Supreme Court
New South Wales
Medium Neutral Citation: Rogers Construction Group Pty Ltd v Mirage Interiors & Construction Pty Ltd [2024] NSWSC 1344 Hearing dates: 21 October 2024 Date of orders: 25 October 2024 Decision date: 25 October 2024 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Challenge to the Adjudication Determination fails
Catchwords: BUILDING AND CONSTRUCTION — Building and Construction Industry Security of Payment Act 1999 (NSW) — adjudication — contested result of adjudication — where plaintiff submits that adjudicator decided the determination on a basis not advocated or reasonably contemplated by either party — question of procedural fairness — denial of procedural fairness not found — challenge to adjudication determination fails
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Cases Cited: A-Civil Aust Pty Ltd v Ceerose Pty Ltd [2024] NSWCA 7
Demex Pty Ltd v McNab Building Services Pty Ltd [2023] NSWCA 261
Category: Principal judgment Parties: Rogers Construction Group Pty Ltd (Plaintiff)
Mirage Interiors & Construction Pty Ltd (First Defendant)
Patrick Tonkin trading as c/o Adjudicate Today Pty Ltd (Second Defendant)
Adjudicate Today Pty Limited (Third Defendant)Representation: Counsel:
Solicitors:
J R B Pearson (Plaintiff)
A Gandar (First Defendant)
Hicksons (Plaintiff)
Henry William Lawyers (First Defendant)
Lauderdale Construction Lawyers (Second and Third Defendant)
File Number(s): 2024/349179
JUDGMENT
-
The plaintiff, Rogers Construction Group Pty Ltd (the “Builder”), challenges an adjudication determination in the sum of $108,451.13, [1] under the Building and Construction Industry Security of Payment Act 1999 (NSW) (the “Act”) in favour of the first defendant, Mirage Interiors & Construction Pty Ltd (“Mirage”), on the basis that the Adjudicator decided the Adjudication Determination on a basis not advocated by either party and which neither party, particularly the Builder, could reasonably have contemplated.
1. Inclusive of GST.
-
An adjudicator under the Act must accord the parties procedural fairness when exercising his or her powers of adjudication. [2]
2. Demex Pty Ltd v McNab Building Services Pty Ltd [2023] NSWCA 261 at [9] (Kirk JA, Mitchelmore and Adamson JJA agreeing).
-
However, by reason of the structure and scheme of the Act, the “content of the requisite procedural fairness is reduced” and will only result in invalidity of an adjudication determination if there is a “significant departure from what would ordinarily be the requirements of procedural fairness for a person exercising a statutory power, and where the departure could be characterised as leading to substantial practical injustice in all the circumstances”. [3]
3. Ibid at [32].
-
There will rarely be a basis for quashing an adjudication determination for want of procedural fairness. [4]
4. See, for example, A-Civil Aust Pty Ltd v Ceerose Pty Ltd [2024] NSWCA 7 at [1] (Leeming JA).
-
My conclusion is that this is not one of those rare cases.
The Original Contract
-
The underlying contract was originally made in or about December 2023. The Builder engaged Mirage to effect services involving the supply and installation of walls, ceilings and partitions at the Busby Fire Station. I will…
Keep reading for free
Create a free CaseChat account to read Rogers Construction Group Pty Ltd v Mirage Interiors & Const... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NSWSC 1344
- Decision Date
CaseChat Overview and Summary
The court examined whether the adjudicator had breached any principles of natural justice or procedural fairness in reaching the decision. The court found that the adjudicator had not acted unfairly by deciding the case on a different basis than that argued by the parties. The court held that the adjudicator was entitled to consider all the evidence presented and to make findings of fact and law based on that evidence. The court also found that the plaintiff had not been deprived of an opportunity to respond to the matters considered by the adjudicator. The court concluded that there was no breach of procedural fairness and that the adjudicator's determination was valid.
The court dismissed the plaintiff's application to set aside the adjudicator's determination. The court held that the adjudicator had not acted outside the scope of the adjudication process and that the determination was not vitiated by any procedural unfairness. The court further held that the plaintiff was bound by the adjudicator's determination and could not challenge it on the basis of procedural fairness. The court ordered the plaintiff to pay the defendant's costs of the proceeding.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.