| CITATION: | Robert Genge v Paragon Portfolio Pty Ltd [2011] QCAT 234 |
| PARTIES: | Robert Genge t/a Jak Genge Building |
| v | |
| Paragon Portfolio Pty Ltd t/a Style Plantation Cairns |
| APPLICATION NUMBER: | BDL219-10 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 05 April 2011 |
| HEARD AT: | Brisbane |
| DECISION OF: | Anne Forbes, Member |
| DELIVERED ON: | 31 May 2011 |
| DELIVERED AT: | Brisbane |
ORDERS MADE: | 1. The Respondent shall pay to the Applicant, by way of damages, the sum of $26,906.00 within 28 days of service of this decision upon it. 2. Interest at the rate of 10 per centum per annum (10%) shall be payable upon the balance from time to time of said sum from the date of this decision until payment. |
| CATCHWORDS: | Building sub-contract – defective work – action by head contractor – respondent in breach of tribunal orders or directions – judgment by default |
APPEARANCES and REPRESENTATION (if any):
Decision determined on the papers.
REASONS FOR DECISION
Robert Genge filed this Application against the Respondent (“Paragon”) on 15 July 2010, seeking damages, interest and costs for breach of warranty and negligence, and alternatively for rectification of defective work.[1]
[1]The claim for rectification has been abandoned, as the Respondent no longer holds an appropriate builder’s licence.
The relevant contract was made on or about 16 April 2007. It was for the installation of bamboo strip flooring on the ground floor of a building constructed by the Applicant for Jan and Julian Warnock at 7 Lee Street, Freshwater, near Cairns. The contract price was $15,840.95, which the Applicant paid in full.
The Respondent commenced work on or about 24 April 2007 and finished on 21 December 2007. At that time the Respondent was licensed as a “low rise” builder, and held itself out as an experienced provider of bamboo flooring.
As the Applicant alleges, it was soon apparent that the Respondent’s work was sub-standard. In March 2008, just three months after completion, severe “cupping” and “ripping” affected the bamboo flooring of the entire ground floor at 7 Lee St Freshwater. Then, and on several subsequent occasions from 2008 to 2010, the Applicant requested the Respondent’s alter ego, Shane Kenneth Wegner, to rectify the faulty workmanship. No rectification or compensation has been forthcoming. The Warnocks complained to the Building Services Authority (“the BSA”) in February 2010; the BSA ordered the Respondent to make repairs within 28 days, but the Respondent did not comply.
In essence, the Applicant says that the problem was caused by the Respondent’s failure to waterproof properly the concrete slab on which the flooring was laid, or to “acclimatise” flooring before installation, or both. It is undisputed that, in October 2009, laboratory tests ordered by the Applicant disclosed a moisture content of 9.2% - 10.6% in 3 samples taken from the floor. A copy of the laboratory report was sent to the Respondent, but no remedial action followed.
The Applicant accepts that he is responsible to the building owners to remedy the allegedly…
Keep reading for free
Create a free CaseChat account to read Robert Genge v Paragon Portfolio Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] QCAT 234
- Decision Date
CaseChat Overview and Summary
The tribunal considered the evidence presented by Genge regarding the defective work and the respondent's failure to rectify the issues as directed. The tribunal noted that the respondent had been found in breach of certain tribunal orders and had not participated in the proceedings. Given this, the tribunal ruled that the respondent was liable for the damages claimed by Genge. The tribunal found that the respondent had not provided a satisfactory explanation for their non-compliance and had thus acted unreasonably. The tribunal also determined that the respondent's failure to address the defects amounted to a breach of the sub-contract and the tribunal's orders.
In its decision, the tribunal ordered the respondent to pay Genge the sum of $26,906.00, representing the damages for the defective work, within 28 days of the decision being served. Additionally, the tribunal imposed interest at the rate of 10% per annum on the outstanding balance from the date of the decision until payment. The tribunal emphasised the importance of adhering to tribunal orders and the consequences of failing to do so. This case underscores the significance of timely and effective compliance with legal directives in construction sub-contracts and the tribunal's role in enforcing such compliance.
Orders
Orders of the court
1. The Respondent shall pay to the Applicant, by way of damages, the sum of $26,906.00 within 28 days of service of this decision upon it.
2. Interest at the rate of 10 per centum per annum (10%) shall be payable upon the balance from time to time of said sum from the date of this decision until payment.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.