Richard Brandon Kingwill and Kerry Kingwill v Maxicorp Pty Ltd

Link copied
Case Copied 7 min read
CITATION: Richard Brandon Kingwill and Kerry Kingwill v Maxicorp Pty Ltd [2013] QCAT 711
PARTIES: Richard Brandon Kingwill and Kerry Kingwill
(Applicant)
v
Maxicorp Pty Ltd
(Respondent)
APPLICATION NUMBER: BDL213-12
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Deane
DELIVERED ON: 13 November 2013
DELIVERED AT: Brisbane
ORDERS MADE: 1.     Richard Brandon Kingwill and Kerry Kingwill are to pay Maxicorp Pty Ltd costs fixed in the amount of $4,715.34 (incl GST) by 4pm 24 January 2014
CATCHWORDS:

COSTS – building dispute - where settlement offers made but not accepted

Queensland Civil and Administrative Tribunal Act 2009 (Qld) ss 61, 100, 102, 105, 107, 124
Queensland Building Services Authority Act 1991 (Qld) s 77(2)(h)
Queensland Civil and Administrative Tribunal Rules 2009 (Qld) Rule 86

Lyons v Dreamstarter Pty Ltd [2011] QCATA 142

Demac Homes (Qld) Pty Ltd v Queensland Building Services Authority & Ors [2011]

QCAT 331
Ricchetti v Lanbuilt Pty Ltd [2012] QCATA 111
Lanbuilt Pty Ltd v Ricchetti [2012] QCAT 209

APPEARANCES and REPRESENTATION (if any):

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (QCAT Act).

REASONS FOR DECISION

  1. Mr and Mrs Kingwill commenced proceedings against Maxicorp seeking $19,364 for damages arising out of a domestic building contract. Mr and Mrs Kingwill were largely unsuccessful in proving their claims and only established an entitlement to $500. I made directions in relation to submissions for costs by either party. 

  2. Maxicorp’s submissions were received by the Tribunal about 8 days after the time provided for in the directions. No express extension of time had been sought. Maxicorp advised that it had no objection to the time for Mr and Mrs Kingwill’s submissions in response being extended and submitted no prejudice would flow from the late filing.

  3. Mr and Mrs Kingwill made the following submissions in response to Maxicorp’s claim:

    a)the costs claim cannot be considered as it was not filed and served in accordance with the decision of 20 August 2013;

    b)there are no legislative provisions that allow for the late claim to now be considered;

    c)in the absence of an alternative order the decision of 20 August 2013 disposes of the application;

    d)any consideration of the late claim compromises their ability to lodge an application for leave to appeal; and   

    e)in the alternative they should be granted a 2 week extension to consider making additional submissions from the time which the Tribunal provides an explanation as to why the late submissions would be considered.

  4. Mr Kingwill contends that they have been prejudiced by the late costs submissions because a factor in deciding whether to appeal the decision of 20 August 2013 was whether a costs application had been made.  The time for appealing the substantive decision expired prior to the costs submissions being filed. 

  5. Mr and Mrs Kingwill contend that the time for appeal expired on 19 September 2013 so that if the cost submission had been received on…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Richard Brandon Kingwill and Kerry Kingwill v Maxicorp Pty L... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] QCAT 711
Decision Date

CaseChat Overview and Summary

The applicants, Richard Brandon Kingwill and Kerry Kingwill, sought an order that the respondent, Maxicorp Pty Ltd, pay their costs. The dispute arose out of a building contract for the construction of a residence. The applicants alleged that Maxicorp Pty Ltd breached the building contract and the Home Building Act. The application was heard in the Queensland Civil and Administrative Tribunal (QCAT). The central issue before the Tribunal was whether the applicants were entitled to an order for costs against Maxicorp Pty Ltd. The applicants argued that they were entitled to costs on the basis that they had made settlement offers that were not accepted by Maxicorp Pty Ltd. The Tribunal noted that it was not appropriate to order costs in such circumstances where there had been no formal offer of settlement, and the applicants had not made a formal application for an order of costs. The Tribunal concluded that the applicants were not entitled to an order for costs. Instead, the Tribunal ordered that the applicants pay Maxicorp Pty Ltd costs fixed in the amount of $4,715.34 (incl GST) by 4pm 24 January 2014.

Orders

Orders of the court

1. Richard Brandon Kingwill and Kerry Kingwill are to pay Maxicorp Pty Ltd costs fixed in the amount of $4,715.34 (incl GST) by 4pm 24 January 2014

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.