Ruhle v Lormist Pty Ltd

Link copied
Case Copied 9 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATON:

Ruhle v Lormist Pty Ltd [2022] QCAT 100

PARTIES:

STEPHEN SCOTT RUHLE

(first applicant)

CYNTHIA JOY RUHLE
(second applicant)

v

LORMIST PTY LTD

(respondent)

APPLICATION NO/S:

BDL053-21

MATTER TYPE:

Building matters

DELIVERED ON:

2 February 2022

HEARING DATE:

On the papers

HEARD AT:

Brisbane

DECISION OF:

Senior Member Brown

ORDERS:

1.     The application for miscellaneous matters filed 19 October 2021 is allowed.

2.     Stephen Scott Ruhle and Cynthia Joy Ruhle must file in the Tribunal two copies and give to Lormist Pty Ltd one copy of an amended application by 4:00pm on 16 February 2022.

3.     The amended application must identify the quantum of Stephen Scott Ruhle’s and Cynthia Joy Ruhle’s claim.

4.     Lormist Pty Ltd must file in the Tribunal two copies and give to Stephen Scott Ruhle and Cynthia Joy Ruhle one copy of a response to the amended application by 4:00pm on 2 March 2022.

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – where the respondent opposed an application brought by the applicant for leave to amend an application for domestic building disputes – where the respondent contended that the shed structure, the subject of the amended claim, constituted a farm building and the dispute was not a domestic building dispute – consideration of ‘tribunal work’, jurisdiction of the tribunal in respect of ‘building disputes’ and the meanings of ‘domestic building work’ and ‘associated work’ under the Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act) – where the tribunal finds that the amended claim did not concern a farm building and that it is reasonably arguable that the subject of the amended claim falls within the meaning of a domestic building dispute – consideration of commercial building dispute.

ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – consideration of whether applicant required to comply with s 77(2) of the QBCC Act in relation to amended claim before it can be determined by the tribunal – finding by the tribunal that s 77(2) does not require compliance with a QBCC process every time there is a material change in the particulars and scope of a building dispute once proceedings have been commenced.

Queensland Building and Construction Commission Act 1991 (Qld) s 75, s 76, s 77(2), sch 1B, s 1, s 4(3), s 4(4)(c), s 13, sch 2

APPEARANCES & REPRESENTATION:

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)

REASONS FOR DECISION

  1. On 2 February 2022 I decided an application for miscellaneous matters by the applicants for leave to file an amended application for domestic building disputes. These are my reasons.

  2. The proceedings were commenced as a minor civil dispute in May 2020. In February 2021 the proceedings were transferred to the building list, it being apparent that the dispute between the parties is a domestic building dispute.

  3. At a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ruhle v Lormist Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] QCAT 100
Decision Date

CaseChat Overview and Summary

The parties involved in this case are Stephen Scott Ruhle and Cynthia Joy Ruhle, the applicants, and Lormist Pty Ltd, the respondent. The dispute revolves around the construction of an extension to the shed on the applicants' land. The applicants filed an amended claim to broaden the scope of the existing dispute. The Queensland Civil and Administrative Tribunal was tasked with determining whether the amended claim constituted a domestic building dispute and whether the applicants needed to comply with a particular statutory process before the tribunal could hear the amended claim.

The legal issues before the tribunal included whether the shed extension constituted a farm building, thereby excluding it from the tribunal's jurisdiction over domestic building disputes. The tribunal also considered whether the amended claim fell within the definition of a domestic building dispute under the Queensland Building and Construction Commission Act 1991 (Qld). Additionally, the tribunal examined whether the applicants were required to follow a specific statutory process every time there was a material change in the particulars and scope of the dispute, once proceedings had already been initiated.

The tribunal concluded that the amended claim did not pertain to a farm building and that it was reasonably arguable that the subject matter of the amended claim fell within the definition of a domestic building dispute. The tribunal found that the statutory process did not need to be followed every time there was a material change in the particulars and scope of a dispute, once proceedings had already been started. Consequently, the application for leave to amend the application was allowed, and the applicants were required to file an amended application that specified the quantum of their claim. The respondent would then have the opportunity to file an amended response.

The tribunal ordered that the application for miscellaneous matters filed on 19 October 2021 be allowed. The applicants must file an amended application by 4:00pm on 16 February 2022, detailing the quantum of their claim. The respondent has until 4:00pm on 2 March 2022 to file an amended response.

Orders

Orders of the court

1. The application for miscellaneous matters filed 19 October 2021 is allowed.

2. Stephen Scott Ruhle and Cynthia Joy Ruhle must file in the Tribunal two copies and give to Lormist Pty Ltd one copy of an amended application by 4:00pm on 16 February 2022.

3. The amended application must identify the quantum of Stephen Scott Ruhle’s and Cynthia Joy Ruhle’s claim.

4. Lormist Pty Ltd must file in the Tribunal two copies and give to Stephen Scott Ruhle and Cynthia Joy Ruhle one copy of a response to the amended application by 4:00pm on 2 March 2022.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

The dispute between the parties relates to the construction of the extension to the shed on the applicants’ land. The building works involved both the construction of a slab and the construction of a structural extension to the shed. The proposed claim by the applicants simply enlarges the scope of the existing dispute. The construction of s 77(2) argued for by the respondent is rejected. Conclusion The application for miscellaneous matters is allowed. I will make orders for the filing of an amended application for domestic building disputes by the applicants. The amended application must particularise the quantum of the applicants’ claim. The respondent will be given the opportunity to file an amended response.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.