| CITATION: | RCTC Pty Ltd v Rappa [2010] QCAT 300 |
| PARTIES: | RCTC Pty Ltd |
| v | |
| Alejando & Frank Rappa |
| APPLICATION NUMBER: | BD252-07 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 25 & 26 February 2010; 10 June 2010 |
| HEARD AT: | Brisbane |
| DECISION OF: | Dr Elena Marchetti, Sessional Member |
| DELIVERED ON: | 29 June 2010 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: |
1. That the respondents pay the applicant the sum of $272,304.06 by 4:00 pm on 31 July 2010.
| CATCHWORDS : | Claim for payment of final two stages of contract; lack of evidence to support counter-claim for defective and incomplete work; QCAT Act – s 48; costs and interest awarded in favour of applicants. |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Ms McNeil of Counsel, instructed by Mr Adames, of Maunsell Pennington Solicitors |
| RESPONDENT: | Mr Lion |
REASONS FOR DECISION
Introduction
On 17 March 2006 the applicant and the respondents entered into a contract for the construction of a duplex (“the building”) at Lot 14 Vista Drive, Ashmore. The contract price was $628,291.00.
The claim is for the payments, which were due for the ‘fixing’ ($125,658.00) and ‘practical completion’ ($94,246.00) stages of the contract, which remain unpaid, together with interest and costs.
The respondents dispute the payment of the unpaid portion of the contract on the basis that the work was incomplete and defective, and in return make a counter-claim for an unspecified amount for what they claim they spent to complete and rectify the work (further particulars in relation to this portion of the claim appear below), together with costs. In paragraph VII of the ‘Further Particulars on Counterclaim’ (“the Further Particulars”), the respondents note that they paid $103,263.70 to ‘complete work left unfinished by the Applicant or not even started at the time of taking possession’. It is unclear, however, if this amount includes all of the defects and claims of incomplete work listed by the respondents.
The respondents request that an amount equivalent to what they spent to rectify the defects and complete the work be deducted off any amount owing under the contract or in the alternative, that any amount owing for the work which was completed by the applicant be calculated on the basis of a quantum meruit claim, which the respondents submit would be covered by the $422,387.00 they claim they have already paid to the applicant.
The respondents also claim that the applicant did not complete the work within a reasonable time and claim an amount of $15.00/day (as per Clause 23 of the contract) for 167 days (totalling $2,505.00) as damages for late completion.
The Dispute
The dispute involves a number of issues, which relate not only to the standard of the building work, but also to what was and was not included in the contract.
The contract documents comprised a Housing Industry Association New Home Construction Contract (June 2000 edition) (“the Contract”), a ‘Full Build Inclusions’ document, and ASK Plans.
The respondents’ grounds for refusing to pay the ‘fixing’ and ‘practical completion’ stages of the Contract are:
·…
Keep reading for free
Create a free CaseChat account to read RCTC Pty Ltd v Rappa and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] QCAT 300
- Decision Date
CaseChat Overview and Summary
The primary legal issues for the tribunal to determine were whether RCTC Pty Ltd was entitled to the final payment for their work and whether Rappa's counter-claim for defective and incomplete work was substantiated. The tribunal had to assess the evidence presented by both parties to determine if the final payment was due and if the respondent's claim was justified.
The tribunal found that RCTC Pty Ltd had provided sufficient evidence to support their claim for payment. Conversely, the tribunal determined that Rappa failed to provide adequate evidence to substantiate their counter-claim for defective and incomplete work. The tribunal emphasised the importance of the burden of proof resting on the party making the claim. Consequently, the tribunal dismissed the respondent's counter-claim and awarded costs and interest in favour of the applicant. The tribunal also made an order for payment of the outstanding amount owed to RCTC Pty Ltd, as well as an order for costs and interest.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi