NSW Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Rowland v Composition Construction Pty Ltd [2014] NSWCATCD 32 Hearing dates: 24 February 2014 Decision date: 14 March 2014 Jurisdiction: Consumer and Commercial Division Before: K Rosser, Senior Member Decision: Payment of damages
1. The respondent shall pay the applicant the sum of $500,000.00 by 14 April 2014.
2. The respondent shall pay the applicant's costs as agreed or assessed.
Catchwords: Home building; Termination of contract; Damages for defective and incomplete work; Liquidated damages; Damages for loss of use of money. Legislation Cited: Home Building Act (NSW) 1989
Civil and Administrative Tribunal Act (NSW) 2013
Consumer, Trader and Tenancy Tribunal Act (NSW) 2002
Consumer Trader and Tenancy Tribunal Regulation 2009Cases Cited: Hungerfords v Walker (1989) 171 CLR 125
Latoudis v Casey (1990) 170 CLR 534 and Oshlak v Richmond River Council 193 CLR 72Category: Principal judgment Parties: Neil Rowland (applicant)
Composition Construction Pty Ltd (respondent)Representation: Mr To of Counsel for the applicant, instructed by Watkins Tapsell Solicitors and Barristers
Mr Emans (director of the respondent) for the respondent
File Number(s): HB 11/48716
reasons for decision
Application
1. Mr Rowland seeks an order for damages in the sum of $500,000.00 from Composition Construction Pty Ltd [Composition Construction] in respect of the cost of rectification of defective works, completion costs, damages for loss of use of money and liquidated damages. The claim arises from a contract for residential building work dated 27 June 2010.
2. In response to the application, Competition Construction claims that it terminated the contract on 2 April 2014 because of breach by Mr Rowland and that Mr Rowland is therefore not entitled to completion costs and damages for loss of use of money. Composition Construction concedes some but not the entire claim in respect of defective work. In relation to liquidated damages, Composition Construction claims that delays in completion of the works were legitimate and that Mr Rowland had refused to accept applications for extensions of time.
Proceedings in the Tribunal
3. The proceedings were commenced 4 October 2011. The application was originally lodged as a cross-application to Composition Construction's application seeking an order requiring Mr Rowland to accept extensions of time and an order that it did not have to pay liquidated damages. (See HB 11/42940)
4. At that time, the contract between the parties was still on foot. The applications were listed for directions on a number of occasions at which time it was noted that the parties were in negotiations. Mr Rowland was put on notice that a claim in respect of damages for defective work could not proceed while the contract was on foot.
5. At a directions hearing on 27 August 2012, Composition Construction withdrew its application and directions were made for the filing and serving of evidence in relation to Mr Rowland's claim for defective work, completion costs and liquidated damages. Both parties were given leave to be represented.
6. At a directions hearing on 4 February 2013,…
Continue reading Rowland v Composition Construction Pty Ltd
Sign in free to access the full text
- AGLC
- Rowland v Composition Construction Pty Ltd [2014] NSWCATCD 32
- Case
- [2014] NSWCATCD 32
- Decision Date
CaseChat Overview and Summary
The court had to determine whether Rowland was entitled to damages for defective and incomplete work and whether those damages could include compensation for the loss of use of the money that should have been paid. The court also needed to consider whether the respondent was liable for liquidated damages, as stipulated in the contract.
The court found that Rowland was entitled to damages for the defective and incomplete work and that these damages could include compensation for the loss of use of the money that should have been paid. The court determined that the loss of use of money was a legitimate claim for damages, as it represented the opportunity cost of the respondent's failure to complete the work on time. The court held that the respondent was liable for liquidated damages, as specified in the contract, and ordered the respondent to pay Rowland the sum of $500,000.00 by a specified date. The court also ordered the respondent to pay Rowland's costs as agreed or assessed.
Orders
Orders of the court
Payment of damages
1. The respondent shall pay the applicant the sum of $500,000.00 by 14 April 2014.
2. The respondent shall pay the applicant's costs as agreed or assessed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.