informed him that its return was imminent, Further, in the centre of a waling-piece or fender some fifty feet was missing and had been missing for some months. There was no suggestion as to when it was likely to be replaced. Both the buoy and the waling-piece were to obviate the danger to a vessel at the berth from northerly winds.
There was a suggestion below that the master should have laid out an additional anchor. This was rejected by all the learned judges and was not pursued before the Board.
The 7th July was a Saturday. Loading began on the 9th and continued till the 12th. About 11.45 a.m. on that day the wind freshened from the north and soon increased to gale force. The ship rolled and damaged herself and the wharf. The learned judge found that the absence of the buoy and of the waling-piece contri- buted to the damage.
The vessel with the necessary parts and equipment to repair the buoy arrived on the 12th and repairs began. The buoy was restored on the 13th.
Proceeding on the basis that the port or wharf was unsafe the appellant's case on construction is simple. It submits that under cl. 1 the charterer has undertaken to nominate a safe port or wharf for the loading. In breach of this provision the port or wharf nominated was unsafe and if damage to the ship flowed from that breach as a natural and probable consequence the charterer is liable for it.
The respondent did not of course suggest that the owner could be compelled to load at an unsafe port, but contends that if the charterer nominated an unsafe port, the owner could reject the nomination, as soon, presumably, as he had discovered that the port was unsafe. He might be entitled to damages for delay caused by the nomination. If, however, he accepted the nomination and went to the port the charterer would, it is said, in no circumstances be liable for damage flowing from the want of safety, unless liability arose under some other provision in the contract.
The two rival contentions can be illustrated by two citations, one from the majority judgment and the other from a judgment of Bailhache J., in Limerick S.S. Co. Ltd. v. W. H. Stott &Co. Ltd. 1 cited by Dixon C.J. 2: Clause 1 of the charter-party appears to
that is to the majority of the High Court, " to be designed to define the obligations of the shipowner with respect to loading ports and to prescribe, consequentially, a limitation upon the charterer's rights to designate such ports though, no doubt, under
1(1921) 1 K.B. 568.
2(1954) 91 C.L.R., at pp. 247, 248.