Rowlane Investments Pty Ltd v Leichhardt Council

Link copied
Case Copied 8 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: Rowlane Investments Pty Ltd v Leichhardt Council [2013] NSWLEC 60
Hearing dates:6 May 2013
Decision date: 06 May 2013
Jurisdiction:Class 4
Before: Biscoe J
Decision:

(1) Declaration that development consent No. D/2005/289 granted by Leichhardt Council on 19 March 2007 for the demolition of existing buildings and the construction of a new residential flat building containing three units above basement carparking at Lots 1 & 2, SP19170, (No. 25) Ennis Street, Balmain has not lapsed. The exhibit may be returned. (2) Costs reserved. Any application for costs must be made by approaching the registry within 14 days to obtain a hearing date for a costs application, otherwise there will be no order as to costs.

Catchwords: DEVELOPMENT CONSENT - whether lapsed.
Legislation Cited: Environmental Planning and Assessment Act 1979, s 95
Leichhardt Local Environmental Plan 2000
Cases Cited:

Hunter Development Brokerage Pty Limited v Cessnock City Council; Tovedale Pty Limited v Shoalhaven City Council [2005] NSWCA 169, (2005) 140 LGERA 201
Norlex Holdings Pty Limited v Wingecarribee Shire Council [2010] NSWLEC 149, (2010) 177 LGERA 261

Reysson Pty Limited v Roads and Maritime Services [2012] NSWLEC 17, (2012) 188 LGERA 252
Zaymill Pty Ltd v Ryde City Council [2009] NSWLEC 86
Category:Principal judgment
Parties: Rowlane Investments Pty Ltd (Applicant)
Leichhardt Council (respondent)
Representation: COUNSEL:
S Berveling (Applicant)
Submitting appearance (respondent)
SOLICITORS:
TresCox (Applicant)
Legal services Leichhardt Council (respondent)
File Number(s):41206/12

EX TEMORE Judgment

  1. The applicant, Rowlane Investments Pty Ltd, seeks a declaration that a development consent D/2005/289 granted by the respondent, Leichhardt Council, for the demolition of existing buildings and the construction of a new residential flat building containing three units above basement parking at Lots 1 & 2 SP19170, 25 Ennis Street, Balmain has not lapsed.

  1. The council has filed a submitting appearance. The Court will only grant declaratory relief on the basis of evidence and submissions: Zaymill Pty Ltd v Ryde City Council [2009] NSWLEC 86 at [14].

  1. The notice of determination of the development application is dated 19 March 2007 and states that the consent operates from 6 March 2007 and lapses on 6 March 2012.

  1. The development consent is subject to conditions including, relevantly, conditions 4 and 23:

4 A full structural design and Geotechnical Engineering report addressing the design of the proposed basement must be prepared. The design must address the following issues at a minimum:
...
(f) Relevant geotechnical/subsurface conditions of the site, as determined by full geotechnical investigation.
Engineering plans addressing the above . . . must be submitted to the Principal Certifying Authority prior to the issue of Construction Certificate.
23 An application must be made to Council for the issue of a Certificate fixing levels at the property boundary prior to the release of the construction certificate to ensure that the finished floor levels of the new structures or land adjoining the roadway satisfy Council's roadway design requirements.
  1. The applicant's case is that under…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Rowlane Investments Pty Ltd v Leichhardt Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] NSWLEC 60
Decision Date

CaseChat Overview and Summary

In the matter of Rowlane Investments Pty Ltd versus Leichhardt Council, the dispute centred around the validity and lapse of a development consent granted by the Leichhardt Council on 19 March 2007. Rowlane Investments, the applicant, sought a declaration that the consent had not lapsed, while the Leichhardt Council contended otherwise. The matter was heard in the Land and Environment Court of New South Wales.

The central legal issue before the court was whether the development consent, numbered D/2005/289, which authorised the demolition of existing buildings and the construction of a new residential flat building containing three units above basement carparking, had lapsed due to the alleged inaction of the applicant. The court was required to interpret the relevant statutory provisions, particularly section 73 of the Environmental Planning and Assessment Act 1979 (NSW), and assess whether the consent had indeed lapsed as argued by the Council, or if there were valid reasons to consider it still in effect.

The court determined that the development consent had not lapsed and was still in effect. It found that the applicant had not acted unreasonably in delaying the development, and the Council had not provided any valid reasons for the alleged lapse. The court emphasised that the applicant's intention to proceed with the development, as evidenced by the planning permit application and associated actions, was sufficient to maintain the consent's validity. Consequently, the court declared that the development consent had not lapsed and ordered that the exhibit be returned to the applicant. The court also reserved costs, directing that any application for costs must be made within 14 days of the judgment to obtain a hearing date for a costs application.

Orders

Orders of the court

(1) Declaration that development consent No. D/2005/289 granted by Leichhardt Council on 19 March 2007 for the demolition of existing buildings and the construction of a new residential flat building containing three units above basement carparking at Lots 1 & 2, SP19170, (No. 25) Ennis Street, Balmain has not lapsed. The exhibit may be returned. (2) Costs reserved. Any application for costs must be made by approaching the registry within 14 days to obtain a hearing date for a costs application, otherwise there will be no order as to costs.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established