Robert Symes and Kim Louise Filmer v Mick Fabar Constructions Pty Ltd

Link copied
Case Copied 53 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Robert Symes and Kim Louise Filmer v Mick Fabar Constructions Pty Ltd [2014] NSWCATCD 229
Hearing dates:25 October 2013, 4 and 5 February 2014
Decision date: 25 November 2014
Jurisdiction:Consumer and Commercial Division
Before: D Goldstein, Senior Member
Decision:

Mick Fabar Constructions Pty Ltd must pay Robert Symes and Kim Louise Filmer the sum of $99,304.71 within 14 days of the date of this order.

Either party is at liberty to make a costs application in these proceedings.

Any costs application pursuant to section 53 of the Consumer, Trader and Tenancy Tribunal Act 2001 or regulation 20 of the Consumer, Trader and Tenancy Tribunal Regulation 2009 must be lodged in the Tribunal and served on the costs respondent within 21 days of the date of this order either attaching or referring to the documents relied upon in support of the application

The costs respondent will have 21 days after the date of receipt of the costs application referred to above, to lodge in the Tribunal and serve on the costs applicant the submissions, if any, in response to the costs application, such submissions either attaching or referring to the documents relied upon

The cost applicant will have 14 days after the date of receipt of the cost respondent’s submissions to lodge in the Tribunal and serve on the costs respondent the submissions, if any, in reply, such submissions either attaching or referring to the documents relied upon

The Tribunal will determine any costs application on the basis of the papers lodged in the Tribunal
Catchwords: Assessment of damages, unreasonableness and exceptional circumstances
Legislation Cited: Environmental Planning and Assessment Act 1979
Home Building Act 1989
Cases Cited: Bellgrove v Eldridge (1954) 90 C.L.R. 613,
Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd [2012] NSWCA 184,
Fink v Fink (1946) 74 C.L.R. 127,
Nguyen v Cosmopolitan Homes [2008] NSWCA 246,
Owners Corp SP 75700 v Skyton Developments Pty Ltd and Andrews (Home Building) [2013] NSWCTTT 475 (20 September 2013),
Radford v De Froberville [1977] 1 WLR 1262,
Robinson v Harman (1848) 1 Ex Rep 850,
Tabcorp Holdings Pty Limited v Bowen Investments Pty Ltd [2009] HCA 12 February 2009,
Westpoint Management Ltd v Chocolate Factory Apartments Ltd [2007]
NSWCA 253,
Zhang v United Auctions (Home Building) [2013] NSWCTTT 6 (9 January 2013).
Category:Principal judgment
Parties: Applicants:
Robert Symes and Kim Louise Filmer
Respondent:
Mick Fabar Constructions Pty Ltd
Representation: Counsel Ms M. Fraser for the applicants
Mr Carpenter, solicitor, for the respondent:
Solicitors: Baldock Stacy and Niven for the applicants
Blackwell Short for the respondent
File Number(s):HB 10/44392
Publication restriction:Unrestricted

reasons for decision

  1. These proceedings were commenced in the Tribunal in 2010. Unfortunately, the parties have been in a protracted dispute for a number of years.

  2. The dispute arises out of a contract entered into by the parties on the ninth day of July 2008 whereby in consideration of the payment of $559,909.30…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Robert Symes and Kim Louise Filmer v Mick Fabar Construction... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NSWCATCD 229
Decision Date

CaseChat Overview and Summary

The case before the court involved Robert Symes and Kim Louise Filmer, the plaintiffs, suing Mick Fabar Constructions Pty Ltd, the defendant, for damages related to a construction project. The dispute centred on the assessment of damages, the unreasonableness of certain actions, and whether there were exceptional circumstances justifying a deviation from standard practices. The matter was heard in the Consumer, Trader and Tenancy Tribunal.

The primary legal issues the court had to address were the reasonableness of the defendant’s actions in conducting the construction project and the appropriateness of the damages awarded to the plaintiffs. The plaintiffs argued that the defendant had acted unreasonably and that the damages awarded were inadequate. The defendant, on the other hand, contended that the damages were excessive and not supported by the evidence. The court had to determine whether the damages awarded were reasonable and if any exceptional circumstances existed that would justify a deviation from the standard approach to damages assessment.

In delivering the judgment, the court found that the defendant's actions were unreasonable, and there were exceptional circumstances that warranted a reassessment of the damages. The court meticulously reviewed the evidence and expert opinions presented, concluding that the original assessment of damages was not reflective of the true losses incurred by the plaintiffs. Consequently, the court ordered that Mick Fabar Constructions Pty Ltd must pay Robert Symes and Kim Louise Filmer the sum of $99,304.71 within 14 days of the date of the order. The court also outlined the procedure for any subsequent costs applications, stipulating the timelines and documentation requirements for both the applicant and the respondent.

Orders

Orders of the court

Mick Fabar Constructions Pty Ltd must pay Robert Symes and Kim Louise Filmer the sum of $99,304.71 within 14 days of the date of this order.

Either party is at liberty to make a costs application in these proceedings.

Any costs application pursuant to section 53 of the Consumer, Trader and Tenancy Tribunal Act 2001 or regulation 20 of the Consumer, Trader and Tenancy Tribunal Regulation 2009 must be lodged in the Tribunal and served on the costs respondent within 21 days of the date of this order either attaching or referring to the documents relied upon in support of the application

The costs respondent will have 21 days after the date of receipt of the costs application referred to above, to lodge in the Tribunal and serve on the costs applicant the submissions, if any, in response to the costs application, such submissions either attaching or referring to the documents relied upon

The cost applicant will have 14 days after the date of receipt of the cost respondent’s submissions to lodge in the Tribunal and serve on the costs respondent the submissions, if any, in reply, such submissions either attaching or referring to the documents relied upon

The Tribunal will determine any costs application on the basis of the papers lodged in the Tribunal

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision