Ray Laurence Constructions Pty Ltd v Nolks
[2010] NTSC 37
•16 July 2010
Ray Laurence Constructions Pty Ltd & Anor v Nolks [2010] NTSC 37
PARTIES: RAY LAURENCE CONSTRUCTIONS
PTY LTD(ACN 108 063 387) AND: CHARLES DICKMAN T/as RAY LAURENCE CONSTRUCTIONS v THORSTEN NOLKS TITLE OF COURT: SUPREME COURT OF THE
NORTHERN TERRITORYJURISDICTION: SUPREME COURT OF THE
NORTHERN TERRITORY
EXERCISING TERRITORY
JURISDICTIONFILE NO: 152 of 2006 (20631733) DELIVERED: 16 July 2010 HEARING DATES: 7, 8, 9, 10 & 11 December 2009 JUDGMENT OF: SOUTHWOOD J CATCHWORDS: CONTRACTS – Building contract – scope of the work – contract documents – contract price – practical completion – builder’s entitlement to payment – counterclaim – defects – delay – loss of use of house
Clyde Contractors Pty Limited ‘trading as Clyde Constructions’ v Northern Beaches Developments Pty Limited [2001] QCA 314; Murphy Corporation v Ackuman Design & Development ‘Queensland’ Pty Limited unreported
Supreme Court of Queensland 19 December 1991; Toll (FGCT) Pty Ltd v
Alphapharm Pty Ltd (2004) 79 ALJR 129; Walter Construction Group Ltd vWalker Corporation Ltd [2001] NSWSC 283, applied
Inverugie Investments Limited v Hackett [1995] 3 All ER 841; Westwood v
Cordwell [1983] Qd R 276, referred to
REPRESENTATION:
Counsel:
Plaintiffs: M Keith Defendant: W Roper Solicitors:
Plaintiffs: Minter Ellison Defendant: De Silva Hebron Judgment category classification: B
Judgment ID Number: Sou1007 Number of pages: 38 IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWINRay Laurence Constructions Pty Ltd & Anor v Nolks [2010] NTSC 37
No 152 of 2006 (20631733)
BETWEEN:
RAY LAURENCE CONSTRUCTIONS
PTY LTD
(ACN 108 063 387)
First Plaintiff
AND:
CHARLES DICKMAN T/as RAY LAURENCE CONSTRUCTIONS
Second Plaintiff
AND:
THORSTEN NOLKS
Defendant
CORAM: SOUTHWOOD J REASONS FOR JUDGMENT
(Delivered 16 July 2010)
Introduction
This proceeding involves a building dispute between Mr Charles Dickman, the builder, and Mr Thorsten Nolks, the property owner, about the construction of a house at 385 Reedbeds Road, Darwin River during the second half of 2004.
Mr Dickman claims that the work he was required to undertake reached a stage of practical completion and that under cl 18 of the building contract he was entitled to be paid in full. He claims the sum of $52,438 which is made up as follows:
| [4] |
| ||
| [5] | the following grounds. (1) The works undertaken by Mr Dickman did not |
1. Final progress claim $32,100.00 2. Variation for lining of veranda ceiling $13,625.00 3. Variation for installation of guttering $1,502.00 4. Variation for stencilling veranda floor $7,800.00 5. Variation for installation of gable vents $330.00 Less Variations reducing the scope of the work $2,919.00
In addition, Mr Dickman claims interest on the amount of $52,438.00 at a rate of 15 per cent per annum from 15 December 2004 under cl 5 of the building contract.
Mr Nolks alleges that Mr Dickman is not entitled to payment of his claim on Mr Dickman claims for that work. (4) The quantum of Mr Nolks’ counterclaim exceeds the quantum of Mr Dickman’s claim.
Mr Nolks conceded that on his behalf his father, Mr Frank Nolks, agreed to the four variations that are referred to in par [2] above which increased the scope of the contract works; and Mr Dickman completed the works which
were the subject of each of those variations. He also accepts the prices
claimed for the variations for the guttering, stencilling of the veranda floor
and gable vents.
Mr Dickman conceded that he is liable for the following defective works and the parties have agreed the cost of rectifying the works as set out below:
1. PVC pipes for waste condensate for air conditioning $261.80 2. The height of the finished concrete floor above the $11,000.00 surrounding ground is lower than specified in the plans
and drainage works around the house are required to
intercept and divert stormwater.
3. Defective gutter system $2,327.60
4. Defective door seals to external swing doors $27.50 5. Missing pop rivets in the soffit lining $71.50 6. Nonconforming overflow relief pipe over the overflow $330.00 relief gully 7. Septic tank lid needs to be raised $1,100.00
In addition to the defective works set out in par [7] above, Mr Nolks claims damages for the following matters which remain in dispute:
1. Defective mortar at the perpendicular ends of the $1,853.50 blocks used to build the eastern and kitchen walls of
the house2. Additional costs of the preparation of ‘as constructed’ $2,000.00 plans arising as a result of the builders failure to
complete all of the works in accordance with the plans
and engineering specifications3. General damages for loss of use of the house arising as $69,454.00 a result of the delay caused by the builders failure to
build the house in accordance with the approved plans
and engineering specifications4. Interest on the damages for loss of use of the house $16,454.60 5. Damages for investigating and diagnosing the defects $10,925.00
The total amount of damages claimed by Mr Nolks is $115,806.10.
The damages claimed for loss of use of the house and for investigating and diagnosing the defects are said to be caused by the builder’s failure to repair the defects and by the time taken to obtain the necessary certificates and approvals for other works which were not done in conformity with the plans and engineering specifications including, a failure to adequately compact the pad on which the house was built and constructing the concrete slab floor at a height less than that specified in the plans. Mr Nolks maintains that as a result of the defective works undertaken by Mr Dickman and his failures to comply with the plans and specifications when constructing the house, the house was not reasonably fit for use because Mr Nolks was unable to obtain an occupancy permit.
The issues
The following issues are the principal issues in the proceeding. (1) What was the contract price? (2) What were the contract documents? (3) Was Mr Dickman required to construct the pad on which the house was built? (4) Did the works undertaken by Mr Dickman reach the stage of practical completion? (5) Was Mr Dickman entitled to the payment of his final
accounts in full? (6) What was the price of the variation for cladding the
veranda ceiling? (7) Was the mortar at the perpendicular ends of the blocks
used to construct the walls of the house defective? (8) Did Mr Dickman’s
defective works and his breaches of contract prevent Mr Nolks from
obtaining an occupancy permit and cause him to suffer a loss of use of the
house for a period of time? (9) Was Mr Nolks entitled to recover the costs
of having the defects and breaches of contract investigated? (10) Was
Mr Nolks entitled to the cost of preparing the ‘as constructed’ plans?The evidence
| [12] |
| ||
| [13] |
| [15] | Laurence Constructions Pty Ltd registered a workmen’s lien on 8 March |
The following affidavits were read on behalf of Mr Nolks: an affidavit of on 24 November 2009, an affidavit of Frank Nolks sworn on 30 October 2009, a further affidavit of Mr Frank Nolks sworn on 24 November 2009, an affidavit of John Scott sworn on 21 October 2009, an affidavit of Andrew Williams sworn on 19 September 2009, an affidavit of John Bradley sworn on 29 October 2009, an affidavit of David Bowler sworn on 29 October 2009 and, in addition, oral evidence was led from Terrence John Roth.
Assignment of the contract
Before dealing with the principal issues referred to in par [11] above it is necessary to briefly deal with the question of assignment of the contract. During the hearing of this proceeding the first plaintiff, Ray Laurence
Constructions Pty Ltd, and Mr Dickman conceded that Mr Dickman had not validly assigned his interest under the building contract to the company. However, up until the hearing the plaintiffs maintained there had been such an assignment.
In par 19 of the Further Amended Statement of Claim it is pleaded that Ray Statement Claim, the first plaintiff sought enforcement of the workmen’s lien pursuant to the Workmen’s Lien Act and insofar as is necessary s 142 of the Land Title Act for the debt of $58,805.12.
The effect of the plaintiffs’ concession is that Ray Laurence Constructions Pty Ltd was not entitled to register a workmen’s lien and the company is not entitled to any relief as claimed in the Further Amended Statement of Claim.
| [18] | Mr Dickman about this topic. In summary, Mr Dickman’s evidence was that |
The contract price
Mr Dickman claimed the total contract price for the building work was $170,500. Mr Nolks maintained the contract price was $160,500. The dispute arose because the building contract which was executed by the parties on 30 March 2004 states, on page one, that the total price for the
building works to be undertaken by Mr Dickman was $160,500. Indeed, on Mr Dickman’s copy of the building contract, the price of $170,722 had been crossed out and the price of $160,500 had been written down.
I find that the contract price was $170,500. I accept the evidence of balance of the contract price or thereabouts, in cash. In accordance with Mr Nolks’ request the price written in the building contract was varied to reflect the maximum amount the bank was prepared to lend Mr Nolks.
| [20] | father of Mr Thorsten Nolks, about quoting on building a house for |
In more detail Mr Dickman’s evidence was as follows.
In about January 2004 he was contacted by Mr Frank Nolks, who is the prepared by an engineer, Mr Charles Chew. The Section 40 Certificate of Compliance specified a safe foundation bearing capacity of 150.0 kPa.
Before providing a quote for the building works Mr Dickman inspected the site at Reedbeds Road with Mr Frank Nolks. At the time he determined that the block would need some scrub cleared and the site levelled before construction could commence. Mr Frank Nolks said he would organise the site clearing and levelling earthworks for the house pad. Mr Dickman then provided a quote and a list of finishes outlining the scope of the building work he was to do for Mr Nolks. The schedule of finishes also recorded the building work which was to remain Mr Nolks’ responsibility.
| [22] |
| ||
| [23] |
| ||
| [24] |
The parties then executed the contracts. Both Mr Thorsten Nolks and of both documents under the heading “Extra Contract Terms” is an asterisk and a notation “Deposit as per quote”. Mr Dickman gave evidence to the effect that the purpose of this notation was to acknowledge the fact that $10,000 was being paid in cash to make up the total contract price of $170,500. It is also common ground that, after the building contract was executed by the parties and prior to payment of the first progress payment claim, Mr Nolks paid Mr Dickman the sum of $10,000 in cash. The payment of the $10,000 is admitted in par 17 of Mr Nolks’ Further Amended Defence to the Further Amended Statement of Claim and Setoff and Counterclaim.
| [25] | quotation and a schedule of finishes from Mr Dickman. Their evidence is |
Both Mr Thorsten Nolks and Mr Frank Nolks deny receiving a written were to be fitted to the house. They told Mr Dickman the doors were to be powder coated French doors. Mr Dickman then said that he had not allowed for powder coated French doors in his quote and he would need an extra $10,000 in cash to pay for the doors.
| [26] | Mr Dickman initially said to him he could build the house for the same price |
During his cross examination, Mr Nolks stated the following. When Mr Nolks’ evidence is really to concede the point in any event.
I do not accept either Mr Thorsten Nolks or Mr Frank Nolks’ evidence that they did not receive either Mr Dickman’s quote or his schedule of finishes. Their evidence is inconsistent with the notation on page 3 of the building
[1].
contract that a deposit was to be provided in accordance with the quotation. signature
It is also inconsistent with the fact that Mr Thorsten Nolks discovered the
schedule of finishes in his list of documents as a document that was in his
possession. Without the schedule of finishes there was no way of knowing
what work was to be done by Mr Nolks. It is inconceivable that
Mr Dickman would have provided the schedule of finishes without also
providing the written quote. Nor do I accept Mr Thorsten Nolks’ evidence
that he did not see the words, “* Deposit as per quote”, written on page
three of the building contract. He initialled each page of the contract.
There is very little on page three of the building contract. In any event,Contract documents
Clause 1.7 of the building contract defines the contract documents as follows:
“The contract documents: the plans, building schedule, building
specification and other documents showing what we are to do for
you.”Clause 1.8 of the building contract defines the work as follows:
| [32] |
“The work: the work to be done and completed under this contract as
shown in the contract documents.”
In par 5.1 of the Further Amended Defence to the Further Amended Statement of Claim and Set-off and Counterclaim, Mr Nolks claims that the contract documents are comprised of:
1. Plans and drawings with endorsed specifications and detailed instructions – 9 sheets numbered D4142-9 inclusive dated March 2003, and in relation to D4142-1 and D4142-2 amended on 26 April 2005, showing the building work to be done under the contract.
2. Northern Territory Building Act 1993 “Section 40 Certificate of Compliance” dated 13 March 2003.
3. Northern Territory Building Act 1993 Building Permit No. 160/82023/3/2 dated 13 April 2004.
4. Schedule of Conditions to Northern Territory Building Act 1993 Building Permit No. 160/82023/3/2.
5. Occupancy Check List attached to the Northern Territory Building Act 1993 Building Permit No. 160/82023/3/2.
Mr Dickman claims that the contract documents are comprised of the schedule of finishes he gave to Mr Nolks and the plans and drawings he was given by Mr Nolks. He denies that the contractual documents included the Building Permit, the Schedule attached thereto, the Occupancy Checklist or the Section 40 Certificate of Compliance.
I find that the contract documents are comprised of the following the plans and drawings (endorsed with specifications and detailed instructions) provided to Mr Dickman by Mr Nolks as certified by Mr Grant O’Callaghan; the Section 40 Certificate of Compliance; the Building Permit; and the Schedule of Conditions attached to the Building Permit.
| [35] | work to be done by the builder. The effect of the inclusion of the schedule |
| [33] | than that shown on the schedule of finishes. It is common ground that |
As to the schedule of finishes, it is clear that the plans contain more works plans. Mr Dickman’s price was based on the work the schedule of finishes stated he was to complete. His price was accepted by Mr Nolks.
| [34] | Clause 2 states that Mr Dickman was to do the work for Mr Nolks at the site, |
Clause 2 of the building contract is headed, “Our Main Obligations”. required by the engineer and by any statute and he was to use good and proper materials. The effect of the requirement to do the work as required by the engineer and by any statute is to establish that it was the intention of the parties to incorporate the Section 40 Certificate of Compliance and the Schedule annexed to the Building Permit as contract documents. The works could not go ahead without a Building Permit being obtained. Mr Dickman also acknowledged that he received a copy of the Section 40 Certificate of Compliance at about the time he received a copy of the plans.
The relevance of the contract documents is that they contain the scope of the that the builder was to prepare the pad on which the house was to be constructed. Consistent with this, there was a notation in the schedule of finishes that there was no applicable soil test required so far as the footings were concerned. The owner was to paint any part of the verandas that required painting. All sanitary tap wear and fittings were to be supplied by the owner. All laundry tubs and tap wear were to be supplied by the owner. The shower screens were to be supplied by the owner. The owner was responsible for all electrical work. All tiles were to be supplied by the owner. The kitchen was to be supplied by the owner. The bedroom robes including the robes in the master bedroom were to be supplied by the owner. All painting was to be completed by the owner. All air conditioning was to be supplied by the owner.
The effect of the inclusion of the schedule of conditions annexed to the Building Permit was as follows. The building could not be occupied unless a Permit to Occupy had been issued by the building certifier (cl 4). It was the builder’s responsibility to confirm that the minimum safe bearing capacity as noted on the structural engineer’s certificate and/or certified drawings is achieved by the foundation prior to placement of any footings. Should the bearing capacity not be achieved, revised footing and/or slab details are to be provided by the builder for approval (cl 14). Prior to the commencement of building works, the site classification report prepared by geo-technical engineer shall be provided to the building certifier. The said report is required to confirm a site classification of Class S in accordance with the requirements of the certifying structural engineer (cl 15). Significantly, the only onus, of relevance, cast upon the builder was to check that the minimum safe bearing capacity was achieved by the foundation prior to the placement of any footings and, if it was not, to obtain a revised footing and/or slab detail. The builder was not required to obtain a site classification report.
Was Mr Dickman required to construct the pad for the house?
I find that Mr Dickman was not required to construct the earth pad on which the house was built. Such work was not included in Mr Dickman’s schedule of finishes. I also accept Mr Dickman’s evidence in this regard. I prefer his evidence to the evidence of Mr Nolks and Mr Frank Nolks.
| [38] | inspected the site at Reedbeds Road with Mr Frank Nolks. At the time he |
Mr Dickman’s evidence was that before providing a quote for the works he stated that he would organise the site clearing and levelling works for the house pad. Mr Dickman advised Mr Nolks that he would need the site cleared of scrub and levelled before the footings could be dug. Mr Frank Nolks advised him that he had a contractor to do the work, Mick from Mick’s Dirt Works.
| [39] | the purpose of inspecting the earthwork. Nothing had been done. After he |
In or about June 2004 Mr Dickman checked the site at Reedbeds Road for Approximately one week later he pegged the area where the house was to be constructed so the plumber could dig the trenches for the plumbing works. At the time the plumber dug the trenches, no further earthworks had been completed at the site. On 13 July 2004 he went to the site and dug the footings. While digging the footings he had to remove additional vegetation including tree roots from the site. Mr Dickman had no problem digging the footings other than the fact he had to remove some vegetation at the same time.
Practical completion
| [40] |
Counsel for Mr Nolks submitted that the building works completed by that in order for the works to reach the stage of practical completion the works had to be reasonably fit for use. The relevant use of a home is occupation of the home. As the home could not be occupied when Mr Dickman completed his works the works were not fit for use. The home could not be occupied because the defects in the work and Mr Dickman’s breaches of contract precluded the certifier from approving the works and this meant an occupancy permit could not issue. The relevance of this submission is that, if the works which had been undertaken by Mr Dickman had not reached practical completion, Mr Dickman was not entitled to final payment in accordance with cl 18 of the building contract.
[41] Clause 18 of the building contract provides:
“18.1 When the work reaches practical completion, we will give you
a final account.
18.2 Within 7 days you must
18.2.1 inspect the work together with us 18.2.2 write down anything that is defective or incomplete in
a certificate of practical completion and sign it and
give it to us and18.2.3 pay the final account in full ‘that is, with no set off or
reduction’ by cash or bank cheque18.3 Then we will hand over the work, and return possession of the
site to you.18.4
So far as we accept responsibility, we must fix the items written in the certificate of practical completion within a responsible time after hand over.”
| [42] | sustained. The provisions of cl 18 and cl 1.10 and cl 1.15 of the contract do |
In my opinion, the submissions made by counsel for Mr Nolks cannot be written notice of any defective or incomplete parts of the work about three months after practical completion. Clause 21.1 of the building contract states that so far as the builder accepts responsibility for any defects the builder has a right to do the work and cl 21.3 provides that the builder must complete such work within a reasonable time. The defects liability provisions of the building contract do not replace the owner’s ordinary entitlement to claim damages for breach of contract or for defects. If the builder does not fix the work within a reasonable time or does not accept responsibility for a defect, the owner is entitled to maintain a claim for damages which would ordinarily be assessed by reference to the cost of engaging other builders to rectify the defective work. Further, the building contract does not contain any provisions whereby the owner can direct the builder to rectify any defects that are discovered during the course of the works.
Practical completion is a question of fact to be determined on the material evidence[2]. Unless the contract provides otherwise a certificate of practical completion is not essential for practical completion to be reached. The
meaning of practical completion will be determined in most cases by the
definition found in the subject contract[3]. It is not necessary for the works to
be defect free in order for practical completion to be reached[4].
The definition of practical completion in the building contract in this case also needs to be interpreted in its relevant factual matrix. Objectively assessing the intention of the parties, it cannot be said that it was their intention that upon the completion of Mr Dickman’s work a certifier would be able to give his approval for the issue of an Occupancy Permit. At all times it was contemplated that there would still be further works to be undertaken and completed by Mr Nolks before an Occupancy Permit could be issued. What was contemplated by cl 1.10 and cl 1.15 of the building contract was that Mr Dickman’s work be substantially complete such that the stages to be undertaken by Mr Nolks could be started. At no stage did Mr Dickman undertake to do all of the work necessary to be completed so that an occupancy permit could issue.
| [45] |
| ||
| [46] |
| ||
| [47] |
| ||
| [48] | From his site inspection, he found the house had been substantially |
In his report, which was in evidence, Mr Fong went on to state as follows. drawings with some noted exceptions architecturally. Internally, little distress was noted on the ceiling/walls/floor. Externally, hairline cracks on the block walls were found on all four walls, the majority of which were located above or below window/door openings. The walls were partially painted, some ‘perpend’ joints had obviously been raked out, presumably from previous investigations and some appeared to have been repaired. It would appear some movement in the walls were from initial settlement and/or from shrinkage of the concrete block walls. From observations made during his site inspection on 19 April 2006 he did not consider the premises to have suffered abnormal settlement and cracking of the floor slab and of masonry walls. He considered the movement which was evident was minor and it exhibited a likeness to shrinkage cracks. That is, normal shrinkage of the block works.
Mr Hadfield, who is a Senior Technical Officer (Plumbing) in Building Advisory Services, stated in an email to Mr Grant O’Callaghan that the spill level of the shower is the same level as the floor waste, which is 100 mm above the overflow relief gully, and complies with Schedule 5, Regulation 4 of the National Plumbing Code. During his re-examination by counsel for Mr Dickman, Mr O’Callaghan agreed that the issue involving the height of the overflow relief gully was a matter of interpretation of the relevant provisions.
| [51] |
| ||
| [52] | him to do additional works on the site. Those additional works involved the |
Was Mr Dickman entitled to the payment of his final account in full?
As practical completion had been reached then, under cl 18.2.3 of the building contract, Mr Nolks was required to pay the final account of Mr Dickman in full.
The price of the variation for cladding the veranda ceiling
Mr Dickman gave evidence that in September 2004 Mr Frank Nolks asked sum of $13,625 for lining all veranda ceilings with colour bond custom orb roof sheeting including all eaves with all flashing fixed; and $1,502 to supply and install 23 metres of cottage green 200 mm half round guttering with 3 x 100 mm PVC downpipes.
200 mm. It only goes in between the trusses around the perimeter of the
house immediately above the block walls. It is nothing to do with the lining
of the veranda ceiling. The vermin mesh goes in vertically above the
finished external block walls near where the trusses sit on top of the blocks.walls. Vermin mesh is comprised of pieces of mesh about 900 mm x approximately 3 metres wide and in other areas 4 metres wide. The veranda surrounds the whole of the external area of the house. Cladding the ceiling involved cladding an area of approximately 195 m² with colour bond custom orb roof sheeting. In order to place the colour bond on the ceiling of the veranda it was also necessary to first attach steel batons to the veranda trusses or rafters.
There is now no dispute in relation to the price charged for the guttering. Mr Nolks disputes that he received the quote for the lining of the veranda ceilings with colour bond. Mr Nolks said that he and his father were told that there would only be an extra charge of $2,000 to $3,000 if they changed
from vermin mesh protection to putting a lining on the veranda ceiling.
I prefer the evidence of Mr Dickman to Mr Nolks in this regard. As to the difference involved in the work, Mr Dickman gave the following evidence. The vermin mesh is only used to seal off between the trusses so that vermin cannot get into the building by passing over the top of the external block
It is unrealistic to suggest, as Mr Nolks did, that the agreed variation would only involve an additional cost of some $2,000 to $3,000. I do not accept his evidence that Mr Dickman said he could do the extra work for that amount. Nor do I accept his evidence that Mr Dickman did not provide him with a written price for this variation. Mr Dickman consistently provided written quotes for any work he was to undertake.
Was the mortar defective?
In par 40 to par 47 of the Further Amended Defence and Counterclaim to the Further Amended Statement of Claim and Setoff and Counterclaim Mr Nolks pleads as follows:
“40. Drawing D4142-4 of the plans and drawings pleaded in
paragraph 5.1.2 of the defence, note 8, specified as follows:
“External block work and roof to be weather proofed to
prevent the penetration of water that could cause unhealthy or
dangerous conditions or loss of amenity for occupants and
undue dampness or deterioration to building.”41.
Drawing D4142-4 of the plans and drawings pleaded in paragraph 5.1.2 of the defence, note 16, specified as follows:
“Concrete masonry walls shall be constructed in accordance
with the requirements of AS3700.”42.
The mortar in the eastern and kitchen walls of the dwelling is of low strength and does not meet the standard of M3 or M4 quality specified in AS3700.
43.
The weak mortar pleaded in the previous paragraph is disintegrating, allowing water and moisture penetration into the dwelling and is at risk of further disintegrating.
44.
The external block work of the dwelling is not weather proof as specified.
45.
In some areas of the eastern and kitchen walls of the dwelling mortar is missing.
46.
The second plaintiff, or in the alternative the first plaintiff, breached his contractual obligations in that:
46.1
The mortar in the eastern and kitchen sides of the dwelling is of low strength and does not meet the standard specified in AS3700.
46.2 He failed to construct the external block work to be
weather proof to prevent the penetration of water.47. As a consequence of the breaches pleaded in paragraph 46 injection of suitable replacement grout of an adequate strength and durability before the defendant may usefully paint the external block work or have such painting carried out by others.”
| [59] |
The burden of proof of these matters lies on Mr Nolks. In support of this claim Mr Nolks principally relied on the evidence of Mr John Scott and his father, Mr Frank Nolks. Mr John Scott’s evidence was that throughout the block walls of the building the mortar in the bed and perpend joints is soft and, in many cases, falling out. He stated it was also noticeable that the mortar in the lower courses appears to be adequate, however, at a level of around the fourth and fifth course there were obvious differences in the mortar quality.
| [58] | with Mr Dickman. He used his fingernail to show him how soft some of the |
The evidence of Mr Frank Nolks was that he raised the issue of the mortar the mortar using a 20 cent coin. He realised there was something wrong with the mortar when he was painting the inside walls with a roller and the mortar between the block work started sticking to the roller. When he saw what was happening he examined the mortar and found it to be quite soft and sandy in texture.
As to mortar sticking to a roller, Mr Dickman gave the following works. The block walls are covered in sand. The mortar does not actually fall out in clumps. In order to avoid material sticking to a roller being used to apply paint to the wall, it is necessary to prepare the wall which is to be painted by brushing it first with a broom. Brushing the wall with a broom will take off all of the loose bits of sand. Mr Dickman never saw any evidence of the mortar coming out in chunks. He also denied that the mortar had arrived at the site as at 1 June 2004.
| [60] | site inspection on or about 23 October 2006, he observed a number of |
The evidence of Mr Brears, who Mr Dickman relied on, is that during his coat of paint on the external surface of the block walls. Normally three coats of a specific type of exterior quality paint are applied to the external surface of block walls. Mr Brears did not see any moisture on the inside of the building.
Mr Dickman gave evidence that he attended at the site on or about 6 December 2004 and repaired the ‘perpends’ in the block work as necessary. When he inspected the walls there was no mortar which came out
in clumps. He also prepared a video of the walls which was tendered in
evidence and he took away a piece of mortar for testing.
In my opinion, the evidence called on behalf of Mr Nolks does not establish that the concrete masonry walls were not constructed in accordance with the requirements of AS3700 or that the mortar in the eastern and kitchen walls
| was of low strength which did not meet the standard of M3 or M4 quality as specified in AS3700. Nor does the evidence establish that the cement was disintegrating allowing water and moisture penetration into the dwelling. All that is established by the evidence is that some of the mortar in the ‘perpends’ in the block walls has not been finished off in a workmanlike manner. As is apparent from the evidence of Mr Brears, to the extent there was any defective workmanship, it was not such as to preclude painting. On his evidence a number of the inside walls have been painted. The proper approach to the resolution of this problem was to ask Mr Dickman to fill in the ‘perpends’ as necessary with grout and, if he failed to do so within a reasonable time, to have the work attended to by the painter or someone else. | |
| [63] | defective in the sense that some of the mortar at the ‘perpends’ of the blocks |
In my opinion the mortar is only defective in a minor way. The work is that the quantum of rectifying this defect is $1,853.50, I would have accepted Mr Brears’ evidence that it would only cost about $1000 to rectify this defect.
Loss of use of the house
Mr Nolks has claimed $69,454.60 as damages for delay. The amount is based on rental returns for an equivalent property to the Reedbeds Road house over the relevant period of the claim. In addition, he has claimed $16,454.60 as interest on these damages. Mr Nolks has claimed these
damages in circumstances where no financial loss has been suffered by him. He did not intend to rent out the house that was being built at 385 Reedbeds Road and he was not incurring any rental or other expenses while the house was being built. The basis of the delay claim is Mr Dickman’s failure to
| complete the building work in accordance with the contract. Mr Nolks maintains that, as a consequence of Mr Dickman’s failures, he has not been able to obtain an occupancy permit which would have enabled him to occupy and enjoy the house. | |||
| [65] |
| ||
| [66] | work which was his responsibility: electrical works including wiring of all |
As at 2 December 2009 Mr Nolks had still not attended to the following facility; installing wash basin in the bathroom and kitchen sink; proper markings to the electrical board and metre box; the provision of a termite certificate; the provision of an electrical certificate of compliance; and painting of the external walls. The fact that these matters have not been attended to means that an occupancy permit could not issue regardless of whether the works completed by Mr Dickman were defective.
| [68] | The Ulman and Nolan report established that the land on which the house |
There was nothing to preclude Mr Nolks attending to the matters referred to above. The reason he did not attend to these matters was that he unreasonably took the view that the house had to be demolished. He did so in circumstances where he was essentially unhappy about the house that he had chosen to build. During cross examination he was asked the following question and he gave the following answer.
COUNSEL: When did you decide that the house was going to
have to be demolished?MR NOLKS:
When did I decide that? Mmm. Well, after getting told that I can’t get a certificate obviously because I haven’t got a Section 40 and the levels that the
house was on. And it’s not what I’ve asked for to be built on the plan. Alright, I have an idea in my head of what I want, I had it put on paper by a
draftsman, I gave it to a builder and he built
something that was in his mind, not what I wanted.
The Section 40 Certificate of Compliance was never truly a major issue. caused any structural problems. Interestingly, in a report which Mr Nolks obtained from Mr Neil Clarke on 15 May 2007, Mr Clarke stated:
The permit to build schedule of conditions – document 6 has points of the sandy fill under the concrete floor. This material is approximately 150 mm thick and is lightly compacted. It is being used to level the site and to act as protection to the waterproof membrane. We did not expect this material to be under the slab beams that support the masonry walls.
14 and 15 that relate to ground conditions. Point 14 calls for the
specified minimum safe bearing capacity to be confirmed onsite.
Point 15 calls for class S ground conditions to be verified onsite.
Point 14 was reviewed by the Ulman and Nolan test report where the
bearing capacity was reduced from 150 kPa to 100 kPa. We are of
the opinion that the document foundation system is adequate for
100 kPa. Point 15 was confirmed by the Ulman and Nolan report.Our inspection of March 2007 did not highlight any structural movement or deterioration in the raft concrete slab or the walls supported by it and thus it would appear the fill material has not deteriorated.
We have found no reference in the documents we received that indicates the building certifier has requested structural certification of the fill material under the raft slab.
The permit to build drawings do not specify the compaction level of the placed fill under the raft slab and only refer to “compacted fill” and call for 50 mm of sand. It would appear the builder has met this
basic requirement.
In my opinion, Mr Nolks has failed to mitigate his loss. Given the contents of Ulman and Nolan report which he obtained in March 2005, there was nothing to prevent him obtaining a further Section 40 Certificate of Compliance early in the piece. Nor was there anything precluding him from organising other tradesmen to attend to the defects in Mr Dickman’s work. Further, between 2007 and 2009 he prevented Mr Dickman from going onto site to attend to the repair of defects.
| [70] |
In my opinion, Mr Dickman’s breaches of contract have not caused use of the house is not made out.
Is Mr Nolks entitled to recover the cost of having the defects and breaches of the contact investigated?
| [71] | Nolan report. The fees charged by Ulman and Nolan were $1,705. It was |
I find that Mr Nolks was entitled to the cost of obtaining the Ulman and circumstances it was reasonable for Mr Nolks to obtain the Ulman and Nolan report.
Mr Nolks is not entitled to claim the costs of obtaining the other reports. Those reports by and large related to issues which have not been established by Mr Nolks. I accept the submissions of Mr Dickman’s counsel in this regard. The defendant has not relied on many of the consultants from whom reports were obtained.
Is Mr Nolks entitled to the costs of preparing the “as constructed” plans?
| [73] |
As a result of the manner in which Mr Dickman constructed the concrete release gully has been constructed, it will be necessary to amend the plans in order to prepare the “as constructed” plans. Mr Platt estimated that the cost of repairing these plans would be $2,000. I find that Mr Nolks is entitled to recover the sum of $2,000 for the preparation of these plans.
Summary of Mr Dickman’s damages
I find that Mr Dickman is entitled to the amounts set out in par [2] above. In addition, under the building contract, he is entitled to interest on this amount at the rate of 15 per cent per annum from 15 December 2004 until the date of judgment. Interest amounts to $43,917. This gives a total amount of $96,355.
Summary of Mr Nolks’ damages
In addition to the damages which are admitted by Mr Dickman as set out in par [7] above, I find that Mr Nolks is entitled to damages for the defective mortar in the sum of $1,853.50; the cost of the Ulman and Nolan report of $1,705; and the costs of preparation of the “as constructed” plans in the
amount of $2,000. In total, in respect of Mr Nolks’ claims against
Mr Dickman his damages amounted to $20,677.00.Orders
| [76] | Mr Nolks in the sum of $75,678. In respect of Ray Laurence Pty Ltd’s |
In the circumstances, I order that there be judgment for Mr Dickman against Mr Nolks. I will hear the parties further as to costs and any ancillary orders.
-------------------------------------
[1] Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 79 ALJR 129 at 137.
[2] Clyde Contractors Pty Limited ‘trading as Clyde Constructions’ v Northern Beaches Developments
Pty Limited [2001] QCA 314.
[3] Murphy Corporation v Ackuman Design & Development ‘Queensland’ Pty Limited unreported
Supreme Court of Queensland 19 December 1991 per Gee and Williams JJ.
[4] Walter Construction Group Ltd v Walker Corporation Ltd [2001] NSWSC 283.
[5] [1983] Qd R 276
[6] [1995] 3 All ER 841
3
0