LAND COURT OF QUEENSLAND
CITATION: Re Pickering [2020] QLC 29 PARTIES: Rai Pickering
(applicant)FILE NOs: MRA016-20 (MLA 100206)
MRA017-20 (MLA 100207)DIVISION: General Division PROCEEDING: Hearing of application for mining lease and objection DELIVERED ON: 7 August 2020 DELIVERED AT: Brisbane HEARD ON: 29 July 2020 HEARD AT: Brisbane MEMBER: PG Stilgoe OAM ORDER: I recommend to the Minister for Natural Resources, Mines and Energy, as the Minister responsible for the Mineral Resources Act 1989, that MLA 100206 and MLA 100207 be granted. CATCHWORDS: ENERGY AND RESOURCES – MINERALS – COURTS OR TRIBUNALS EXERCISING JURISDICTION IN MINING MATTERS – QUEENSLAND – OTHER COURTS OR TRIBUNALS – where a small-scale gold miner applied for two mining leases near the Palmer River in far north Queensland – where the owner of the cattle station on which one of the leases was situated objected to the grant of both leases – where that sole objector was a non-active objector and did not appear at the hearing – whether to recommend the grant of the leases under s 269 of the Mineral Resources Act 1989 – consideration of the factors in s 269(4) of the Mineral Resources Act 1989 – where the Court recommended the grant of both leases
Mineral Resources Act 1989 s 269
APPEARANCES:
R Pickering, the applicant (self-represented)
Small scale operators have been mining for gold on the Palmer River for over a century. Many of these operations have been conducted on Palmerville Station, a 134,000 ha grazing property about 100 km north west of Port Douglas.
Rai Pickering has applied for two mining leases to allow him to mine gold and silver ore. MLA 100207 is a 54 ha area located on Palmerville Station. MLA 100206 is a 30.5 ha area located on the Palmer Goldfield Resources Reserve, which is bordered by Palmerville to the east, west and south. Mr Pickering intends to use a 5-10 tonne excavator, processing three tonnes per hour for eight hours per day. He thinks that he will process a total of 60,000 tonnes. Both leases include space for a camp, an open cut mine and a mill.
Mr Pickering has also applied for an environmental authority (APP0038367).
Chelsea on the Park Pty Ltd recently bought Palmerville Station. Chelsea objected to Mr Pickering’s leases but did not elect to be an active party in these proceedings and did not appear at the hearing.
Chelsea objects to Mr Pickering’s proposed mining leases on the following grounds:[1]
[1]“Attachment 1 Grounds of Objection” in filed document 1 of MRA016-20; “Attachment 1 Grounds of Objection” in filed document 1 of MRA017-20.
1. the areas are not sufficiently mineralised to justify the grant of the leases;
2. the leases will not result in an acceptable level of development and utilisation of the mineral resources on the leases;
3. the size and shape of the leases are not appropriate;
4. Mr Pickering has not demonstrated that he has the necessary financial or technical resources to mine the leases;
5.…
Keep reading for free
Create a free CaseChat account to read Re Pickering and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QLC 29
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included whether the applicant met the criteria for the grant of the leases, and whether the objector's non-active status and absence at the hearing should influence the court's decision. The court considered the factors outlined in section 269(4) of the Mineral Resources Act 1989, which include the applicant's past conduct, the potential environmental impact, and the public interest. After weighing these factors, the court concluded that the applicant was a suitable candidate for the leases and that the objector's absence did not preclude a recommendation.
In reaching its decision, the court emphasised the importance of small-scale mining activities to the local economy and the potential benefits of the proposed leases to the applicant and the region. The court also noted the lack of substantial opposition and the applicant's commitment to environmental protection. Consequently, the court recommended to the Minister for Natural Resources, Mines and Energy that both MLA 100206 and MLA 100207 be granted.
The final orders of the court were to recommend the grant of the mining leases MLA 100206 and MLA 100207 to the Minister for Natural Resources, Mines and Energy.
Orders
Orders of the court
I recommend to the Minister for Natural Resources, Mines and Energy, as the Minister responsible for the Mineral Resources Act 1989, that MLA 100206 and MLA 100207 be granted.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.