Restifa Pty Ltd v Sutherland Shire Council

Case

[2009] NSWLEC 1267

7 August 2009

No judgment structure available for this case.

Land and Environment Court


of New South Wales


CITATION: Restifa Pty Ltd v Sutherland Shire Council & ors [2009] NSWLEC 1267
PARTIES:

APPLICANT
Restifa Pty Ltd

RESPONDENT
Sutherland Shire Council

INTERVENOR
(admitted under s38(2) of the Land and Environment Court Act ,1979)
Westfield Ltd and Supabarn Supermarket Pty Ltd
FILE NUMBER(S): 10696 of 2008
CORAM: Tuor C - Taylor C
KEY ISSUES: SECTION 97 APPEAL :- appeal for deemed refusal of a development application for a mixed use development.
Proper planning framework, weight to be given to draft LEP and DCP and other planning documents,
Consistency with LEP and DCP and strategic framework,
Economic impact of retail development and whether assessment adequate
Water quality of compensatory waterbody for ecological and recreational purposes.
LEGISLATION CITED: Environmental Planning and Assessment Act, 1979; Environment Protection and Biodiversity Conservation Act, 1999; Land and Environment Court Act 1979; Threatened Species Conservation Act, 1995. Sutherland Shire Development Control Plan 2006; Sutherland Shire Local Environmental Plan, 2006. State Environmental Planning Policy No 1
CASES CITED: Aldi Foods v Holroyd City Council [2004] NSWLEC 253
Blackmore Design Group Pty Ltd v North Sydney Council [2001] NSWLEC 279
Bongiorno Hawkins Frassetto & Associates Pty Ltd v Griffith City Council [2007] NSWLEC 205
GPT Limited v Belmorgan Property Development Pty Ltd [2008] NSWCA 256
Kavia Holdings Pty Limited v Sydney City Council [2003] NSWLEC 195
Morrison Design Partnership Pty Limited v North Sydney Council and Director General of the Department of Planning [2007] NSWLEC 802
Stockland Development Pty Ltd v Manly Council [2004] NSWLEC 472
Terrace Tower Holdings v Sutherland Shire Council (2003) 129 LGERA 195
The Village McEvoy v City of Sydney Council [2009] NSWLEC 1232
Zhang v Canterbury Council (2001) 51 NSWLR 589
DATES OF HEARING: 16, 17, 18, 19, 20, 23 February; 3, 9 April; 30 June; 1, 2 July. Written submissions 16, 20, 31 July 2009
 
DATE OF JUDGMENT: 

7 August 2009
LEGAL REPRESENTATIVES:

APPLICANT
Mr A Galasso SC with Ms S Duggan, barrister
INSTRUCTED
by Gadens

RESPONDENT
Mr T Robertson SC
INSTRUCTED
by HWL Ebsworth

INTERVENOR
Mr Hutley SC with Mr Larkin, barrister
INSTRUCTED
by Mallesons and Freehills

JUDGMENT:


      THE LAND AND
      ENVIRONMENT COURT
      OF NEW SOUTH WALES

      Tuor C with Taylor C

      7 August 2009

      10696 of 2008 Restifa Pty Ltd v Sutherland Shire Council

      JUDGMENT

1 COMMISSIONERS: This is an appeal against the deemed refusal by Sutherland Shire Council (the council) of a development application under the Environmental Planning and Assessment Act 1979 (the Act) for a mixed use development at 566-594 Princes Highway, Kirrawee (the site).

2 The issues raised by council relate principally to the impact of the proposed retail development on the role and function of Kirrawee and Sutherland Centres. Council also contends that the proposal does not address adequately a number of urban design and landscape issues and the compensatory habitat water body (the pond) to be provided on the site is unresolved. The parties also did not agree on the extent of traffic management works to be provided.

The site

3 The site is known as the Kirrawee Brick Pit and has a frontage to the north to the Princes Highway (252m), to the south to Flora Street (251m), to the west to Oak Street (160m). To the east the site adjoins the industrial premises that form part of the James Cook Industrial Estate.

4 The site is approximately 4.2 ha in area and slopes from south west to north east with a fall of approximately 10m.

5 Situated in the northern part of the site are remnants of foundations of the Brick Foundry, which existed on the site from the 1900s ceasing production in the 1970s. An electricity substation is located near these remains to the north of the site.

6 About a third of the site is occupied by the disused quarry, which has become a lake with depths of up to 10m to 15m. The lake is a source of water for the Grey Headed Flying Fox and the Eastern Bent winged Bat.

7 Remnant Sydney Turpentine-Ironbark Forest is located along the southern and western boundaries of the site.

8 The locality is characterised by residential development being a mixture of single dwellings and residential flat buildings to the east and north east and industrial development to the west, south and north of the site. Kirrawee centre is located to the south east and Kirrawee Railway station is walking distance from the site. Sutherland centre is about 1.4 km from the site.

Planning framework

9 The majority of the site is within Zone 7 Mixed Use - Kirrawee under Sutherland Local Environmental Plan 2006 (LEP 2006), which is where the mixed use development is proposed. The remainder and western part of the site is within Zone 13 – Public Open Space and is where the park and the pond are to be developed.

10 Mixed use premises are permissible with consent within Zone 7. LEP 2006 defines mixed use premises as:

          Mixed use premises means a building that is used both for a land use having a residential purpose and for another non – residential land use that is permissible with or without consent .

11 The objectives of Zone 7 are:

          (a) to take advantage of the zone’s access and profile from the Princes Highway,
          (b) to create development that mixes employment activities within a liveable urban environment,
          (c) to encourage high employment-generating development that encompasses high technology industries, commercial display centres and light industries compatible with the existing locality and adjoining residential buildings,
          (d) to allow the zone to support a live-and-work culture that provides for local employment and acts as a transition between employment activity and strict residential uses in the surrounding neighbourhood,
          (e) to permit light industrial uses that are compatible with the desired future residential amenity of the zone,
          (f) to ensure the design of all residential buildings is of a high architectural quality and all residential buildings have an attractive streetscape setting,
          (g) to ensure development is carried out in a way that addresses the street concerned (achieving an attractive and vibrant streetscape) and reinforces surveillance of the public domain,
          (h) to make provision for a prestigious gateway development capable of employing a substantial workforce,
          (i) to provide a substantial area of public open space for employees, residents and the local community,
          (j) to facilitate the re-vitalisation of the Kirrawee Town Centre and the Kirrawee railway station precinct,
          (k) to ensure any expansion of retail activity within the zone maintains the role and function of Kirrawee Town Centre and does not adversely impact on the sustainability of other centres in the Sutherland Shire,
          (l) to ensure any new shops integrate with and support the existing Kirrawee Town Centre,
          (m) to ensure development is compatible with, and does not adversely impact on, the amenity of the surrounding residential area, particularly in terms of air pollutants, noise emissions and visual effects.

12 Amendment 4 to LEP 2006 (LEP 2006 Amendment 4) was gazetted on 9 January 2009, which is after the development application was lodged. LEP 2006 Amendment 4 made a number of general amendments including changes to the definition of “gross floor area” to exclude the parking and access required by council. LEP 2006 Amendment 4 also made specific changes to Zone 7, it added objectives (k), (l) and (m). It also deleted convenience stores and added vehicle and mechanical repair premises and light industries to the permissible uses in Zone 7.

13 Clause 58 of LEP 2006 is a savings provision which provides:


          A development application made, but not finally determined, before the commencement of Sutherland Shire Local Environmental Plan 2006 (Amendment No 4) is to be determined as if the plan had been exhibited but had not been made.

14 The parties agree that as LEP 2006 Amendment 4 has been gazetted it is imminent and certain but disagreed on the weight to be given to the amendments to Zone 7, which we discuss in the Strategic issue below. We find that the proper planning approach is that the proposal should be consistent with the planning framework established by LEP 2006 Amendment 4.

15 LEP 2006 includes other relevant clauses in relation to building height (cl 33), building density (cl 35), landscape area (cl 36), urban design – general (cl 48), and urban design – residential buildings (cl 49). The proposal does not comply with the building height and building density controls and the applicant has submitted an objection under State Environmental Planning Policy No 1 (SEPP 1). Council did not press the non compliance with these controls as an issue in the proceedings.

16 Sutherland Development Control Plan 2006 (DCP 2006) is also relevant. Chapter 2 includes Locality Strategies for areas in Sutherland Shire, including Kirrawee (Clause 1) and Sutherland Centre (Clause 2).

17 Chapter 3 – Urban Design of DCP 2006 provides objectives and controls for development. Clause 9.a.3 provides the following objective for Floor Space Mix in the Mixed Use – Kirrawee Zone:

          to ensure that the scale and intensity of retail development within the mixed use zone does not undermine the function of the Kirrawee Local Centre as the town centre of the locality, nor undermine the role of other centres in the locality.

18 Clause 9.b.2 provides that:

          1. The development of land at 556-594 Princes Highway, Kirrawee (the Brick Pit site)
            a. Must provide for the following mix of floor spaces:
              Residential: 27,320 sqm.
              Employment: 10,470 sqm.
              with the retail component of employment uses not exceeding 20% of the total employment generating floor space.
            b. Land on the corner of Oak Road and Princes Highway must be either hotel, commercial development, Seniors Housing or a mix of residential and these uses.
            c. Land fronting the Princes Highway must have commercial uses on the ground floor with medical and legal uses preferred.
            d. Land fronting on the eastern side of the site fronting Princes Highway may be used as either commercial or residential/commercial mix subject to noise transmission being addressed through the imposition of appropriate performance criteria.
            e. Land with no street frontage must be designed so that the ground floor units can be used for either commercial or residential uses.
            f. Shops shall help activate streetscapes and the public domain so that the amenity of residents and workers is enhanced.
            g. Intensive retail land uses, such as a large supermarket, are not appropriate.
          2. Despite subclause 1. the use of the site for educational purposes is encouraged.
          3. Development of land elsewhere in the Mixed Use – Kirrawee Zone must provide a minimum of 25% floor space for Employment use with the retail component of employment uses not exceeding 20% of the total employment generating floor space.

19 Amendment 4 to DCP 2006 (DCP 2006 Amendment 4) became effective in 9 January 2009, which is after the development application was lodged. The objective (cl 9.a.3), the maximum 20% retail component (cl 9.b.2.a), cl 9.b.2.1.g and cl 9.b.2.3 were added under DCP 2006 Amendment 4, which does not include a savings clause. The parties disagreed on the weight to be given to DCP 2006 Amendment 4, which we discuss in the Strategic issue below. We find that the proper planning approach is that the changes made as part of DCP 2006 Amendment No 4 expand and clarify controls which were already included in DCP 2006. The changes should be considered and given weight, although as with any DCP an application may be inconsistent with the requirements of the DCP if, on the merits, this is appropriate.

20 The Kirrawee Local Area Masterplan (LAM) was prepared by the former owner of the site, Sydney Water, following extensive community consultation and was endorsed by council in September 2003. The conclusions of the LAM have been incorporated into LEP 2006 and DCP 2006.

21 A number of strategic planning documents have been prepared by council. These include Our Shire our Future, Shaping the Shire to 2030, Hirst Report, Blueprint for Action and the Structure Plan 2003. The parties disagreed on the weight to be given to these documents and to the LAM which we discuss in the Strategic issue below. We have given these documents and the LAM little weight other than that they form the basis of LEP 2006 and DCP 2006. We acknowledge that these background documents may be considered to assist in understanding the intent of provisions in LEP 2006 and DCP 2006 where this is unclear or in dispute between the parties. However, we have not found it necessary to do so.

22 In November 2007, the NSW Government prepared the Draft South Subregional Strategy (draft Strategy) as part of the Metropolitan Strategy. The Strategy has been exhibited but to date has not been adopted. The parties disagreed on the weight to be given to the Strategy, which we discuss in the Strategic issue below. We have considered the Strategy but given it little weight as it is not an adopted policy and there is no certainty as to its future. We note that the Metropolitan Strategy identifies Sutherland Centre as a “potential major centre” however, the structure of the Metropolitan Strategy is that it will be implemented through more detailed controls, such as the sub regional strategies, LEPs and DCPs. Within this context, the proper planning approach is to give weight to LEP 2006 and DCP 2006 although we find that these documents are not inconsistent with the future role for Sutherland identified in the Metropolitan Strategy.


Background

23 The hearing began on site on 16 February 2009. The retail component of the proposal proposed two supermarkets (7003sqm) and a total retail component of 10,678sqm (the original proposal). The court heard evidence from residents, visited the site, Kirrawee Centre and Sutherland Centre.

24 The Court heard evidence from the urban design, economic and traffic experts. On the morning of 20 February, the parties indicated that they had reached an in-principle agreement as to changes that were required, including:

      • creating the principle pedestrian entry to the shopping centre at the corner of West and Flora Streets enabling a closer physical connection to the Oak Road retail precinct;
      • increasing the active retail frontage along Flora Street and the new pedestrian entry;
      • deletion of one supermarket and reduction in gross leasable floor area of shopping centre to 8000sqm, excluding cafes on ground level of Building E;
      • relocation of proposed childcare centre from Building A, adjacent to open plant room and loading dock driveway, to Building I, opposite the proposed public open space;
      • reduction in the required parking in the order of 106 spaces;
      • relocation of the building footprint of Building K to achieve an open space area consistent with that required under the DCP 2006;
      • reduction in the footprint of the residential component of Building K, to more closely reflect DCP 2006 and the addition of an extra residential level.

25 The parties requested an adjournment to enable amended plans that reflected the in-principle agreement to be prepared and for the amended application to be renotified and considered by council. We granted the adjournment and issued Directions for an agreed timetable on 3 March 2009 for the amended plans (March amended application).

26 Council considered the March amended application at its meeting on 23 March 2009. It did not determine the application and resolved to continue to defend the appeal.

27 By Notice of Motion filed on 27 March 2009, Westfield Limited (Westfield) sought leave to be joined as a party pursuant to s 39A of the Land and Environment Court Act 1979 (the Court Act). The parties agreed that the Notice of Motion be vacated on the basis that Mr B Brown be granted leave to provide planning evidence in the proceedings on behalf of Westfield.

28 The hearing resumed on 3 April 2009. The Court heard further resident evidence (4 objectors) on the March amended application. A joint statement of the urban designers, planners, stormwater and traffic experts recommended further detailed changes (Exhibit CC). A further joint report from the economists (Exhibit BB) indicated that they did not object to a single supermarket of the size proposed in the March amended application. The applicant sought that the agreed changes be implemented through deferred commencement conditions or alternatively that the matter be again adjourned for amended plans. Council opposed both submissions.

29 On the basis that the changes were beyond those appropriately dealt with by conditions and the agreement of the experts as to appropriateness of the changes, we again granted leave for the amended plans and issued directions for a timetable (April amended application).

30 By Notice of Motion filed on 12 June 2009, Westfield and Supabarn Supermarket Pty Ltd (Supabarn) sought orders to intervene in the proceedings. The Notice of Motion was heard on 19 June 2009. For the reasons discussed below, on 22 June 2009, we granted leave for Westfield and Supabarn to intervene in the proceedings pursuant to s38 (2) of the Court Act.

31 On 19 June 2009, Mr Robertson SC, for the council, sought leave to call a new expert in relation to the hydrology and water quality issue. Mr Galasso SC, for the applicant, opposed the additional expert but submitted that the applicant would also seek leave to call an additional expert if council’s motion was successful. On 22 June 2009, we refused council’s application on the basis that hydrology and water quality issues of the pond had been an issue in the proceedings from the start. The parties had selected experts with appropriate expertise to deal with the issue. These experts had generally reached agreement on the pond scheme subject to further information being provided. Therefore, a different expert was not warranted, particularly as the applicant objected. In reaching this decision we were unaware that an alternate scheme for the pond was now proposed.

32 The hearing again resumed on 30 June 2006 to consider the April amended application. The Court heard further resident evidence (2 objectors) and expert evidence on ecology and water quality issues, traffic, urban design, landscape, economic and planning issues.

33 The applicant made submissions at the end of the hearing. A timetable was set for the intervenor and the council to file written submissions on 15 July and the applicant to file written submissions in reply on 25 July. The intervenor filed its submissions on 16 July but the council did not provide its submissions until 20 July. The applicant was therefore granted an extension until 31 July, which was met.


34 Westfield and Supabarn sought orders that:


          1. The Intervenors be joined as a party to the proceedings pursuant to s 39A of the Land and Environment Court Act 1979.

          2. The Intervenors be permitted to call expert town planning and economic impact evidence in relation to the retail component of the proposed development that is the subject of the proceedings.

          3. In the alternative to Orders 1 and 2, that the Intervenors be permitted under s 38(2) of Land and Environment Court Act to participate in the proceedings by leading evidence, cross examining witnesses and making submissions in relation to the retail component of the proposed development that is the subject of the proceedings.

          4. Such further orders as the Court sees fit.

35 Council supported the motion and the applicant opposed it.

36 In support of the motion, Westfield relies on an affidavit of Ms D Townsend sworn on 12 June 2009 and Supabarn relies on the affidavit of Mr Kahagalle and Mr Koundouris both sworn on 12 June 2009.

37 Section 39A of the Court Act provides:


          39A Joinder of parties in certain appeals
          On an appeal under section 96 (6), 96AA (3), 96A (5), 97 or 98 of the Environmental Planning and Assessment Act 1979, the Court may, at any time, on the application of a person or of its own motion, order the joinder of a person as a party to the appeal if the Court is of the opinion:
          (a) that the person is able to raise an issue that should be considered in relation to the appeal but would not be likely to be sufficiently addressed if the person were not joined as a party, or
          (b) that:
            (i) it is in the interests of justice, or
            (ii) it is in the public interest,
            that the person be joined as a party to the appeal.

38 Section 38(2) of the Court Act provides:


          (2) In proceedings in Class 1, 2 or 3 of the Court’s jurisdiction, the Court is not bound by the rules of evidence but may inform itself on any matter in such manner as it thinks appropriate and as the proper consideration of the matters before the Court permits.

39 The Notice of Motion was heard on 19 June 2009. Mr N Hutley SC, for the applicants for joinder (the intervenor), and Mr Galasso referred to Morrison Design Partnership Pty Limited v North Sydney Council and Director General of the Department of Planning [2007] NSWLEC 802 where Preston CJ provides a summary of the relevant principles in applying the tests in s39A. These include that it is appropriate to join a party where, if not joined, the Court would not have a “meaningful assistance” or there would be “no meaningful contradictor” on important issues that the Court needs to consider to give a proper and lawful decision”.

40 Both Mr Hutley and Mr Galasso referred to other authorities to support their position.

41 In summary, the key difference in their submissions was whether the economic and planning issues would be “sufficiently addressed” without joinder.

42 Mr Hutley submitted that the issues would not be sufficiently addressed for the following key reasons:

      i. The economic evidence is based on flawed assumptions in relation to zonings and there has been no economic analysis of the amended proposal for one supermarket.
      ii. The economic and planning issues have a direct impact on Supabarn. It is in a position to provide evidence, which it alone can adduce.
      iii. Council’ planning and economic experts have changed their position on the appropriateness of the retail component without adequate justification. Due to the unexplained agreement there is no effective contradictor to the evidence of these experts on significant issues in dispute.
      iv. The Court would be assisted by evidence from the intervenor’s planning and economic experts and through cross examination of the Council’s experts, which would not be able to be undertaken by the council.

43 Mr Hutley submitted that leave is now being sought because previously Council’s planning and economic experts were addressing the relevant issues. However, their opinions had changed, not in response to design changes, and without adequate explanation. While Council was still pressing the issues there was no effective contradictor or an ability for council to effectively cross-examine its own experts.

44 Further, Mr Hutley submitted that the joinder would not delay or significantly extend the proceedings.

45 Mr Galasso submits that the issues had been sufficiently addressed through expert evidence and cross-examination. The experts had reached agreement through a process of the evolution of changes to the design in response to expert evidence. There had therefore, been an effective contradictor.

46 Both Westfield and Supabarn had ample opportunity to make written submissions and be heard by the Court. Both are competitors to the proposed supermarket and the issue before the Court is one of broad strategic context and not of competition. Section 39A is not a facility to enable dissatisfied objectors to seek to intervene as issues are resolved.

Findings

47 While we accept that there is merit in Mr Galasso’s submission and that it is unusual to permit a party to intervene at this late stage of proceedings. However, the proceedings, as outlined else where in the judgment and detailed in the affidavits in support of the motion, have been unusual given the adjournments for amended plans and changing position of council and its experts.

48 In his detailed submissions, Mr Hutley has raised significant issues in relation to the evidence before the Court which we consider have not, and given the agreement of the experts, are not likely to be sufficiently addressed without an effective contradictor. Given the complexity and seriousness of the issues we consider that it is important that they be examined thoroughly. In reaching this decision we note that the Intervenor is able to meet the timetable and that there is unlikely to be a material extension of the proceedings.

49 We note that the Notice of Motion seeks an alternative order to intervene under s38(2) of the Court Act which despite the introduction of s39A remains open to the Court as stated by Pain J in Kavia Holdings Pty Limited v Sydney City Council [2003] NSWLEC 195. As noted by Jagot J in Bongiorno Hawkins Frassetto & Associates Pty Ltd v Griffith City Council [2007] NSWLEC 205, the considerations in s 39A are also of relevance in exercising discretion under s38(2).

50 Due to the unexplained change in position of council’s planning and economic experts and the questions raised about the economic methodology, it is appropriate we be informed by further economic and planning evidence to give proper consideration of the matters before the Court. However, given the limited nature of the issues we did not think it necessary to join the intervenor as a party under s39A of the Court Act.

51 We therefore made the following order and a timetable for evidence:


          The Intervenors be permitted under s38(2) of the Land and Environment Court Act 1979 to call expert economic and planning evidence, cross examine economic and planning experts and make submissions in relation to the retail component of the proposed development.

The proposal

52 The April amended application for which consent is now sought is for a Masterplan for the entire site and construction of Stage 1 for a mixed retail, commercial, residential development with a child care centre, basement car parking and open space recreation area.

53 The proposal is described in the Final Amended Statement of Facts and Contentions as follows:

      Masterplan
      The Masterplan for the proposed development consist of the following:
        • Residential Development - consisting of approximately 250 dwellings (equating to approximately 27,112sq.m GFA)
        • A retail shopping centre - as outlined in the Stage 1 description)
        • Commercial uses (4,581sq.m GFA) including offices and a child care centre for up to 20 children
        • All uses contained within structures below the assumed or actual ground level .of the site or in a series of building envelopes of between 2 and 6 stories above the podium level.
        • 927 parking spaces in various basement, podium and driveway locations.
        • A public park (approximately 0.9ha)
        • Various pocket parks or urban spaces within the development and general landscaping of the site;
        • Associated site works (including dewatering), parking/loading, services and amenities.
        • New north-south and east-west roads to provide vehicular, bicycle and pedestrian access internally through the site, and
        • External road improvements.
        • In situ conservation of the brick kiln foundations

      The total gross floor area of the proposal is 42,045 sq.m.
        Stage One
        Stage One of the Masterplan involves the following components. These components are provided in greater detail as follows;
        Retail and Commercial Component
        A total of 11,274 sqm of commercial and retail floorspace is proposed, comprising:
        • A shopping centre on the lower ground level;
          1 supermarket (4,500sq.m (GFA)
          1 mini-major (675 sqm GFA)
          Mall specialty stores and kiosks (225sq.m GFA);
        • External specialty shops and cafes along the Flora Street frontage (600sq.m GFA);
        • Block E Retail (Cafes) at podium level 163sq.m GFA)
        • Lower Ground Commercial (765sq.m GFA)
        • Podium Level Commercial (176sq.m GFA)
        • The shopping centre has direct pedestrian access to Flora Street, with pedestrian entrances in Building E at the corner of West and Flora Streets and at the eastern end of Flora Street. An escalator and lifts provide access between the car park and the shopping centre and the ground floor podium.
        • Loading facilities comprising 7 docks are provided on the Lower Ground level.
        • The total retail and commercial component of the stage 1 proposal equates to 9,104 sqm. GFA. The full retail component is contained within the Stage 1 application.
        • The hours of operation of the retail facility are as follows;
              Retail uses 6am to midnight (7days)
              Loading dock 6.00am to 11 pm (7 days)
              Cafe 7am to 10.00pm (7 days)
      Residential Component
      Stage 1 proposes four residential buildings consisting of 63 units in total, as described in further detail below;
        • Block C - is located at the south-eastern corner of the site. 10 apartments are proposed to be accommodated within a 3 level building. 6 x 2 bedroom, 3 x 3 bedroom and 1 x 3 bedroom (plus study) apartments are proposed.
        • Block D - is located at the south of the site. It is proposed to accommodate 30 apartments within a 4 level building. 14 x 1 bedroom, 9 x 2 bedroom, 7 x 2 bedroom apartments are proposed.
        • Block E - is located at the south of the site, between Block D and the Brick Pit Park. The proposed 4 level building is to accommodate the shopping mall entry and cafe areas at the ground floor podium level, and 9 x 2 bedroom apartments within the 3 floors above.
        • Block F - is located in the approximate centre of the site, adjacent to the Brick Pit park. 13 apartments are proposed to be accommodated with a 4 level building. 6 x 2 bedroom, 1 x 2 bedroom (plus study), 1 x 3 bedroom and 5 x 3 bedroom apartments (plus study) are proposed.
        • Off street parking for the proposed new residences is accommodated on the Basement 2 level. 216 car parking spaces are proposed on this level to service both the proposed Stage 1 residences and some of the future staged DA residences.
      Parking Provision
      A total of 679 parking spaces are proposed in the stage 1 development comprising:
        • Basement 1 (Retail) - 358 spaces
        • Basement 2 (Residential and Visitor) - 249 spaces
        • Princes Highway Driveway Entry - 14 spaces
        • Ground Level Podium - 58 spaces
      Public Park
      The proposal involves the dedication of the land zoned 13 - Public Open Space to Council as a public reserve, and is seeking consent to carry out physical works to that land.
      Embellishment works include:
        • Construction of a 801.6 sqm pond;
        • Filling of the existing brick pit to assist in providing works;
        • Retention of the portions of the endangered ecological community (STIF) within the site, combined with compensatory planting in other off site locations;
        • Supply and treatment of water to maintain the proposed pond as a compensatory habitat;
        • Entrances and safety fences
        • Construction of amenities area
        • Construction of a playground

      Landscaping
      Permanent landscaping works, including a series of "pocket parks"

      Roads
      Internal north-south and east-west roads to provide vehicular, bicycle and pedestrian access through the site.

      Signage
      Signage zones for Stage 1 retail buildings; and

      Site Works
      Associated site works including de-watering, services and utilities for the Stage 1 works.

54 The Court heard expert evidence for the Applicant from:

      • Ms G Morrish, architect and urban designer
      • Mr G Pindar, traffic consultant
      • Mr A Darroch, planner
      • Dr D Robertson, ecologist
      • Mr A Dimasi, retail economist
      • Mr M Richards, hydraulic engineer
      • Ms N Sonter, landscape consultant

55 The Court heard expert evidence for the council from:

      • Mr N Dickson, architect and urban designer
      • Mr C McLaren, traffic consultant
      • Mr K Nash, planner
      • Mr I Drinnan, environmental scientist
      • Mr B Haratsis, economist and planner
      • Dr G Amos, hydraulic engineer
      • Mr M Sherrie, infrastructure manager
      • Mr N Metcalf, landscape consultant

56 The Court heard expert evidence for the intervenor from:

      • Mr B Brown, planner
      • Mr M Evesson, planner on economic issues

57 In addition, Mr A Kingswell, for the applicant and Mr I Drinnan, for the council provided expert reports on contamination issues but were not required for cross examination on this issue.

Resident evidence

58 The Court visited the site and heard evidence from people both in favour and opposed to the development. The key concerns of those who opposed to the development are the increase in traffic and impacts on the existing road system from cars and service vehicles, inadequate parking provision and noise. The adjoining owners and occupiers of the James Cook Industrial Estate were concerned about the restrictions that the proposal would place on the operation of their businesses, particularly the location of the driveway adjoining their property. They were also concerned that the driveway, in conjunction with the existing substation and the strata ownership of their property, would limit the opportunity for its future redevelopment.

59 Ms B Hoffmann and Ms C Stubbs who operate car repair businesses in the James Cook industrial Estate were particularly concerned that the location of the driveway would prevent brake tests, which are currently carried out in Flora Street and require a length of 100m for cars and 300m for trucks. They stated that there was no other suitable location for brake testing in the vicinity. They were also concerned by the loss of on street parking in Flora Street, which they considered had not been adequately replaced within the development. They maintained their concerns in relation to the March and April amended applications.

60 Mr Koundouris, a Director of Supabarn gave evidence on site in relation to the impact of the proposal on the Supabarn supermarket (under construction on the corner of President Avenue and Old Princes Highway, Sutherland) and Sutherland Town Centre. He considered that the retail component of the proposal would effect the viability of the business and consequently would impact upon Sutherland Town Centre failing to develop its higher order role in the retail strategy.

61 Mr D Hunt, a local retailer, expressed concern about the impact of the proposal on small retailers. He considered the additional competition from a large shopping centre would impact on small shopping centre which, in his opinion, plays an important part, such as providing improved security of streets through informal surveillance by shop keepers.

62 The main reason that people supported the proposal was because it would provide increased retail facilities for which there was a demand from people within the area, particularly older people who supported a supermarket in close proximity to their homes.


63 Contention 1 refers to the strategic context of the proposal. Council contends that:


          The proposal involves, amongst other things, a large major supermarket and mini major. Retail development of that scale is entirely inconsistent with the strategic planning for the site as embodied in the Metropolitan Strategy, the Sutherland Shire Structure Plan 2003, Sutherland Shire Local Environmental Plan 2006, Sutherland Shire Development Control Plan 2006, Amendment No 4 to Sutherland Shire Local Environmental Plan 2006, the adjoining Kirrawee Village Shopping Centre and the planning outcomes envisaged through the extensive community consultation process undertaken as part of the Kirrawee Local Area Masterplan.

          Further the proposal does not provide for adequate or suitable employment uses, contrary to the evolved planning strategic context for the subject site.

64 Contention 1 provided further particulars on the proposal’s inconsistency with these planning documents.

65 The key disagreement between the parties and the intervenor was the weight to be given to the planning document, whether they established a retail hierarchy and whether the proposal is consistent with the strategic objectives.

66 Mr Nash and Mr Brown considered that there was a clear centre hierarchy established by the LEP 2006 and DCP 2006, Amendment 4 and the other planning documents, including the draft Strategy. In response to the original proposal for two supermarkets, Mr Nash concluded that:


          The development of a stand alone shopping centre on the Kirrawee Brick Pit would seriously dent the potential for the retail development envisaged for Sutherland Centre being achieved thereby inhibiting the likelihood of Sutherland Centre becoming a major centre…….and is inconsistent with the strategic planning outcomes reflected in the State and Local Environmental Planning Instruments and the DCP.

67 Mr Darroch gave little weight to the draft Strategy as this and the Metropolitan Strategy set the future direction of areas whereas the site is already zoned under LEP 2006 to permit a mixed use development. In his opinion, there are only two broad strategic questions which need to be addressed; firstly does the proposal meet the objectives of Zone 7, in particular objective (j) to facilitate the re-vitalization of the Kirrawee Town Centre and the Kirrawee railway precinct. Secondly, what is the impact on existing retail facilities in surrounding centres.

68 In Mr Darroch’s opinion, both the original and the amended proposal meet the objectives of the zone, in particular, it will provide over 500 new residents in walking distance of the station. The additional residents will revitalise Kirrawee Town Centre. Mr Darroch gave little weight to objectives (k) and (l) of the zone which were introduced under LEP 2006 Amendment 4, as he considered these to be made in response to the development application. Nonetheless, he considered the proposal met these objectives.

69 The planning experts relied on the evidence of the economists to determine whether the proposal would result in an economic impact on other centres, particularly Sutherland.

70 In response to the evidence of Mr Haratsis and Mr Dimasi on the original proposal, Mr Nash, in his oral evidence on 3 April 2009, stated that Kirrawee could accommodate one supermarket and not impact on the local area and therefore not impact on the future role of Sutherland as a major centre. This conclusion was based on the likelihood that the occupants of the original proposal for two supermarkets at Kirrawee would be Coles and Woolworths, which would mean that neither of these major retailers would be likely to locate in Sutherland. Whereas if one supermarket was located at Kirrawee the potential remained for an additional supermarket, including a Coles or Woolworths, to be established in Sutherland as a competitor. We understand that this conclusion was the genesis of the March amended application.

71 In response to the further evidence of Mr Haratsis on 1 and 2 July, Mr Nash expressed doubts about the size of the supermarket proposed as this had not been modelled and it may have the potential to impact negatively on Sutherland and Gymea. He was satisfied that a single supermarket of the size proposed (4,500 sqm) would not impact on the existing Kirrawee Town Centre.

72 The planning experts agreed that for the purpose of the objectives for Zone 7 in LEP 2006, the term Kirrawee Town Centre means the existing Oak Road shops. Although Mr Darroch considered that the term has other meanings in other documents.

73 Both Mr Darroch and Mr Nash agreed that:


          Oak Road will remain the retail precinct for Kirrawee Village. The Brickpit proposal is a destination shopping centre mainly accessible by vehicles.

74 Despite the difference in the catchment of the centres, Mr Nash and Mr Darroch agreed that the new centre would not become a second town centre and that the Kirrawee Town Centre would remain a local centre. Other than Mr Nash’s concerns in relation to the impact of the proposal on Sutherland, and to a lesser extent Gymea, they agreed that the proposal generally met the objectives for Zone 7 in LEP 2006 and the requirements of DCP 2006

75 Mr Brown states that Sutherland has an existing retail floorspace of 8,500 sqm and an approved retail floor space of 3,200 sqm (including the 2,500 sqm Supabarn supermarket), a total of 11,700 sqm. The proposal provides 8,151 sqm of retail floorspace and the existing shops in Oak Road provide 2,500sqm, a total of 10,6512 sqm. He concludes that:


          Given the similar amount of floorspace and the proximity to Sutherland, Kirrawee will compete with Sutherland as the higher order centre in this part of the Shire…..

          The proposal will draw on customers from a wide catchment (certainly much wider than the local area) in conflict with Kirrawee’s designated role, not only as a local centre but as local centre which is not intended to grow significantly. The proposal would change its functions so that it will be more akin to an ‘Urban Centre’ zoning. Further there is concern that approval of the proposal will allow other sites in the Mixed Use zone to provide for competing retail uses, further eroding the established hierarchy

76 In Mr Brown’s opinion this was inconsistent with the strategic role for Sutherland and Kirrawee established by the planning controls. In particular, Mr Brown did not consider that the proposal met the objectives for Zone 7 in LEP 2006 and was inconsistent with a number of the controls in DCP 2006.

77 Whereas Mr Darroch’s held the contrary opinion that:


          The proposal will not change the Centre's hierarchy. It is not just the retail component that determines the role of the centre its other uses as well. In the case of Sutherland it is the administrative and civic functions that mean that it will always remain the dominant centre over Kirrawee. Kirrawee will remain as a local centre. Sutherland will maintain its role as the economic evidence is that the proposal not inhibit the ability of Sutherland have a full line large scale supermarket.

Findings

78 The parties made extensive submissions about the weight to be given to LEP 2006 Amendment 4 and DCP 2006 Amendment 4 and to the other planning documents. They agreed that under s79C of the Act, LEP 2006 and DCP 2006 must be taken into consideration but disagreed as to whether these documents established a retail hierarchy.

Proper planning approach

79 For the reasons discussed below we find that the proper planning approach is an assessment of the application under LEP 2006 and DCP 2006. LEP 2006 Amendment 4 must be considered and given weight and the proposal should be consistent with the planning approach established in this amendment.

80 DCP 2006 Amendment 4 is not to be given determinative weight but is to be considered in conjunction with the other provisions of DCP 2006 as a focal point to assess the merits of the application.

81 We have not found it relevant to consider the other planning documents as LEP 2006, DCP 2006 and their amendments provide an adequate planning framework to assess the application.

    • LEP 2006 Amendment 4

82 The parties agreed that the savings provision in cl 58 of LEP 2006 require that LEP 2006 Amendment 4 be considered as if exhibited but not made. The parties also agreed that as the amendment is gazetted it should be considered as imminent and certain. Further, the parties agreed that the approach to determining the weight to be given to amendments in these circumstances is outlined in Blackmore Design Group Pty Ltd v North Sydney Council [2001] NSWLEC 279 where Lloyd J reviewed relevant cases and applicable principles as follows:


          21. The first question is the weight to be given to the 2001 LEP. That question is governed by cl 5(3) of that instrument: 'the environmental planning instrument repealed or amended by this plan shall apply as if this plan had been exhibited but had not commenced'. With the benefit of hindsight it is possible to say that although the 2001 LEP had not been made, at the time of lodgement of the development application on 13 November 2000 it was both certain and imminent. At that stage, the then draft LEP had been exhibited three times, had been formally adopted by the council and had been forwarded to the Department of Urban Affairs and Planning for making by the Minister.

          22. The weight to be given to a draft local environmental plan in such circumstances is settled. In particular the question has been considered in a series of cases involving the present 2001 LEP in draft form.

          23. Mathers v North Sydney Council [2000] NSWLEC 84 (unreported) was heard when the then draft LEP had had its second exhibition but submissions had not been considered. Talbot J said (at par[29]):
              'It is appropriate given the history of the development of the draft instruments to give draft LEP 2000 significant weight to the extent the Court is satisfied that approving the development will not detract from its objectives as expressly stated or reflected in the proposed controls ...'

          24. Architects Haywood & Bakker Pty Ltd v North Sydney Council [2000] NSWLEC 138 (unreported) was heard after the third exhibition, when submissions following that exhibition were being considered. Pearlman J put the question in the following terms (at par [32]):
              'The question, then, is the degree of weight to be placed upon [the plan's] provisions in the assessment of the proposed development. That involves considering whether the making of the Draft LEP is certain and imminent. It also involves considering the effect cl 5(3) of the Draft LEP which is a savings provision ...'

          25. Pearlman J then said (at par [33]) that the planning approach which the draft LEP adopts must be regarded as certain to be brought into force within the reasonably foreseeable future; and hence she placed 'significant weight' upon its provisions in the assessment of the development application in that case. Her Honour then turned her attention to the savings provisions of the draft LEP (at par [34]):
              'The savings provision does not require a different approach. The effect of cl 5(3) is to place the Draft LEP in precisely the same position so far as concerns this development application whether it had formally come into force or still remained a draft as currently pertains. In either case, it is to be taken into consideration as if it had been placed on public exhibition, and accordingly given some weight in the assessment of the planning implications of the development application.'

          26. Edward Listin Properties Pty Ltd v North Sydney Council [No.2] [2000] NSWLEC 181 (unreported) was also heard after the third exhibition but also after the council had resolved to make the plan and had forwarded it to the Department of Urban Affairs and Planning to be made by the Minister. Talbot J said (at par [9]):
              'In the circumstances outlined above it is incumbent upon the Court to place considerable weight on any relevant provisions of the draft LEP and the impact that granting of development consent may have on implementation of its objectives.'

          27. Walker v North Sydney Council [2001] NSWLEC 211 (unreported) was heard almost one month after Edwards Listin Properties. Cowdroy J said in that case (at par [31]):
              'Arising form the judgments of Talbot J and Pearlman J the adoption of the draft LEP is imminent ... The Court therefore gives due force to such clause and upholds the council's submission that cl 68 of the draft LEP warrants rejection of the development application.'


          28. Finally, Detita Pty Ltd v North Sydney Council [2001] NSWLEC 209 (unreported) was heard after the 2001 LEP had been made. I held (at par [6]) that the effect of the savings clause (cl 5(3)) meant that the notionally draft planning instrument must be awarded such weight as must be given to any such instrument when its implementation is certain and imminent. I further decided (at par [11]) that in the circumstances of that case the notionally draft local environmental plan should be afforded determining weight.

          29. It seems to me that in applying the savings clause, cl 5(3), to the present case, one cannot ignore the fact that the 2001 LEP has been made. In applying the words of the clause that 'the environmental planning instruments repealed or amended by this plan shall apply as if this plan had been exhibited but had not commenced', it is necessary in the light of that circumstance to assume that the making of the notionally draft plan was certain and imminent. In Architects Haywood v Bakker Pty Ltd, Pearlman J said that the savings provision does not require a different approach. I thus reject the submissions of the applicant that this approach is not consistent with the purpose of cl 5(3).

          30. Whether one applies the test of 'significant weight', or 'some weight', or 'considerable weight' or 'due force' or 'determining weight' to the later instrument is not, however, the end of the matter. The savings clause still has some work to do. The proposed development is a permissible development by dint of the savings clause. In giving the 2001 LEP the weight of being imminent and certain, that does not mean that there is no further inquiry. It is necessary to look at the aims and objectives of the later instrument and then see whether the proposed development is consistent therewith”.

83 Mr Hutley submits that considerable weight must be given to the changes to Zone 7 to include objectives (k) and (l) introduced as part of LEP 2006 Amendment 4. In his submission the proposal is inconsistent with these objectives. Mr Robertson endorsed this submission.

84 Mr Galasso submits that the changes relevant to the proposal do not effect an actual change to LEP 2006. Further, he submits that the new objectives:


          …arguably emphasise the planning goal of providing retail in the zone and provide goals for that retail, namely: revitalisation; integration; and not adversely impacting on the sustainability of others centres in the Shire. For the reasons outlined the proposal meets the general goals of these objectives.

85 In reviewing these submissions it appears that there is no disagreement that objectives (k) and (l) introduced as part of LEP 2006 Amendment 4 must be given considerable weight. The disagreement between the parties is whether the objectives are met, which we discuss below.

86 We note that the planning experts give considerable weight to the changes in LEP 2006 Amendment 4 to the definition of “gross floor area” which excludes parking required by the development. Without this amendment the proposal has an FSR of 1.52: 1, which exceeds the FSR of 1:1 permissible under clause 35 of LEP 2006.

87 We find that the proper planning approach is that the proposal should be consistent with the planning framework established by LEP 2006 Amendment 4.


    • DCP 2006 Amendment 4

88 Mr Hutley submits that the weight to be given to a DCP is established in Zhang v Canterbury Council (2001) 51 NSWLR 589 where the Court of Appeal held:


          The consent authority has a wide ranging discretion … but the discretion is not at large and is not unfettered. DCP 23 had to be considered as a ‘fundamental element’ in or a ‘focal point’ of the decision making process. A provision so directly pertinent to the application for consent … as was cl 4.0 of DCP 23 was entitled to significant weight in the decision making process but was not, of course, determinative.

89 DCP 2006 Amendment 4 contains no savings provisions and limits the size of any retail development throughout Zone 7, including the Brick Pit site. Mr Hutley submits that the proposal is contrary to the provisions in DCP 2006 Amendment 4 and that:

          DCP Amendment No. 4 is entitled to be a “fundamental element” in the decision making process, and be given “significant weight”, despite the circumstance that it was made after the development application was lodged. In making its decision, the Court must apply the law and find the facts as they exist when the appeal is heard: see Janlz Constructions v Randwick Municipal Council (1976) 35 LGRA 70 at 72-73 (CA) per Grass JA; Woollahra Municipal Council v TAJJ Investments (1982) 49 LGRA 123 at 130 (CA) per Mahoney JA; Sofi v Wollindilly Shire Council (1975) 31 LGERA 416 per Waddell J; and Architectural Property Services v Rockdale City Council [1999] NSWLEC 83 at [16] per Lloyd J. DCP Amendment No. 4 constitutes a significant element of the legal and factual matrix to be applied at the time of the making of the Court's decision.

90 Mr Galasso accepts that the provisions of a DCP are to be the focal point but submits that there is no requirement that the provisions must be met as a condition precedent to the granting of development consent. Further he submits that:

          ….changes to the DCP must be taken into account, but because they were introduced following the lodgement of the development application and after the commencement of the appeal, and the Applicant contends in fact as a reaction to the proposed redevelopment of the site (pp 140-141 of Council’s bundle, exhibit 1), such timing requires that they be given according weight.
          In this regard, there have been a number of decisions in which the Court has held that a DCP introduced after a development application has been lodged should be given less weight. For example in Architectural Property Services v Rockdale City Council [1999] NSWLEC 83 Lloyd J said at [16]:
          “Where the relevant development control plan commenced after the development application had been made it should not be given determinative weight. This is not to say that the standards.... should be ignored, they should be taken into account. A failure to comply will not necessarily be fatal to the application provided that it is otherwise satisfactory. Although [the] previous development control plan.... is now repealed, its controls may also be taken into consideration as indicative of standards and controls which applied when the development application was made.

91 We note that in the circumstances of this case, DCP 2006 Amendment 4 applies to Zone 7, although some provisions refer only to the Brick Pit site, such as the limit on the retail floorspace component, however, a similar limit has also been introduced to the remainder of Zone 7. Amendment 4 does not repeal or replace provisions of a DCP but rather adds to existing provisions to clarify their intent. DCP 2006 Amendment 4 came into force after the development application was lodged on 9 April 2008. However, Mr Nash’s evidence is that council adopted a report on the proposed changes in September 2007 and they were initially exhibited in March/April 2008 as part of DCP 2006 Amendment No 3. The changes have therefore had a long gestation period and generally deal with a wider area than just the Brick Pit site. We find that the provisions in Amendment 4 are not to be given determinative weight but are to be considered in conjunction with the other provisions of DCP 2006 as a focal point to assess the merits of the application. There is no requirement that the provisions in DCP 2006 Amendment 4, as with any provisions in a DCP must be met, but they must be considered.

    • Other planning documents

92 The parties held different opinions about the weight to be given to the non statutory planning documents, including the planning studies, LAM, the Strategy and the Metropolitan Strategy. Mr Hutley and Mr Robertson submit that these documents should be given weight. LEP 2006 and DCP 2006 have evolved from a long history of strategic planning which they submit establishes a retail hierarchy for Sutherland that is also recognised in regional planning documents. Mr Hutley submits that:


          The LEP must not be read in a vacuum, in the manner for which the applicant contends. The non-statutory policies form the background against which the value judgments required by the EPA Act and the LEP are to be made.

          Of course, the non-statutory policies are also matters to which the Court may have regard when it considers “the public interest” as required by s.79C(1)(e): Terrace Tower Holdings v Sutherland Shire Council (2003) 129 LGERA 195,...

93 Mr Hutley submits that the LAM should be considered on the basis of the principles established by McClellan CJ in Stockland Development Pty Ltd v Manly Council [2004] NSWLEC 472 and by Talbot J in Aldi Foods v Holroyd City Council [2004] NSWLEC 253. Mr Hutley states that:


          The LAM is a master plan which was the product of extensive research and public consultation. It has not been significantly departed from. It is compatible with the LEP, the DCP and the Draft South Sub-Region Metropolitan Strategy. It should be given weight in the Court's assessment of the application .

94 Mr Galasso submits that there is no retail hierarchy, whether strategic or otherwise. He accepts that the historical planning for the site should be recognised but submits that:


          ….where historical assessment has merged into contemporary planning instruments or plans, which themselves are specifically required to be taken into account in the determination of a development application, it is illogical, incorrect and patently disproportionate to that merging to suggest that the historical documents should be resurrected and afforded a level of importance beyond their true place in history……

          ……The LEP and the DCP speak for themselves……

95 Mr Galasso submits that there is no adopted “regional planning policy” and that the LAM is not a “policy” as referred to in Stockland as its relevant provisions have been incorporated into LEP 2006 and DCP 2006. Nor is it a “masterplan” as referred to in Aldi as it is not made as a consequence of the controls in LEP 2006 or DCP 2006.

96 Mr Galasso states that there is no requirement in s79C to take into account other planning documents although he acknowledges that they may be considered under “public interest” consistent with the decision in Terrace Towers.

97 We accept Mr Galasso’s submission to the extent that under s 79C of the Act, LEP 2006 and DCP 2006 must be considered and that these documents “speak for themselves. LEP 2006 and DCP 2006 were prepared following extensive strategic planning and incorporate provisions relating to the Brick Pit site and other areas. We find that these provisions are adequate to understand the role and function for these centres envisaged under the planning controls. The non statutory planning documents could be considered to assist in the understanding of the LEP and DCP or as part of the “public interest” considerations. However, this is not mandatory and we have not found it necessary to do so.

98 We note that this approach is not inconsistent with the approach of the applicant’s experts and Mr Galasso who referred to the LAM to understand the type of planting required along the Princes Highway frontage of the development.

    • LEP 2006

99 Mr Hutley and Mr Robertson submit that the zones in LEP 2006 and the Locality Strategies in DCP 2006 establish a three level hierarchy of centres being Zone 10 – Neighbourhood Centre, Zone 9 – Local Centre (which includes Kirrawee Town Centre) and Zone 8 – Urban Centre (which includes Sutherland). These three centre zones occur in locations throughout the Shire.

100 Mr Galasso accepts that the “centres” have different roles but that:

          …nowhere within either the LEP or the DCP is any notion of a centres hierarchy established. Within the LEP no such concept is even marginally addressed; and within the DCP, whilst certain town/areas are addressed individually, they are not ranked inter-se sufficient to be able to establish any hierarchy.

101 The Brick Pit and other land in Kirrawee is within Zone 7 – Mixed Use Kirrawee. This zone is specific to Kirrawee and does not occur elsewhere in Sutherland. In Mr Hutley’s and Mr Robertson’s submission, the role of Zone 7 is different to that of Zone 9 and it is not part of the Kirrawee Town Centre referred to in the Zone 7 objectives. They submit that the Kirrawee Town Centre is that part of Kirrawee within Zone 9. The objectives of Zone 9 seek to maintain its role as a local centre and they submit that the proposal’s impact on these objectives should also be considered.

102 Mr Galasso submits that Kirrawee Town Centre is not limited to Zone 9 but that the Brick Pit site and other parts of Zone 7 are an integral part of Kirrawee Town Centre. Further he submits that the zoning of Zone 7 establishes that “Kirrawee is intended to grow and serve a broader function than a mere local centre area”.

103 To understand these competing submissions and determine whether there is a retail strategy established by LEP 2006, it is necessary to consider the objectives of the zones.

104 The zone objectives for each of the centre zones define different roles for the different centres being urban, local and neighbourhood. Although not explicit, this implies a hierarchy of centres or the strategic role the centre is to play in the Shire. It also indicates the role of retail in each type of centre.

105 Mr Galasso places considerable weight on the permissibility of “shops” in Zone 7 as providing an imprimatur for a supermarket of the size proposed. However, “shops” are permissible within each centre zone as well as in the mixed use zone and there are no numerical prescriptions on their size and intensity within the LEP controls. “Shops” whether a single corner shop or a supermarket are permissible within each zone, the test then being whether it is consistent with the zone objectives and other relevant controls. A number of the zone objectives are similar in each centre zone. However, each centre zone includes a different objective in relation to retailing and employment.

106 In Zone 9 the objectives include:

          (b) to promote viable, small, local and specialty shops to support the needs of the local community and provide local employment,

107 Zone 10 includes an objective that limits the scale of retail. It provides:

          (a) to promote small scale retail and business activities to serve the day to day needs of the surrounding local community.

108 Whereas Zone 8 has a broader range of permissible retail uses and does not include an objective that limits retail to a local catchment. Until LEP 2006 Amendment 4, the objectives for Zone 7 were silent on retail. Given the extensive range of objectives we interpret this absence to be that retailing, while permissible, was not a priority within the zone. Amendment 4 has clarified this omission.

109 Mr Galasso submits that the addition of objectives (k) and (l) in LEP 2006 Amendment 4 elevate the important role of retailing in Zone 7. He states that:


          Importantly, neither the LEP nor the DCP prohibit retail development on the subject site, or in Zone 7….. Although the Applicant’s submissions are that the amendments to the LEP and the DCP post-date the lodgment of the development application, and whilst necessary to be taken into account (in terms of the LEP amendments), and whilst required to be taken into account (in terms of the DCP amendments), those amendments in fact for the first time speak in a positive sense about retail development in Zone 7. Quite ironically, this, for the first time, points to and contemplates retail development on the subject site, and more extensively within Zone 7…..

110 We do not accept that the introduction of these objectives should be interpreted in this manner. Rather, it appears that the objectives were introduced to clarify the role of retail in Zone 7. While the use was permissible there were no objectives for shops. The primary role of the zone when the objectives are read as a whole is to encourage residential uses in conjunction with some employment generating uses to create a live/work precinct.

111 We accept that it is not clear what the term Kirrawee Town Centre refers to in the Zone 7 objectives. Different planning documents use different terms to refer to the existing shops in Oak Road such as the existing Kirrawee Town Centre, Kirrawee Local Centre, Kirrawee Village and the Main Street Precinct. The planners agreed that Kirrawee Town Centre in LEP 2006 refers to the existing centre (Zone 9). However, we find that, as it is expressed in LEP 2006, the Kirrawee Town Centre as it develops will consist of both the Local Centre Zone (Zone 7) and the Mixed Use Zone (Zone 7).

112 However, while both zones will be part of the future Kirrawee Town Centre their roles, as articulated in LEP 2006 and in greater detail in DCP 2006, are envisaged to be different. Kirrawee Town Centre would comprise distinct precincts: Zone 9 being primarily the retail precinct and the Zone 7 being primarily a residential and employment generating precinct with retail having a support role.

113 We do not accept Mr Galasso’s submissions that the retail role of the future Kirrawee Town Centre should be other than as a local centre, which is clearly stated in objective (b) of Zone 9.

114 We accept Mr Hutley’s submission that objectives for Zone 9 identify clearly its retail function as being to meet local needs. The retail role of Zone 7 needs to be considered within this context. It is clear that development of the Brick Pit site and other sites within Zone 7 will expand the role of Kirrawee Centre with a large increase in residential and commercial uses with retail meeting the needs of the increased population. However, we do not accept that LEP 2006 envisages that this will result in Kirrawee not remaining a local retail centre.

115 Objectives (k) and (l) of Zone 7 aim:

          (k) to ensure any expansion of retail activity within the zone maintains the role and function of Kirrawee Town Centre and does not adversely impact on the sustainability of other centres in the Sutherland Shire,
          (l) to ensure any new shops integrate with and support the existing Kirrawee Town Centre

116 Objective (k) requires that any expansion of retail in Zone 7 maintains the role and function of Kirrawee Town Centre. We accept that Kirrawee Town Centre can include both Zone 9 and Zone 7 but that its function, whether separately or combined, is as a local centre. It is inevitable that Kirrawee will grow with increased residential and to a lesser extent employment generating uses in Zone 7, but as we understand objective (k), retail in Zone 7 is to support that in Zone 9 and is to meet the needs of this expanded local population but is not to provide a broader regional function.

117 Further, objective (l) provides that new shops in Zone 7 should integrate with and support the existing Kirrawee Town Centre. We accept Mr Hutley’s submission that:


          These provisions confirm that the role of any development of the Brick Pit site vis-a-vis the Kirrawee Town Centre should be a “supporting” role, rather than a principal or dominating role as proposed by the applicant…..
    • DCP 2006

118 The role for each centre is described in greater detail in DCP 2006 and further clarifies the role envisaged for each centre.

119 Clause 1.a of Chapter 2 of DCP 2006 includes a Centre Strategy for Kirrawee. Relevantly this provides that:


          The intention of the strategy is not to be overly prescriptive, but to provide a strategic framework for future planning and design of the Town Centre. Detailed building envelopes have therefore not been developed.

          Rather, the key aspect of the approach is to prioritise the public domain, which means the new development should be designed in response to the scale and character of the street and open space area. This approach recognises that development controls in the private domain need to be flexible to meet market demand. It is also important that the framework responds to the community vision for Kirrawee Town Centre.

120 Clause 1.a.1 includes the following values and character for Brick Pit site


          Redevelopment of the Kirrawee Brick Pit complements the existing town centre by accommodating a variety of uses, possibly including residential, commercial, educational, community and open space.

121 The aim in Clause 1.b.1 to create a identifiable character for the town centre includes:


          Reinforce the role and function of the existing Oak Road retail precinct as the town centre of Kirrawee.

122 Clause 1.c provides specific strategies for precincts within the Kirrawee Centre including Precinct 1 – Main Street Precinct and Precinct 2 - Brick Pit Precinct.

123 The specific strategies for the Main Street Precinct relevantly include:

          Precinct 1: Main Street Precinct
          The Main Street, Oak Road, is the retail precinct for Kirrawee Village. 1-2 storey street edge buildings define the precinct. New corner buildings at the northern and southern ends will define the edges of the precinct.
          Expansion of the retail precinct south over the railway is desirable in the longer term as the local population grows. Expansion of the south part will include train bus interchange, bus stops and shelters and necessary space to accommodate future transport activities. Those changes will help identify the precinct from President Avenue. Pollard and Rotary Park will be enhanced and Pollard Park will be integrated to become the gateway.
          This strategy seeks to provide the following:
      • Retain the main character of the street.
                  ……
      • The retail precinct is encouraged to expand allowing retail uses to extend around the corner into Flora Street for a short distance.
                  ……
      • The new buildings should allow retail uses fronting at ground level and residential or commercial uses on the upper floors.
                  ……
      • Area of commercial and retail space to be increased by approximately 3000sqm.

124 The specific strategies for the Brick Pit Precinct are:

          Precinct 2: Brick Pit Precinct
          The Brick Pit site is the main focus of future development. It presents huge potential for a mix of development including mixed employment, a variety of housing types including apartments, live / work building types, and accessible building for aged and disabled people. The Brick Pit has the potential to become an urban lifestyle area with high amenity, easy access to transport, and good access to facilities and services.
          The Brick Pit has been disused for some time. There is contamination to both soil and groundwater and, because of the unstable edges of the Pit, risks to pedestrians. There is a cost implication associated with the remediation of those edges. This strategy promotes and / or provides the following:
      • A lively mixed use precinct close to public transport and shops.
      • New streets creating a permeable block structure and connectivity
      • Larger barrier type apartment buildings located along the Princes Highway frontage with large landscape setbacks to reduce noise impacts and improve amenity and street address.
      • Mixed employment / residential developments close to existing James Cook Business Park as a transition between existing industrial and future residential development.
      • Mixed employment/ residential developments along Princes Highway and Flora Street.
      • Housing for older people or people with a disability especially high care (nursing home) and low care (hostel) housing, be considered for any residential component on the Brick Pit Site.
      • Native tree plantation to proposed new streets.
      • Clear car parking spaces in between new street trees.
      • New pavement and street furniture should be incorporated within development applications, consistent with overall concept of town centre design.
      • Proposed 0.9Ha public open space zoned as Park, including an amphitheatre, an outdoor café, artificial lake and community toilets. Park will include existing remnants of Sydney Turpentine Ironbark Forest and native flora. The park will be funded by the contributions of the developers within the study area.
      • Proposed a total of 0.135Ha Public Open Space as pocket parks.
      • Shops within the Mixed Use – Kirrawee zone shall not due to their size or intensity create a second town centre. Development of the mixed use zone shall not undermine the function of the Kirrawee Local Centre as the town centre for the locality, meeting the regular shopping and service needs of the local community.
      • Shops within the Mixed Use – Kirrawee Zone shall help activate the public domain and enhance the predominately residential and non-retail commercial character of the site.
      • The design and siting of any shops within the Mixed Use - Kirrawee Zone shall have clear, direct accessible pedestrian links to the existing Oak Road retail precinct so that shops support the revitalisation of the retail function of the Kirrawee Local Centre.

125 Similar to LEP 2006, the DCP included no explicit references to retail prior to Amendment 4 when the last three strategies were added.

126 Chapter 2 section 2.a of DCP 2006 provides the strategy for Sutherland Centre, which relevantly includes:

          The key focus for the future of Sutherland Centre is to create a vibrant retail and administrative core which increases the existing level of retail activity and provides for the centre to be supported by appropriate residential densities and housing types. The strategy aims to achieve this through ensuring that development is of an appropriate scale
          and character to define Sutherland Centre.

          ……………….

          Notwithstanding the extensive redevelopment in the middle and outer rings of the centre, the majority of the retail core area is yet to be redeveloped. This DCP seeks to create a
          framework that fosters best practice in the development of residential and commercial buildings for these important remaining areas. The consolidation of allotments in certain
          areas may be necessary to achieve development which contributes to the enhancement of the town centre’s built form.

          The future (re)development of Sutherland Centre will enable the Centre to be characterised by increased residential development and administrative, office and cultural activities and also significantly improved retail functions……

          …….

          It is hoped that future development will include the introduction of a large-scale supermarket and discount department store, bulky goods retailers and small-scale active retailers. This range of retail activities will create variety and vitality throughout the centre.

          The comprehensive redevelopment of Sutherland Centre’s retail activities will support the significant increase in resident population anticipated by this Plan.

          Sutherland Centre plays a significant role in Sutherland Shire and is recognised as a district centre. The district role of the centre is reinforced by the concentration of major government functions and Council’s administrative services. Recent residential development surrounding the retail and commercial functions of the centre has highlighted the opportunities available for sustainable growth within the Sutherland Centre retail and commercial core.

          Sutherland Centre is a primary public transport node being located on the Cronulla/Illawarra/South Coast rail line and provides opportunities to build its role as the principal bus/rail interchange in the Shire.

127 We find that the Locality Strategies in Chapter 2 of DCP 2006 clearly define different roles for different centres and precincts. While there is no specific reference to a retail strategy or hierarchy this can be inferred through the different role of retailing in each centre or precinct. The function or importance of retailing is linked to the area or catchment it is proposed to serve, for example Kirrawee is identified as serving local needs whereas Sutherland is identified as serving a district role.

128 From the Locality Strategies for Sutherland and Kirrawee; including the Main Street Precinct and the Brick Pit Precinct, we conclude that there is an emphasis on the important role that retailing is to play in Sutherland Centre. Clearly the centre fulfils a number of other roles such as administrative, residential and as a transport interchange but retailing is also specifically identified as a major function that planning for the centre encourages.

129 Similarly in Kirrawee, Oak Road is identified as the retail precinct for Kirrawee, with limited opportunities for physical expansion. The Brick Pit Precinct identifies that its principal function is to provide a support role for retail in the existing centre and to meet the needs of the increased local population likely to result from residential and employment generating development in Zone 7.

Consistency with the Zone objectives

130 The question then becomes one of whether the proposal is consistent with objectives for Zone 7.

131 There is no clause in LEP 2006 that an application may only be approved if it is consistent with the objectives of the zone. Nonetheless we find that a consideration of the zone objectives and the consistency of the proposal with these objectives are relevant, although a finding of inconsistency would not result in an automatic failure of the application.

132 There was no disagreement that the residential component of the development (about 27,000 sqm GFA) and (following amendments) that the urban design and amenity of the development generally met the objectives for Zone 7.

133 To a lesser extent, the council was concerned about the amount of commercial floorspace to be provided (about 4,581 sqm GFA), particularly in proportion to the retail component (about 8,000 sqm GFA) and whether this met the employment generating and live/work objectives of the zone. Although, there was recognition that retailing would generate employment opportunities and the issue was not pressed other than in relation to the retail issue.

134 By far, the key difference between the parties related to the retail component of the development and whether this met the Zone 7 objectives (j), (k) and (l). This issue did not focus on the use per se but on the scale of the retail development. There was general agreement that retailing and a supermarket should be provided on the site. The site was seen as ideal for such a use as the brick pit created a large hole that now needs to be filled. A supermarket and parking is suited to such a below ground use. The main concern was that the size of the supermarket, the mini major and specialty retail was too large and beyond that required to meet the needs of the existing and future local population. The proposed retail component would be attractive to a wider catchment area and, if approved, would change the role of Kirrawee from a local centre and potentially compete with Sutherland.

135 The evidence of the council planning and economic experts on this issue changed markedly between amendments. The basis for the change was unclear and to a large extent contradictory given their initial evidence in response to the two supermarket proposal and their later evidence in respect of the one supermarket proposal. While we understand their change of opinion in response to the number of supermarkets, we do not understand their response in relation to the size of supermarkets. It appears that Mr Nash’s evidence relied strongly on that of Mr Haratsis, which we discuss below.

136 In assessing the proposal against the relevant retail objectives (j), (k) and (l) of Zone 7, if Kirrawee Town Centre is considered to be both Zone 7 and Zone 9, we accept that the increase in population generated by the development is likely to facilitate the re-vitalisation of the Kirrawee Town Centre and the Kirrawee railway station precinct as a whole (Zone 7 and 9). However, we do not accept that it will result in a revitalising of the existing Kirrawee Town Centre, which is envisaged to remain the main retail precinct of Kirrawee, or the Railway Precinct. The size of the retail proposal on the Brick Pit site will impact on the existing Kirrawee Town Centre. The evidence indicates, although inconclusive, that there may be an impact on individual retailers but that the existing centre is likely to remain viable. However, the evidence does not indicate that the existing Kirrawee Town Centre or the Kirrawee Railway Precinct will be “revitalised” in the face of such strong competition and therefore, the proposal is inconsistent with objective (j).

137 We find that the proposal is also inconsistent with objective (k) in relation to the role and function of Kirrawee Town Centre. As discussed above, the role and function of retailing in Kirrawee Town Centre as stated in objective (b) of Zone 9 is to promote viable, small, local and specialty shops to support the needs of the local population. The role of retailing in Zone 7 is to support this role as stated in objective (l) of Zone 7. Due to size of the retail component of the development, particularly the undisputed evidence that the supermarket would be the largest in the area and would attract people from a wide catchment area, the proposal is likely to elevate the retail role of Kirrawee Town Centre above that of a local centre.

202 Partly as a consequence of this consensus, we agreed to allow the applicant to amend its proposal. At this time, it was our view that the joint conferencing of the experts had, so it seemed, produced a more acceptable proposal in regards to the issues of stormwater and ecology. However, on returning to the Court with the final amended proposal in late June 2009, it became clear that the applicant had altered their pond design in a manner significantly different to the above agreement. Consequently, this resulted in further new issues.

203 The primary concern arising out of the final amended proposed development relates to the pond, its water quality and quantity and the physical shape of the pond edges (the batter slope).

204 In relation to water quality, the essence of the issue is what is an acceptable water quality standard for the proposed pond and its use as a drinking water source for the bats as well as for incidental exposure and contact with humans. In addition and of some significance, was the issue of surety in regards to the ongoing maintenance of any determined water standard for the pond.

205 Originally, the ecology experts for the applicant and council, Dr Robertson and Mr Drinnan, respectively, agreed that the water quality should be the ANZECC Water Quality Guidelines for Freshwater Lakes and Reservoirs. However, arising from the final amended plans now before the Court, the applicant has proposed a different water quality standard, one equivalent to that found in the nearby Engadine constructed wetland.


206 The Court has received limited evidence from the applicant as to why and precisely how the proposed pond system at the subject site will function in a similar way to the wetland at Engadine. We note that the applicant in its amended SEE describes the Engadine system as a stormwater pond. They also describe the treatment of water in the proposed pond would be consistent with the functioning of the Engadine system. It is apparent that the Engadine wetland system is significantly different from the pond proposed at the park in several important ways:


      (i) The Engadine wetland is not an enclosed system since it receives fresh water inputs and flushing from natural runoff from its upstream catchment. This enhances this system’s capacity to turnover its water body and to flush nutrients, contaminants and associated environmental problems such as algal blooms and related odours from the waterbody. The subject development’s pond is a limited open system, meaning its capacity to ‘self regulate’ is largely absent. We note that there will be some inflow to the pond (calculated at < 250 L/month per m3 of storage from the parkland and internal roads) along with direct evaporation and precipitation and overflow releases. However, the proposed biofiltration methods will not remove all of the total nitrogen and phosphorous and there is limited capacity once these are in the pond for the treatment of contaminants, particularly as they accrue overtime.

      The proposal to seal of the pond’s base will have the effect of stopping any vertical ground water fluxes with the pond system, which erases two potential beneficial opportunities: flushing and the provision of a potential water source to top up the lake. We note that the Joint Experts report on Contamination prepared by Mr Drinnan and Mr Kingswell stated that it was agreed that beneficial reuse of ground water on the site is not practical and that the issue can be managed by a condition stating that no groundwater can be reused on site. However, in oral evidence, Mr Drinnan and Mr Amos suggested that groundwater could be used to top up the pond in the event of a dry period causing the surface to fall below the agreed 800 sqm. In any case, the potential for the use of groundwater has not been given due consideration nor has it been explained properly why it could or should not be used. We note that there be a remaining contamination issue in relation to the pond’s bottom sediment, which is a matter that could be resolved by conditions of consent. Water quality testing results reported in Mr Kingswell’s statement of evidence, revealed that the water quality in the Brick Pit passed ANZECC quality guidelines for a wide range of contaminants. The conclusion of the water testing was that “ the physical and chemical parameters indicated that the water within the former brickpit showed no evidence of unacceptable impact by natural or anthropogenic factors ”.

      (ii) The Engadine wetland is a larger waterbody and has a macrophyte footprint to waterbody ratio of 1:3. Macrophytes and wetlands have a significant capacity for reducing nutrient and contaminant loading and associated algal blooms. The proposed pond at the subject site would require an estimated area of ~2400 sqm (equivalent ratio of 1:3 of waterbody : macrophytes, as per the Engadine wetland) for adequate natural biotreatment of waters. Further, water treatment is enhanced via flow and turnover in wetland systems, which will not be possible at the subject site because it is a closed system. Arising from these limitations, it was noted in Exhibit 24 (section 4.16, p. 3.3 and 3.4) that an on-site water treatment plant was required to maintain water quality. The Ecology experts noted in relation to this requirement: “ It is agreed provided that provision is made to maintain water quality in the proposed lake ”. The current proposal before the Court offers no such provision.

      (iii) The Engadine wetland is not generally accessible to the public, which means that it is less likely to be affected by rubbish and other deleterious human artefacts, which may have the potential to reduce water quality. In addition, the Council argued that because the wetland at Engadine is not associated with public recreational use a lesser water quality standard at this location is acceptable compared to that at the proposed site.

207 On the basis of the evidence before the Court, we have formed the view that there is insufficient information for us to compare the two systems, their use and functioning. Consequently, the proposal is unsatisfactory since it relies upon the Engadine wetland as an exemplar of the potential future functioning of the pond system at the subject site. These issues have the effect of causing us to have either or both (i) sufficient uncertainty about the outcome of the pond proposal, and (ii) that the information pertaining to design and likely outcomes is of an inadequate standard to warrant refusal of the application. These issues can be summarised as follows:

      • The Engadine system is of a different size, physical and biological functioning (including inputs, throughputs and outputs) and has a different application and relationship with respect to human use than that proposed at the subject site. Consequently, the differences are uncertain and of such magnitude that it is inappropriate to use the Engadine system as a comparison of what may be achieved at the subject site.
      • The reliance on a water quality standard in the proposed pond that is not suitable for the dual use of habitat provision for threatened species as well as recreational activities in the adjacent park. The applicant proposes a water quality standard equivalent to that in the Engadine wetland compared to those stated in the ANZECC Water Quality Guidelines for Freshwater Lakes and Reservoirs, as preferred by the council.
      • There is a lack of evidentiary material demonstrating that the water quality will be maintained in perpetuity in the pond, such that as a very minimum, it meets the needs of endangered species. Alternatively, in the Council’s case, there is insufficient explanation as to how the water quality will continue to meet the aforementioned ANZECC standard. Indeed, in order to achieve acceptable water quality standards it was agreed by Dr Robertson, after being advised by Mr Drinnan, that sufficient mechanical methods must be in place to protect the drinking water source for benefit of the threatened species.

208 The Court understands that there was an element of conflicting evidence about the acceptability of a specific water quality standard for the threatened bats that use the Brick Pit site. Dr Robertson’s opinion that was based on field observations were that the bats were not so constrained by water quality given that he had seen bats drinking from sewage treatment ponds. In oral evidence Mr Drinnan agreed that the attainment of the ANZECC guidelines for the bats represented the “high standard” and acknowledged that it was now accepted knowledge that the bats drank from the Engadine wetlands. Further, in oral evidence the ecological experts agreed that the critical factor for the Grey-headed flying fox bats was the provision of food sources more so than the provision of water. Nevertheless, there remains two salient facts arising out the current proposal:


      (i) Irrespective of the zoning of the park (Zone 13 – Public Open Space), the proposal intends to have no impact on the threatened fauna and as the Court understands it, the current application provides no information to demonstrate how water quality (ANZECC or Engadine standard) will be maintained in perpetuity. Dr Robertson in his oral evidence noted that there would indeed be some need for fine-tuning to ensure that the water body and its determined quality are maintained. We do not disagree with the applicant’s final submissions that maintaining water quality in a pond such as this is not “ novel ” and is “ commonplace ”. However, it is unfortunate that in amending its final design the applicant has failed to explain how this will be achieved and without this certainty, there can is no guarantee that the threatened fauna will not be negatively impacted.

      (ii) There remains a significant and unresolved difference of opinion between the council and the applicant in regards to the relationship between the use of the pond and its water quality. The land where the pond is to be located is within Zone 13 which provide the following objectives:
          (a) to enable development of land for open space and recreation purposes,
          (b) to provide active and passive open space, allowing for a range of recreational activities and facilities that meet the needs of all ages in the community,
          (c) to enable development ancillary to the primary legal use of land that will encourage the enjoyment of land in the zone,
          (d) to preserve public open space that enhances the scenic and environmental quality of Sutherland Shire.

209 Relevantly, the objectives require that the land provide for a range of recreational uses for all ages in the community. Thus, while some may prefer a more passive interaction with the adjoining water body (e.g. reading) others may prefer a more active space. Children in particular are likely to fall into this latter category. Further, it was the Council’s view they envisaged making use of the park for educational purposes that would require some access to the water for macroinvertebrate sampling. As noted correctly by Mr Galasso in his submissions, this would require that water quality standards must be compliant with ANZECC water quality guidelines for freshwater lakes and reservoirs. Given the likely contamination of pond waters by faecal coliforms from birds and mammals, maintenance of the water quality to the higher ANZECC standard (or even the Engadine standard) would be problematic without some form of mechanical or chemical treatment, as was originally intended. In the creation of the park there is a significant opportunity to design a water body and to ensure ongoing maintenance and highest recreational use. These goals can be coupled to achieving a minimal environmental and human risk through the provision of an appropriate treatment train at the development stage. Although the applicant contends that access to the water (active recreational use) is not necessary or appropriate, there are significant recreational, educational and social benefits that may arise from the higher standard as opposed to the lesser standard and design as proposed.

210 The applicant also contends that a higher level of embellishment to the pond should be undertaken by the council, financed via funds gathered from existing and future s 94 contributions. We were not asked to adjudicate on the funding of the park or s 94 contributions. We also note that the FSR calculations for the development include the site area of the park, which provides significant additional floor space for the development. The park forms part of the applicant’s proposal and its adequacy must be assessed regardless of how it is to be funded.

211 We are of the view that the proposal in its current form is sub-optimal because the maintenance of the water quality standard is not certain and in its proposed form, results in a sub-optimal design and less holistic use of the park and its surrounds. Given the integral nature of the park and its ecological constraints and the amendments that have already occurred, we are not satisfied that the design can be left to a deferred commencement condition.

Water quantity impacts of the proposal

212 It was agreed by the experts Mr Drinnan and Dr Robertson that the development’s stormwater detention system should be used to ensure that there is sufficient water to maintain a waterbody of at least 800 sq m at all times.

213 It was also agreed in the Joint Town Planning, Urban Design, Traffic and Stormwater Expert Report that in order to guarantee the necessary water volume for the pond system, that the “desired option is likely to involve storage to ensure that no less than 150 L/month per m3 of pond value is provided”. The current proposal before the Court does not include supplementary storage, the consequences of which are water fluctuations resulting from prolonged periods of drought. Over the next 30 years these fluctuations were estimated to be in the order of ~300 mm for 90 % of the time but up to a maximum of 1.2 m during exceptionally dry periods (incorporating climate change effects).

214 The lack of definite provision to buffer the anticipated water fluctuations in the proposed pond is an unsatisfactory outcome of the design because it affects the agreed area and volume of water required to maintain a drinking water source for the threatened bat species. The predicted water fluctuations has resulted in an amended pond design that proposes a 1:2 batter and a ‘moat’ of fringing macrophytes along its eastern edge to discourage entry to the pond adjacent to the proposed park.

215 The council suggest that the proposed steep batters (1 vertical (V): 2 height (H)) at the edges of the pond are a response to the anticipated water fluctuations and the absence of any alternative water storage systems to deal with this issue. Mr Richards, disagreed that the batter design was a response to the potential for the pond water level to fluctuate. Nevertheless, construction of batters of this angle causes conflicts with good design as recommended in the Department of Land and Water Conservation (1997) Constructed Wetlands Manual. This document recommends that batters should have very gentle edge slopes between 1V:6H and 1V:8H. These would have the effect of providing wide areas for macrophyte growth (assisting bioflitration) as well as providing additional safety (entry and exit) for anyone who accidentally enters the waterbody.

216 The applicant’s response to the potential safety issues arising from such a steep batter has been to propose an adjacent fringing wetland (moat) and a pool-type fence along the eastern margins of the pond, where the public would interface with the pond. The applicant contends that these structures will provide a significant barrier to the pond and reduce the risk of park users falling into the pond.

217 Nonetheless, the result of the fluctuating water levels will be that the pond’s macrophytes (a contributor to biofiltration and water treatment – though argued to be insufficient by the Council on their own due their size) as well as the ‘moat’ vegetation may be negatively impacted by any prolonged dry periods. While we accept the Mr Galasso’s submission that this could be dealt with by the provision of an irrigation system, there was no detail provided as to how this would work and whether it would rely on reticulated or captured stormwater.

218 It is our understanding that the council objects to this design for several reasons. These include that it represents an inappropriate response for a recreational park/pond interface and that there is no detail in the design as to how the fringing moat (macrophyte) vegetation will be sustained during dry periods.

219 The council also objected to the proposed pool type fence as it was not only a response to poor design of the pond and its system, but that it provided insufficient security. A fence of this nature was, in the Council’s view, inadequate and that a “man-proof fence” would be required. Mr Dickson concurred with the view that the fence was an inappropriate response and that it conflicted with intended use of the park and the associated pond.

220 In oral evidence Mr Drinnan and Mr Amos for the Council said that principal issues relating to the applicant’s stormwater and water quality conundrum could be resolved with the following alterations:

      • by having a batter edge around the edge of the pool with a steepness of 1V:6H;
      • by ensuring the system was properly flushed, which would enable a proper turnover of the waterbody;
      • the inclusion of mechanical or chemical treatment device for the water to ensure water quality standards are maintained;
      • the use of groundwater or roof top water as a top up for the pond in the event of dry periods.

221 Mr Richards considered the current design was satisfactory but agreed it could be amended to take advantage of on-site rainwater capture and re-sue but this may impinge on the BASIX requirements for the development. He accepted that the suggestions of Mr Drinnan and Mr Amos are feasible but that these solutions would require extra water storage and pumping (which were proposed in previous versions of the design). Mr Richards noted that these aspects had been minimised in the current scheme before the Court. We note that there was no explanation from the applicant as to why the agreed amendments to the previous scheme were abandoned in favour of the current proposal.

222 Mr Drinnan asserted that the deficiencies in the current proposal could not amended via a deferred commencement condition because there would remain significant uncertainties in the outcome.

223 It is a requirement that the consent authority be satisfied that there will be no significant impact on the site’s listed species and the STIF community. Without a final design before the Court in regards to maintenance and functioning of the water system we are not provided with this satisfaction and therefore cannot approve the application.

224 Mr Drinnan noted that the issue relating to water and ecology was a long standing problem of the applicant’s proposal and that there had already been two amendments but the matter remained unresolved and consequently the proposal as it stands, with all its deficiencies, was in his view, unsatisfactory.

225 We also adhere to that view and are in agreement with the council that the significant and protracted problems related to the issue of integrating properly the water and ecological issues means that we are not confident about imposing a deferred commencement condition. Therefore, in the absence of a final and resolved scheme, this proposal remains inadequate for approval.

Urban design and landscape


226 The initial proposal raised significant disagreement between the urban design experts, which has been substantially resolved through the amendments. Despite this, there remained some substantial changes that these experts and the planners recommended. These included;

      • That the length of building N be reduced to 45m
      • The footprint of the revised Building N be moved
      • Building L be reduced in length by 4m.

227 Ms Morrish and Mr Dickson remained in disagreement on matters including the design of the pond, amenity issues with Buildings C, D and E, and the provision of landscaping along Princes Highway. Although the key disagreement centred on whether the proposal was sufficiently resolved after so many amendments to be approved or whether the changes still required were beyond conditions and resulted in uncertainty.

228 Mr Robertson submits that due to the urban design changes as well as the stormwater management and the road and parking designs, the proposal lacks finality and would not satisfy the principles established in GPT Limited v Belmorgan Property Development Pty Ltd [2008] NSWCA 256. He states that:


          These design inadequacies are simply too numerous and too inextricably related to other development objectives to be subject to deferred commencement conditions. In our submission, it would not only be unwise to grant consent without resolving them, it would be unlawful to do so

229 Whereas Mr Galasso submits that:


          To the extent, finally, that conditions of consent are an appropriate vehicle by which to accommodate slight design change (s 80A(1) of the Act), or to achieve “express outcomes or objectives” (s 80A(4) of the Act) it is to be recalled that this site is quite extensive in nature, and the level of specificity for design with respect to the site is uncommon. The level of specificity provided by the Applicant and the approach to fine tune the development in the circumstances of the significant size of the site, and the development, is proportionate and appropriate. It is neither unwise, nor unlawful, to impose such conditions and any submission to that effect (CWS [80]) is inappropriate, and wrong.

230 While it is disappointing that after amendments there are still matters that require further design resolution. However, it is a very large development and the application is for a masterplan and construction of Stage 1. Further development approval will be required for later stages. In relation to the urban design changes we do not accept Mr Robertson’s submission’s that they cannot be affected through conditions of consent or further development approvals. In our opinion, the nature of the urban design changes does not result in sufficient uncertainty that would warrant a refusal of the application.

Traffic

231 Similarly, in relation to the issues that remain in dispute between the traffic experts, we find that these would not warrant refusal of the application and could be affected through conditions of approval. As for other reasons we have found that the application must fail we have not adjudicated on the remaining issues between these experts.

Conclusion

232 The proposal is a major mixed use development on a significant site in Kirrawee. There was general support for the residential and commercial components of the development and, through the process of amendments, the urban design and traffic issues between the parties are largely resolved.

233 The main issue relates to the retail component of the development, particularly the size of the supermarket. While a supermarket and retail use of the site is appropriate there is concern about the size of the 4,500 sqm supermarket, particularly the impact it may have on Sutherland and Kirrawee, both economically and on the strategic role of these centres.

234 There is clearly an undersupply of retail floorspace within the region and a need for further supermarkets. The key question is whether Kirrawee is the appropriate location for such a large supermarket. We have concluded that LEP 2006 and DCP 2006 define a hierarchy of centres and that, in this hierarchy, retailing has a specific role to play. Kirrawee is intended to remain a local centre and retailing is to serve the needs of the local population. The Brick Pit site is intended to provide predominantly residential development with a commercial component and to a lesser extent retail supporting the needs of the new population and creating an active live/work environment. In our opinion, Kirrawee Town Centre together with the development of the Brick Pit site is envisaged to remain a local centre.

235 The agreed evidence of the experts is that the supermarket and associated retail will mainly be accessible by vehicles and will meet the shopping needs of a wider catchment. The submission of the applicant is that with the development of the Brick Pit site and other sites in the mixed use zone it is inevitable that Kirrawee Town Centre will not remain a local centre. In our opinion this is inconsistent with what is envisaged in the planning controls for the area.

236 No assessment of the economic impacts of a 4,500 supermarket has been undertaken. Given the scale of the development and its likely impacts we are not satisfied that we can rely on the previous economic analysis for the original two supermarket and a “judgement call” made by the experts. Particularly as there were significant doubts raised about the impact of the original scheme and its methodology in calculating the figure for retail trade data. Given the amendments to the proposal, we do not think it appropriate to further delay the proceedings for such an assessment to be undertaken nor was any request to this effect made by the parties.

237 In our opinion the size of the supermarket and retail component has the potential to impact on the sustainability of Kirrawee and Sutherland Centres. If not economically but in the strategic role that they play in the region, which needs to be thoroughly assessed.

238 The other concern is in relation to the role of the park and the final design of the pond. It is clear under the planning controls that the park is to be both a recreational facility as well as meet an ecological function. The evidence is that the park and pond can meet these roles but despite the amended schemes this has not been achieved. We are not satisfied that this matter can be resolved as a deferred commencement condition given its inter relationship with the ecological issues on the site.

239 For these reasons the application must fail.


240 The Orders of the Court are:

        1) The appeal is dismissed.
        2) The development application for a mixed use development at 566-594 Princes Highway, Kirrawee, is refused
        3) The exhibits, except Exhibit 49, are returned.
- 2 -

      __________________ __________________
      Annelise Tuor Dr Mark Taylor
      Commissioner of the Court Commissioner of the Court