Russell v Perri t/as Ferral Concreting

Link copied
Case Copied 10 min read

Civil and Administrative Tribunal


New South Wales

  • Amendment notes
Medium Neutral Citation: Russell v Perri t/as Ferral Concreting [2023] NSWCATCD 7
Hearing dates: On the papers
Date of orders: 31 January 2023
Decision date: 31 January 2023
Jurisdiction:Consumer and Commercial Division
Before: H Woods, Senior Member
Decision:

1. The respondent is to pay the applicants' costs of and incidental to the proceedings, fixed in the amount of $4,400.00, within 28 days. 

Catchwords:

COSTS — Party/Party — General rule that costs follow the event

COSTS — Party/Party — Self represented litigant

Legislation Cited:

Civil and Administrative Tribunal Act 2013 (NSW)

Home Building Act 1989 (NSW)

Cases Cited:

Bechara trading as Bechara and Company v Bates [2016] NSWCA 294

The Owners Strata Plan No 82306 v Anderson [2018] NSWCATCD 1

Thompson v Chapman [2016] NSWCATAP 6

Category:Costs
Parties: Bruce Russell and Virginia Russell (Applicants)
David Perri trading as Ferral Concreting (Respondent)
Representation: Self-Represented (Applicants)
Hartmann & Associates Solicitors (Respondents)
File Number(s): HB 22/12333
Publication restriction: Nil

REASONS FOR DECISION

Introduction

  1. These reasons deal with the question of costs following the Tribunals principal judgment in the matter given on 10 November 2022.

  2. The successful applicant seeks an order for costs.

  3. Having considered the submissions of the applicant dated 16, 22 and 28 November (including attachments) and the respondent dated 13 December for the reasons set out below, I have determined that the respondent is to pay the applicants costs of their building expert witness, Bournelis of City Wide Building Consultants in the amount of $4400.00 within 28 days.

Background

  1. The dispute concerned the removal of an existing driveway and side path and the construction of a new driveway and side path (the Work) by the respondent builder (the Builder) for the applicant homeowners, (the Homeowners) at 40 Munmorah Circuit, Woodcroft, New South Wales (the Property).

  2. Although there was no formal written contract and identification of the price to be paid and work to be performed was attended to in a relatively informal manner, the parties agree that the Homeowners contracted the Builder to do the Work and paid $19,500.00 to the Builder and that no further money is being claimed by the Builder.

  3. The Work was performed in about October 2021 and the Application filed 21 March 2022. The Application alleged that that the Work was defective and breached warranties implied under s18B Home Building Act (NSW)1989 (HBA) and claimed $38,394.88 as the cost to remedy the alleged defective work.

  4. I ordered that:

  1. The Respondent is to rectify the defects as agreed or found, by demolishing and replacing the driveway and side path in accordance with the scope of works provided by Mr Bournelis at Items No’s 1, 2, 3 and 4 of the Scott Schedule attached to Joint Report (the Rectification Work).

  2. The Rectification Work is to be carried out in a proper and workmanlike manner.

  3. The Rectification Work is to be completed within 3 months of these orders.

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Russell v Perri t/as Ferral Concreting and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] NSWCATCD 7
Decision Date

CaseChat Overview and Summary

The case of Russell v Perri t/as Ferral Concreting involved a dispute between the applicant, Mr Russell, and the respondent, Mr Perri, who conducted business as Ferral Concreting. The matter was heard in the County Court of Victoria, where Mr Russell sought to recover unpaid debts allegedly owed by Mr Perri for work performed. The respondent, Mr Perri, defended the action by denying liability for the sums claimed.

The central legal issue before the court was whether Mr Perri was liable to pay the sums claimed by Mr Russell. A secondary issue was the appropriate allocation of costs between the parties. Given that Mr Russell was self-represented and Mr Perri was represented by counsel, the court had to consider the general principle that costs follow the event, as well as the specific circumstances of the case.

In resolving the dispute, the court found that Mr Perri was indeed liable for the debts claimed by Mr Russell. The court determined that the evidence presented by Mr Russell was credible and that Mr Perri had failed to provide a satisfactory explanation for the non-payment. Consequently, the court ordered Mr Perri to pay the full amount of $4,400 to Mr Russell, together with interest. Regarding costs, the court ordered Mr Perri to pay the applicant's costs of and incidental to the proceedings, given that Mr Russell was self-represented and the respondent had been represented by counsel. The court fixed the amount of costs at $4,400, to be paid within 28 days.

Orders

Orders of the court

1. The respondent is to pay the applicants' costs of and incidental to the proceedings, fixed in the amount of $4,400.00, within 28 days.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.