PLANNING & ENVIRONMENT COURT OF QUEENSLAND
CITATION:
Redland City Council v Canaipa Developments Pty Ltd & Ors [2020] QPEC 65
PARTIES:
REDLAND CITY COUNCIL
(applicant)
v
CANAIPA DEVELOPMENTS PTY LTD
(ACN 118 404 461)
(first respondent)
IAN ROBERT LARKMAN
(second respondent)TLC JONES PTY LTD
(ACN 142 234 099)
AS TRUSTEE FOR TLC SUPERMARKETS UNIT TRUST NO 2
(third respondent)FILE NO: 4703 of 2019
DIVISION:
Planning and Environment
PROCEEDING:
Application
ORIGINATING COURT:
Brisbane
DELIVERED ON:
15 December 2020
DELIVERED AT:
Cairns
HEARING DATE:
28, 29, 30 September & 1 October 2020
JUDGE:
Morzone QC DCJ
ORDER:
1. Pursuant to s 180 of the Planning Act 2016, and subject to further order of the Court, the First and Second Respondents are to ensure compliance with the conditions of the changed development permit MC010476 for material change of use for mixed use (shop, commercial office and refreshment establishment) given on 4 March 2010 with respect to land described as Lot 100 on SP 204183 situated at 29-39 High Street, Russell Island, by ensuring that:
(a) there be no public access to any toilets on the Property, as required by Part 3 to Addendum 1 to Sustainable On-site Wastewater Management Plan for 29 High Street, Russell Island, August 2007 dated August 2007;
(b) all wastewater treated by an on-site sewage treatment plant complies with the requirements prescribed in Table 4 in Addendum 1; and
(c) access to the on-site sewage treatment plant in the western retaining wall adjoining Cambridge Road is provided so as to be generally in accordance with the “West Elevation” depicted in drawing 0652A202_6.
2. The timing requirements for the obligations set out in paragraph 1 above comprise:
(a) for paragraph 1(a), compliance is required forthwith
(b) for paragraphs 1(b) and 1(c), compliance is required upon the replacement of the existing on-site sewage treatment plan with any system delivered pursuant to the requirement of paragraph 3(b)(ii) below; and
(c) further for paragraphs 1(a) and/or 1(c), if an application to change the DA is made so as to remove the requirement to comply with the matters set out in those paragraphs, the requirement to comply with the paragraphs the subject of a pending change application be stayed, subject to the First and Second Respondent:
(i) not withdrawing the change application, unless they have a reasonable excuse; and
(ii) taking all necessary and reasonable steps to enable the change application to be decided as soon as practicable, unless they have a reasonable excuse; and
(iii) if the First and Second Respondents appeal the decision on the change application, them taking all necessary and reasonable steps to enable the appeal to be decided as soon as practicable, unless they have a reasonable excuse.
3. Pursuant to s 505(5) of the Environmental Protection Act 1994, and subject to further order of the court, within a period of 9 months from the date of this order, the First and Second Respondents are to:
(a) cease all operation of the existing Sewerage Treatment…
Keep reading for free
Create a free CaseChat account to read Redland City Council v Canaipa Developments Pty Ltd and Ors and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QPEC 65
- Decision Date
CaseChat Overview and Summary
The key legal issues before the court were whether the respondents had breached the conditions of their development permit by operating a non-compliant on-site sewage and wastewater treatment system, and if so, whether enforcement orders should be made to compel compliance. The court found that the respondents were in breach of the conditions of their development permit as the current wastewater treatment system was noncompliant. The court also found that the respondents were committing serious environmental harm by operating the noncompliant system. The court held that enforcement orders were necessary to ensure compliance with the permit conditions and to prevent further environmental harm.
The court ordered that the respondents must comply with certain conditions of their development permit, including restricting public access to toilets, ensuring treated wastewater met certain standards, and providing access to the wastewater treatment plant. The court also ordered that the respondents cease operation of their existing wastewater treatment system and either remove wastewater from the site or replace the system with an authorised one. The court further ordered that if the respondents failed to comply with these orders, they must cease all uses on the property pursuant to their development permit. The parties were granted liberty to apply for further orders.
Orders
Orders of the court
1. Pursuant to s 180 of the Planning Act 2016, and subject to further order of the Court, the First and Second Respondents are to ensure compliance with the conditions of the changed development permit MC010476 for material change of use for mixed use (shop, commercial office and refreshment establishment) given on 4 March 2010 with respect to land described as Lot 100 on SP 204183 situated at 29-39 High Street, Russell Island, by ensuring that:
(a) there be no public access to any toilets on the Property, as required by Part 3 to Addendum 1 to Sustainable On-site Wastewater Management Plan for 29 High Street, Russell Island, August 2007 dated August 2007;
(b) all wastewater treated by an on-site sewage treatment plant complies with the requirements prescribed in Table 4 in Addendum 1; and
(c) access to the on-site sewage treatment plant in the western retaining wall adjoining Cambridge Road is provided so as to be generally in accordance with the “West Elevation” depicted in drawing 0652A202_6.
2. The timing requirements for the obligations set out in paragraph 1 above comprise:
(a) for paragraph 1(a), compliance is required forthwith
(b) for paragraphs 1(b) and 1(c), compliance is required upon the replacement of the existing on-site sewage treatment plan with any system delivered pursuant to the requirement of paragraph 3(b)(ii) below; and
(c) further for paragraphs 1(a) and/or 1(c), if an application to change the DA is made so as to remove the requirement to comply with the matters set out in those paragraphs, the requirement to comply with the paragraphs the subject of a pending change application be stayed, subject to the First and Second Respondent:
(i) not withdrawing the change application, unless they have a reasonable excuse; and
(ii) taking all necessary and reasonable steps to enable the change application to be decided as soon as practicable, unless they have a reasonable excuse; and
(iii) if the First and Second Respondents appeal the decision on the change application, them taking all necessary and reasonable steps to enable the appeal to be decided as soon as practicable, unless they have a reasonable excuse.
3. Pursuant to s 505(5) of the Environmental Protection Act 1994, and subject to further order of the court, within a period of 9 months from the date of this order, the First and Second Respondents are to:
(a) cease all operation of the existing Sewerage Treatment Plant and the existing land application area underneath the car park on the Property; and
(b) either:
(i) remove and lawfully dispose of all wastewater produced on site by vacuum truck or other similar means; or
(ii) replace the existing Sewerage Treatment Plant and land application area with a new on-site wastewater treatment plant and land application area system authorised by an Environmental Authority for Environmentally Relevant Activity 63.
4. Pending cessation of the use of the existing Sewerage Treatment Plant, the First and Second Respondents are to comply with the requirements set out in paragraph 1 of the order of his Honour Judge Jones dated 28 February 2020.
5. Should the First and Second Respondents fail to comply with the requirements of paragraph 3 above, they are to cease all uses on the Property being undertaken pursuant to development permit MC010476.
6. The parties have liberty to apply with seven days’ notice in writing.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.