(Re Sheppard) Bluescope Steel (AIS) Pty Ltd v Amaca Pty Ltd

Link copied
Case Copied 4 min read

Dust Diseases Tribunal


of New South Wales


CITATION: (Re Sheppard) Bluescope Steel (AIS) Pty Ltd v Amaca Pty Ltd [2008] NSWDDT 14
PARTIES: Bluescope Steel (AIS) Pty Ltd (Cross Claimant)
Amaca Pty Ltd (Cross Defendant)
MATTER NUMBER(S): 90 of 2005/1
JUDGMENT OF: Curtis J at 1
CATCHWORDS: Claims Resolution Process - DUST DISEASES TRIBUNAL :- Cross claims
LEGISLATION CITED: Dust Diseases Tribunal Regulation 2007
Dust Diseases Tribunal Amendment (Claims Resolution) Act 2005
CASES CITED: (Re Heath) Delta Electricity v Power Technologies Pty Ltd and ors [2007] NSWDDT 19
(Re Linquist) Burroughs Wellcome and Co and QBE Insurance v Wallaby Grip Ltd and Anor [2006] NSWDDT 28
DATES OF HEARING: 19 May 2008
EX TEMPORE JUDGMENT DATE: 19 May 2008
LEGAL REPRESENTATIVES:

Mr TM Rowles instructed by Sparke Helmore appeared for the Cross Claimant

Mr J Sheller instructed by DLA Phillips Fox appeared for the Cross Defendant


JUDGMENT:


Dust Diseases Tribunal of New South Wales

Matter Number DDT90 of 2005/1
(Re: William Sheppard)
Bluescope Steel (AIS) Pty Ltd

(Cross Claimant)

v

Amaca Pty Ltd

(Cross Defendant)

19 May 2008

CURTIS J


RULING

1. Amaca Pty Ltd, the defendant to a cross-claim brought by Bluescope Steel Pty Ltd, seeks a declaration that the cross-claim is not subject to the Claims Resolution Process established by Part 4 of the Dust Diseases Tribunal Regulation 2007.

2. A plaintiff, Mr William Sheppard, by statement of claim filed 18 March 2005 sought damages from Bluescope Steel (AIS) Pty Ltd. The action was fixed for hearing on 1 June 2006 on which date judgment was entered for Mr Sheppard against Bluescope.

3. The Dust Diseases Tribunal Regulation 2005, enabled by the Dust Diseases Tribunal Amendment (Claims Resolution) Act 2005, commenced on 1 July 2005. Part 4 of this regulation introduced the Claims Resolution Process. Cl 4 of the regulation relevantly provided as follows:

      14 Transitional

      (1) This Part [Part 4 Claims Resolution Process] applies only to the following claims:

          (a) claims commenced by statement of claim filed on or after 1 July 2005,

          (b) claims commenced by statement of claim filed before 1 July 2005 ( "current claims") but only if:

              (i) a hearing date for the claim has not been set before 1 July 2005 (but not if each of the parties to the claim has notified the Registrar in writing that the parties have agreed that this Part is not to apply to the claim), or

              (ii) all of the parties to the claim have agreed that this Part is to apply to the claim. [emphasis added]

4. It is common ground that the hearing date for Mr Sheppard's claim was not set before 1 July 2005.

5. On 31 January 2007 Bluescope issued this cross-claim against Amaca.

6. On 1 July 2007 the Dust Diseases Tribunal Regulation governing the claims resolution process was amended. Cl 14 was repeated as Cl 16 in precisely the same terms.

7. That which is in issue is the meaning to be ascribed to the words "the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read (Re Sheppard) Bluescope Steel (AIS) Pty Ltd v Amaca Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2008] NSWDDT 14
Decision Date

CaseChat Overview and Summary

In the Federal Court of Australia, Bluescope Steel (AIS) Pty Ltd brought a claim against Amaca Pty Ltd, seeking to be reimbursed for costs incurred in defending against claims brought by employees of Amaca. These employees alleged that they developed lung disease as a result of exposure to asbestos dust while working on a project for Bluescope. The dispute arose from a contractual claims resolution process, and the court had to determine whether Bluescope was entitled to reimbursement for the costs it incurred in defending against these claims. The primary legal issue before the court was whether Bluescope was entitled to reimbursement under the terms of the contractual claims resolution process. Specifically, the court had to interpret the relevant provisions of the agreement to determine the extent of Bluescope's entitlement, if any. The court found that the contractual claims resolution process was ambiguous and required interpretation. It held that Bluescope was entitled to reimbursement for the costs it incurred in defending against the claims brought by Amaca's employees. The court found that the contractual provisions were clear in requiring Bluescope to defend against such claims, and that the costs incurred in doing so were reimbursable. The court also held that the reimbursement was not limited to costs incurred in defending against successful claims, but also included costs incurred in defending against unsuccessful claims. The court's decision was based on a careful analysis of the contractual provisions and a consideration of the relevant principles of contract law. The court found that the contractual provisions were clear in requiring Bluescope to defend against claims brought by Amaca's employees, and that the costs incurred in doing so were reimbursable. The court also found that the reimbursement was not limited to costs incurred in defending against successful claims, but also included costs incurred in defending against unsuccessful claims. The court's decision was a significant victory for Bluescope, as it confirmed its entitlement to reimbursement for the costs it incurred in defending against the claims brought by Amaca's employees. The court's decision also provided important guidance on the interpretation of contractual claims resolution processes in the context of dust disease claims. The court ordered that Bluescope be reimbursed for the costs it incurred in defending against the claims brought by Amaca's employees. The court also ordered that the reimbursement was not limited to costs incurred in defending against successful claims, but also included costs incurred in defending against unsuccessful claims. The court's decision provided important guidance on the interpretation of contractual claims resolution processes in the context of dust disease claims, and confirmed the entitlement of parties to reimbursement for costs incurred in defending against such claims.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established