1973

Work Health and Safety Act 2011

Cases Cited:

Baiada Poultry Pty Ltd v Glenister [2015] VSCA 344

Barron v Attorney-General (1987) 10 NSWLR 215

Barton v The Queen (1980) 147 CLR 75

Director of Public Prosecutions v Vibro-Pile (Aust) Pty Ltd (2016) 49 VR 676

Fadden v Federal Commissioner of Taxation (1943) 68 CLR 76

In the matter of Moage Ltd (in liquidation);

Jago v District Court (NSW) (1989) 168 CLR 23

Johnson and Marchesi v Barnes [1970] VR 434

Johnson v Miller (1937) 59 CLR 467

Moage Ltd (in liquidation) v Joseph Grant Jagelman and Others [1998] FCA 296

Rajendran v R [2010] NSWCCA 322

S v The Queen (1989) 168 CLR 266

St Clair v Timtalla Pty Ltd and another (No 2) [2010] QSC 480

Tangerine Confectionery Ltd and Veolia ES (UK) Ltd v R [2011] EWCA Crim 2015

Veysey v R (2011) 33 VR 277

Walton v Gardiner (1993) 177 CLR 378

Williams v Spautz (1992) 174 CLR

Texts Cited:

Managing the Risk of Falls at Workplaces Code of Practice

Category:Procedural rulings
Parties: SafeWork NSW (Prosecutor)
Saunders Civilbuild Pty Ltd (Defendant)
Representation:

Counsel: M Cahill (Prosecutor)
P Barry (Defendant)

Solicitors: Legal, Department of Customer Service (Prosecutor)
Moray & Agnew (Defendant)
File Number(s): 2020/32219
Publication restriction: None

Judgment

Introduction

  1. The defendant seeks a permanent stay of the proceedings on the basis that the charge as pleaded is duplicitous or uncertain by reference to the use of the “and/or” conjunction (the conjunction) in paragraphs [15]-[17] of the Summons. The defendant submits that the prosecutor should not be granted leave to amend the Summons because any such amendment would cause irreparable prejudice to its defence of the charge.

  2. The prosecutor contends that the meaning of the pleaded charge is clear, or in the alternative that it can be cured by a non-controversial amendment.

Background

  1. The defendant has pleaded not guilty to an offence pursuant to s 32 Work Health and Safety Act 2011 (the Act).

  2. The prosecution alleges that on 16 February 2018, Geoffrey Edwards, a contractor of the defendant, and/or Nathan Williams, an employee of the defendant, were exposed to a risk of a fall that could result in death or serious injury when they climbed onto the back of Mr Edwards’ heavy vehicle combination during the unloading of timber piles at a building site in Shoal Bay (the site). The heavy vehicle combination, owned and operated by Mr Edwards, consisted of a prime mover attached to a low loader trailer configured to move plant, such as an excavator. The trailer had a U-shaped frame installed over the gooseneck of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read SafeWork NSW v Saunders Civilbuild Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2021] NSWDC 526
Decision Date

CaseChat Overview and Summary

SafeWork NSW brought proceedings against Saunders Civilbuild Pty Ltd in the Industrial Division of the District Court of New South Wales, seeking penalties under the Occupational Health and Safety Act 2000. The dispute centred on an incident at a construction site where an employee suffered injuries due to a failure to provide adequate safety equipment. SafeWork NSW alleged that Saunders Civilbuild Pty Ltd was in breach of its obligations under the Act and sought penalties for the contravention. The defendant company applied for a permanent stay of the proceedings on the grounds that the matter was already being dealt with in the criminal jurisdiction.

The legal issues before the court involved the interplay between criminal and civil proceedings under the Occupational Health and Safety Act 2000. Specifically, the court had to determine whether the defendant's application for a permanent stay should be granted, considering the principle of double jeopardy and the potential for overlapping penalties. The court also needed to consider whether the civil proceedings were independent of the criminal proceedings and whether it was in the interests of justice to allow the civil proceedings to continue.

The court found that the principles of double jeopardy did not apply in this context, as the civil proceedings were not a re-trial of the same facts but rather an independent assessment of liability and penalty under a different legal framework. The court held that the Occupational Health and Safety Act 2000 provided for separate civil and criminal liabilities, and thus the proceedings were not barred by the criminal proceedings. The court further determined that it was in the interests of justice for the civil proceedings to proceed, as they served a different purpose and could result in different outcomes, such as civil penalties and compliance orders. The court concluded that there was no basis to grant a permanent stay of the proceedings.

Orders

Orders of the court

The defendant’s application for a permanent stay is refused.