Supreme Court
New South Wales
Medium Neutral Citation: Reward Interiors Pty Ltd v Master Fabrication (NSW AU) Pty Ltd [2020] NSWSC 1251 Hearing dates: 11 September 2020 Date of orders: 14 September 2020 Decision date: 14 September 2020 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Defendant’s notice of motion of 30 July 2020 dismissed with costs
Catchwords: BUILDING AND CONSTRUCTION – payment claim served by subcontractor on builder under Building and Construction Industry Security of Payment Act 1999 (NSW) – no payment schedule served by builder – alleged agreement between sub-contractor and builder that builder pay amount less than the amount claimed in payment claim in satisfaction of payment claim – where builder then paid agreed amount – whether that agreement void by reason of s 34 of the Act
BUILDING AND CONSTRUCTION – whether subcontractor entitled to summary judgment for difference between amount claimed in payment claim and amount paid pursuant to the agreement
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Practice Note SC Eq 3
Cases Cited: Multiplex Constructions Pty Ltd v Luikens and Anor [2003] NSWSC 1140
The Minister for Commerce (formerly Public Works & Services) v Contrax Plumbing (NSW) Pty Ltd & Ors [2005] NSWCA 142
Texts Cited: Robert McDougall, “Prohibition on Contracting Out of the Building and Construction Industry Security of Payment Act (NSW)” (2006) 22 BCL 246.
Category: Procedural and other rulings Parties: Reward Interiors Pty Ltd (Plaintiff/Respondent)
Master Fabrication (NSW AU) Pty Ltd (Defendant/Applicant)Representation: Counsel:
Solicitors:
D Weinberger (Plaintiff/Respondent)
HWL Ebsworth Lawyers (Plaintiff/Respondent)
CCS Legal Pty Ltd (Defendant/Applicant)
File Number(s): 2020/187009
Judgment
-
The plaintiff, Reward Interiors Pty Ltd, is a building contractor. The defendant, Master Fabrication (NSW AU) Pty Ltd is a subcontractor.
-
Reward sues Master for damages arising out of work done by Master, as subcontractor, in relation to the construction of a primary school in Schofields.
-
By its cross claim [1] Master claims $64,504 being the amount allegedly due by reason of service by Master on Reward of a payment claim under s 13 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (“the Act”).
1. Originally a claim made in the Local Court but transferred to this Court by orders made on 6 July 2020.
-
Now, by notice of motion filed on 30 July 2020, and despite the exhortation in the Practice Note against the making of such applications,[2] Master seeks summary judgment for that amount and to strike out the relevant paragraphs of Reward’s cross claim defence. [3]
2. Practice Note SC Eq 3 at [62].
3. Originally its defence in the local Court proceedings.
-
On 29 February 2020 Master served on Reward a payment claim for $566,285.61.
-
Reward did not serve a payment schedule under s 14 of the Act in response to that payment claim.
-
However, on 31 March 2020, Mr Mayank Patel from Master sent an email to Mr David Ashcroft from Reward stating that “the total payable amount for the February 2020…
Keep reading for free
Create a free CaseChat account to read Reward Interiors Pty Ltd v Master Fabrication (NSW AU) Pty L... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] NSWSC 1251
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the agreement between Reward Interiors and Master Fabrication was void under section 34 of the Act, and if Reward Interiors was entitled to summary judgment for the difference between the amount claimed in the payment claim and the amount paid. The court had to determine whether the Act precluded any agreement that resulted in a lower payment than the amount claimed in the payment claim, and if such an agreement would render the payment made under it invalid. Additionally, the court needed to assess whether Reward Interiors could obtain summary judgment for the shortfall.
The court held that section 34 of the Act did not render the agreement between Reward Interiors and Master Fabrication void. The court found that the Act did not preclude an agreement between the parties that resulted in a payment less than the amount claimed, provided that such an agreement was reached in good faith. The court further held that the payment made by Master Fabrication under the agreement was valid and not void under the Act. As for the summary judgment, the court found that Reward Interiors was not entitled to it because the Act did not provide for summary judgment for the difference between the amount claimed and the amount paid. The court concluded that Reward Interiors would need to pursue the shortfall through other means available under the Act.
In conclusion, the court determined that the agreement between Reward Interiors and Master Fabrication was not void under section 34 of the Act, and that Reward Interiors was not entitled to summary judgment for the difference between the amount claimed and the amount paid. The court’s decision underscored the importance of good faith in agreements under the Building and Construction Industry Security of Payment Act 1999 (NSW) and clarified the remedies available to subcontractors in such circumstances.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi