Supreme Court
New South Wales
Medium Neutral Citation: Rockdale City Council v Calibre Construction Corp Pty Ltd [2015] NSWSC 1980 Hearing dates: 17 November 2015 Date of orders: 23 December 2015 Decision date: 23 December 2015 Jurisdiction: Common Law Before: Fagan J Decision: Plaintiff’s claim dismissed
Catchwords: CONTRACTS – construction – conditions of development consent – contribution value – whether estimated contribution value was binding – whether quantity surveyor erred in determining contribution value of access road – scope of “construction of the road”
WORDS AND PHRASES – “construction of the road” – “structures”Legislation Cited: Environmental Planning and Assessment Act 1979 (NSW)
Road Transport (Mass, Loading and Access) Regulation 2005 (NSW)Cases Cited: Agricultural & Rural Finance Pty Ltd v Gardiner [2008] HCA 57; (2008) 238 CLR 570
APN (Outdoor Trading) Pty Ltd v Melbourne City Council [2012] VSC 8
Australian Vintage Ltd v Belvino Investments No 2 Pty Ltd [2015] NSWCA 275
Brambles Holdings Ltd v Bathurst City Council [2001] NSWCA 61; (2001) 53 NSWLR 153
Legal and General Life of Australia Ltd v A Hudson Pty Ltd (1985) 1 NSWLR 314
Ooralea Developments Pty Ltd v Civil Contractors (Aust) Pty Ltd [2013] QSC 254
Ward v Griffiths (1987) 9 NSWLR 458Category: Principal judgment Parties: Rockdale City Council (Plaintiff)
Calibre Construction Corp Pty Ltd (Defendant)Representation: Counsel:
Solicitors:
Jason Lazarus (Plaintiff)
Nigel Cotman SC (Defendant)
David Creais (Plaintiff)
Michael Ayache (Defendant)
File Number(s): 2015/117490 Publication restriction: Nil
Judgment
-
On 5 August 2009 the plaintiff, as consent authority under the Environmental Planning and Assessment Act 1979 (NSW) (“the Act”), granted to Brewster Murray Pty Ltd approval for a multi-storey residential development on a parcel of land within the plaintiff’s local government area. The subject site is at 9 – 11 Woolongong Road, Arncliffe in Sydney’s South-East (“the site”). Pursuant to s 94 of the Act the plaintiff required, as Condition 67 of the development consent, that the holder of the consent (“the developer”) should pay $2,132,763.18 by way of contribution towards the cost of local infrastructure and facilities.
-
The site has at all material times been owned by Mahmoud Mohanna and Mohammad Mouslimani. On 23 February 2005 Messrs Mohanna and Mouslimani caused the defendant to be incorporated as a special purpose vehicle to undertake all activities in relation to a proposed development of the site. In about March 2006 the defendant on behalf of the owners consented to Brewster Murray Pty Ltd, a firm of architects, making a development application. After the development consent had issued on 5 August 2009 to Brewster Murray Pty Ltd, in late 2010 either that company or the landowners authorised the defendant to act on the consent and appointed it as builder of the development. Upon the defendant receiving this authorisation and appointment it became bound by the conditions upon which that consent had been issued.
-
The development has now been completed by the defendant and the plaintiff claims from the defendant an alleged unpaid balance of the contribution sum referred…
Keep reading for free
Create a free CaseChat account to read Rockdale City Council v Calibre Construction Corp Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] NSWSC 1980
- Decision Date
CaseChat Overview and Summary
The court had to determine whether the term "construction of the road" in the development consent included the construction of certain structures. The council argued that the contribution value was binding and that the quantity surveyor's determination was incorrect, as it failed to account for the full cost of the access road, including the structures. Conversely, the construction company contended that the surveyor's assessment was accurate and that the term "construction of the road" did not necessarily encompass additional structures.
The court examined the terms of the development consent and the scope of the quantity surveyor's role. It found that the term "construction of the road" did not inherently include the construction of structures. The court concluded that the surveyor's determination of the contribution value was correct, as it accurately reflected the costs associated with the road itself, excluding additional structures. Therefore, the estimated contribution value was not binding to the extent that it included costs for structures not covered by the term "construction of the road."
The court's decision upheld the surveyor's assessment and clarified the scope of the term "construction of the road." As a result, the contribution value determined by the surveyor was not binding to the extent it included costs for structures not covered by the term. The final orders of the court reflected this determination, ensuring clarity in future dealings between the council and construction companies regarding development consents and contribution values.