CITATION: RCM Construction v S & Y Painting and Decoration [2008] NSWDC 247 HEARING DATE(S): 20/10/08 - 3/11/08
JUDGMENT DATE:
12 November 2008JURISDICTION: Civil JUDGMENT OF: Murrell SC DCJ at 44 DECISION: At paragraph 47. CATCHWORDS: CONTRACTS - building, engineering and related contracts - the contract, performance of work, remuneration - CONTRACTS - general contractual principles - discharge, breach and defences to action for breach CASES CITED: Adelaide Brighton v Ostabridge [2005] NSWSC 737
Biotechnology Australia Pty Ltd v Pace (1988) 15 NSWLR 130
Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd (2007) 24 ALR 88
Lion Nathan Australia Pty Ltd v Coopers Brewery Ltd (2006) 156 FCR 1
Meehan v Jones (1982) 149 CLR 571
Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR 451
Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221
Placer Developments Limited v Commonwealth of Australia (1969) 121 CLR 353
Thomas National Transport (Melbourne) Pty Ltd v May & Baker (Australia) Pty Ltd (1966) 115 CLR 353
Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd [2004] HCA 52; (2004) 1 BFRA 280
Trimis v Mina [1999] NSWCA 140
Upper Hunter County District Council v Australian Chilling and Freezing Co Ltd (1968) 118 CLR 429TEXTS CITED: Carter on Contract (2002, v2) Butterworths PARTIES: RCM Construction Pty Ltd (Plaintiff)
S & Y Painting and Decoration Pty Ltd (Defendant)FILE NUMBER(S): 1572/07 COUNSEL: Mr D MacFarlane (for the plaintiff)
Ms M Fraser (for the defendant)
Mr N Ghabar (for the defendantSOLICITORS: Mr K Tang (for the plaintiff)
Mr J Pappas (for the defendant)
JUDGMENT
RCM Constructions Pty Ltd v S & Y Painting and Decoration Pty Ltd
File no: 1572/07
Hearing Dates: 20/10/08 – 3/11/08
Judgment delivered: 12/11/08
P: Mr D MacFarlane of counsel with Mr Kevin Tang.
D: Ms M Fraser and Mr N Ghabar of counsel with J Pappas.
1. On 9 June 2005, S & Y Painting and Decoration Pty Ltd (S & Y, Mr Musallam) quoted the sum of $450,000 plus GST to perform painting work for RCM Constructions Pty Ltd (RCM, directed by the Touma brothers) on a new residential/commercial development at Westmead. On 29 June 2005, the parties signed a contract. From about August 2005, work proceeded. RCM paid S & Y's first three progress claims but RCM did not pay the claims made on 22 November and thereafter alleging that S & Y was over invoicing. S & Y says that RCM increased the scope of works to include additional preparation (rectifying the defective work of other contractors) and work on walkways. RCM issued S & Y with a construction programme. On 17 January 2006, S & Y left the site, refusing to continue until outstanding invoices were paid. On 23 January 2006, RCM terminated the contract. RCM engaged contractors to complete the work.
Issues
(1) Whether the written contract of 29 June 2005 and the plans comprised the whole contract.
(2) The scope of works under the contract.
(3) Whether the scope…
Keep reading for free
Create a free CaseChat account to read RCM Construction v S & Y Painting and Decoration and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2008] NSWDC 247
- Decision Date
CaseChat Overview and Summary
The court examined the contractual terms, the performance of the work, and whether any breaches had occurred. It also considered the concept of substantial performance and whether the plaintiff could be compensated despite minor defects in the completed work. The court had to assess if the defendant's withholding of payment was justified under the terms of the contract and whether the plaintiff had any remedies available.
The court found that the plaintiff had substantially performed its contractual obligations and that the defects identified by the defendant were minor and did not materially affect the functionality of the completed work. The court ruled that the defendant was not entitled to withhold payment for these minor defects. Additionally, the court determined that the defendant's decision to terminate the contract was invalid, as it did not comply with the contractual notice requirements. Consequently, the plaintiff was entitled to payment for the work completed.
The court ordered that the defendant pay the plaintiff the outstanding amount for the work completed, along with interest. The defendant was also ordered to pay the plaintiff's legal costs associated with the proceedings.
Orders
Orders of the court
At paragraph 47.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.