RWA Developers Pty Ltd v Auburn Council

Case [2003] NSWLEC 445


>

Land and Environment Court


of New South Wales


CITATION: RWA Developers Pty Ltd v Auburn Council [2003] NSWLEC 445
PARTIES:

APPLICANT:
RWA Developers Pty Ltd

RESPONDENT:
Auburn Council
FILE NUMBER(S): 10009 of 2003
CORAM: Bignold J
KEY ISSUES: Appeal - Development Consent :- Refusal of Development Consent
LEGISLATION CITED: Environmental Planning and Assessment Act 1979, s 97
CASES CITED:
DATES OF HEARING: 26/03/2003
EX TEMPORE
JUDGMENT DATE :

03/26/2003
LEGAL REPRESENTATIVES:


APPLICANT:
Mr R M O'Gorman-Hughes, Solicitor

SOLICITORS
Deacons

RESPONDENT:
Mr S N Griffiths, Solicitors

SOLICITORS
Pike Pike and Fenwick



JUDGMENT:


IN THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES

BIGNOLD J

26 March 2003

10009 of 2003 RWA DEVELOPERS PTY LIMITED V AUBURN COUNCIL

JUDGMENT

HIS HONOUR

1. This is an appeal pursuant to of the Environmental Planning and Assessment Act, s 97 against the determination of the Council refusing development consent to an application to demolish an existing warehouse building situate at premises known as No 7, Samuel Street, Lidcombe, and to erect a residential flat building on the site containing some eight flats.

2. The matter comes to the Court today upon earlier notice that the parties had settled the case and were asking the Court to give effect to that settlement. To that extent consent orders have been handed up to the Court, which propose by consent the upholding of the appeal, the granting of development consent to the aforesaid development, subject to conditions of consent which have been prepared and a document to be annexed to the short minutes.

3. The settlement is the culmination of negotiations between the parties following the lodgement of the original development application, which had been the subject of the Council’s prior determination refusing development consent. The Council took that course despite recommendations from its planners that approval be granted subject to deferred commencement conditions nominated in the planning report.

4. The application had been notified to the public both in its original form and in the two subsequent amended forms that it has taken. On no occasion has any objection been received by the Council either in respect of the original or the first amendment or the second amendment. It is the second amended plans that are before the Court today for which consent is sought and to which the draft consent orders are addressed.

5. Following the filing of the appeal the developer entered into negotiations with the Council with a view to resolving the matters that had caused the Council’s original decision to refuse development consent. In particular the developer addressed the two matters concerning site contamination, clean up and stormwater drainage, which had been the subject of the planner’s recommendations for deferred commencement conditions, and other aspects which had informed the Council’s decision to refuse consent.

6. These matters are summarised in a report prepared by the Council’s development team leader, Mr Gordon Edgar, a copy of which report has been tendered as Annexure B. In that report, Mr Edgar concludes that the amended proposal has been fully assessed in accordance with s 79C of the Act, that the reasons for the original decision refusing consent and the outstanding issues that had been previously highlighted which had originally resulted in a recommendation for the imposition of deferred commencement conditions have all been resolved to the satisfaction of the Council. It was in those circumstances that he recommended that the Council enter into the consent orders which are now before the Court.

7. I am satisfied, particularly in light of the two planning reports of the Council’s servants which have come into evidence, exhibits A and B, that it is entirely appropriate for the Court to give effect to the settlement reached between the parties as is reflected in the short minutes of order which have been prepared by the parties’ legal representatives and signed by them, which I too shall sign and place with the Court papers.

8. Accordingly, by consent, I make the orders set forth in the short minutes. Those short minutes include, as Annexure A, the detailed conditions of development consent agreed between the parties. The exhibits shall be retained by the Court. Gentlemen, with your leave I just altered Order 3 to give effect to that order. I note that the plans referred to in Condition 1 of the conditions of approval are the plans being Exhibit 1 in these proceedings.

Details
AGLC
RWA Developers Pty Ltd v Auburn Council [2003] NSWLEC 445
Case
[2003] NSWLEC 445
Decision Date

CaseChat Overview and Summary

In the Land and Environment Court of New South Wales, the case of RWA Developers Pty Ltd v Auburn Council dealt with an appeal against the refusal of development consent by Auburn Council. The applicant sought to demolish an existing warehouse at No 7, Samuel Street, Lidcombe, and replace it with a residential flat building containing eight units. The Council had refused consent despite recommendations from its planners for approval subject to deferred commencement conditions. The applicant subsequently entered into negotiations with the Council to address the concerns that had led to the refusal of consent, resulting in a settlement between the parties.

The key legal issue before the court was whether to uphold the settlement reached between the parties, which proposed granting development consent subject to certain conditions. The court had to consider whether the settlement adequately addressed the concerns that had led to the Council's refusal of consent and whether it was appropriate to give effect to the consent orders prepared by the parties' legal representatives.

Bignold J, who presided over the case, concluded that the settlement was appropriate and should be given effect. The court was satisfied with the two planning reports prepared by the Council's servants, which concluded that the amended proposal had been fully assessed and that the outstanding issues had been resolved to the satisfaction of the Council. The court signed the consent orders prepared by the parties' legal representatives, which included the detailed conditions of development consent agreed upon. The plans referred to in the conditions were to be retained by the court.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.