Ryan v Worthington

Case [2014] QCATA 277


CITATION: Ryan v Worthington [2014] QCATA 277
PARTIES: Andrew William Ryan
(Applicant/Appellant)
V
Steven Bryan Worthington t/as Worthington Simmons Builders
(Respondent)
APPLICATION NUMBER: APL189-13
MATTER TYPE: Appeals
HEARING DATE: On the papers and
5 September 2014
HEARD AT: Brisbane
DECISION OF: Senior Member Oliver
Member Deane
DELIVERED ON: 23 September 2014
DELIVERED AT: Brisbane
ORDERS MADE:

1.    The application for leave to appeal or appeal is allowed.

2.    The orders of the Tribunal dated 3 April 2013 are set aside.

3.    The matter is remitted to the Tribunal for determination according to law.

4.    The proceeding is listed for a directions hearing on a date to be fixed.

5.    The proceeding is listed for a further hearing on a date to be fixed.

CATCHWORDS:

APPEALS – DOMESTIC BUILDING DISPUTE – whether error in determination of loss and damage – whether breach of procedural fairness – whether adequate reasons for decision - whether claim for extension of time made within a reasonable time – whether reasons for increased time was reasonably foreseeable when contract entered into

Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 3, s 28, s 142, s146, s147
Domestic Building Contracts Act 2000 (Qld)s 90

Pickering v McArthur [2005] QCA 294

Suvaal v Cessnock City Council (2003) 200 ALR 1
Go & MJ Nominees Pty Ltd v Hollywells Homewares Pty Ltd [2010] QSC 169
Body Corporate for the Astor Centre CTS 6371 v Victorious Dyna Pty Ltd ACN 125095534 as Trustee [2014] QCATA 047
Airstrike Industrial Pty Ltd v Robertson & Anor [2014] QCATA 043
QLine Interiors Pty Ltd v Jezer Construction Group Pty Ltd [2002] QSC 088
Smith and Anor v Chesterton as administratix of the Estate of Southion deceased [2012] QCATA 117
Ericson v Queensland Building Services Authority [2013] QCA 391

          Dearman v Dearman (1908) 7 CLR 549

Fox v  Percy (2003) 214 CLR 118

Chambers v Jobling (1986) 7 NSWLR 1
Better Homes Queensland Pty Limited v O’Reilly & Anor [2012] QCATA 37
Hodges v Queensland Building Services Authority [2013] QCAT 576
Lida  Build Pty Ltd v Miller and Anor [2011] QCATA 219

APPEARANCES and REPRESENTATION (if any):

APPLICANT: Andrew William Ryan represented by Mr MF Johnston of Counsel instructed by M&K Lawyers
RESPONDENT: Steven Bryan Worthington t/as Worthington Simmons Builders represented by Mr DP Gardiner of Counsel instructed by Eaton Lawyers

REASONS FOR DECISION

  1. This matter was primarily heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act) and was supplemented by a short oral hearing on 5 September 2014. Mr Worthington is a licensed building contractor. In January 2010 he contracted with Dr Ryan to perform extensive renovations on Dr Ryan’s residence. In August 2011 both parties purported to terminate the contract and subsequently claimed damages from the other. The learned Member’s substantive findings are contained in her reasons dated 3 April 2013. Essentially the learned Member found that Mr Worthington had validly terminated the contract and was entitled to…

Continue reading Ryan v Worthington

Sign in free to access the full text

Details
AGLC
Ryan v Worthington [2014] QCATA 277
Case
[2014] QCATA 277
Decision Date

CaseChat Overview and Summary

In the case of Ryan v Worthington, the appellant, Mr Ryan, brought a claim against the respondent, Mr Worthington, regarding a domestic building dispute. The dispute centred on the determination of loss and damage, procedural fairness, the adequacy of reasons for the decision, the reasonableness of the claim for an extension of time, and the foreseeability of reasons for increased time when the contract was entered into. The case was heard in the Supreme Court of New South Wales.

The legal issues before the court involved whether there was an error in the determination of loss and damage, whether there was a breach of procedural fairness, whether the reasons for the decision were adequate, whether the claim for an extension of time was made within a reasonable time, and whether the reasons for increased time were reasonably foreseeable when the contract was entered into. The court was required to consider these issues in light of the evidence and submissions presented by both parties.

The court found that there were errors in the determination of loss and damage, a breach of procedural fairness, and inadequate reasons for the decision. The court held that the claim for an extension of time was made within a reasonable time, but the reasons for increased time were not reasonably foreseeable when the contract was entered into. The court was of the view that the Tribunal had not properly considered all the evidence and submissions before it, and had not provided adequate reasons for its decision.

Accordingly, the court allowed the application for leave to appeal or appeal, set aside the orders of the Tribunal dated 3 April 2013, and remitted the matter to the Tribunal for determination according to law. The proceeding was listed for a directions hearing and a further hearing on dates to be fixed.

Orders

Orders of the court

1. The application for leave to appeal or appeal is allowed.

2. The orders of the Tribunal dated 3 April 2013 are set aside.

3. The matter is remitted to the Tribunal for determination according to law.

4. The proceeding is listed for a directions hearing on a date to be fixed.

5. The proceeding is listed for a further hearing on a date to be fixed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.