Raub and Alderton v Wide Bay Constructions t/as Dixon Homes Hervey Bay

Link copied
Case Copied 15 min read

CITATION:

Raub & Alderton v Wide Bay Constructions t/as Dixon Homes Hervey Bay [2017] QCAT 90

PARTIES:

Sally Raub and Simon Alderton
(Applicants)

v

Wide Bay Constructions t/as Dixon Homes Hervey Bay

(Respondent)

APPLICATION NUMBER:

BDL100-15

MATTER TYPE:

Building matters

HEARING DATE:

13,14 October 2016

HEARD AT:

Hervey Bay

DECISION OF:

Member Quinlivan

DELIVERED ON:

28 March 2017

DELIVERED AT:

Brisbane

ORDERS MADE:

1. The applicant's claim for review of the QBCC's decision dated 22 April 2015 is dismissed.

2.    The applicant’s in relation to items 5, 6, 7 and 8 of the Amended Defective Work Schedule dated 19 February 2016 is dismissed.

3.    The claims by the applicants for the rectification of the applicant’s roof are dismissed.

CATCHWORDS:

Claim for rectification of alleged defective work, statutory warranty, expert conclave, exercise of review jurisdiction

APPEARANCES:

APPLICANT:

Sally Raub and Simon Alderton

RESPONDENT:

Ms R. Pezzuti, Solicitor, Bell Dixon Butler, Lawyers.

REASONS FOR DECISION

Background

  1. The applicants Sally Raub and Simon Alderton are the owners of a property at 31 Bluewater Road Booral, Queensland. On 10 December 2007 they entered into a contract with the respondents, Wide Bay Constructions Pty Ltd trading as Dixon Homes, Hervey Bay for the building of a home on their property.

  2. According to the applicants, a problem arose shortly after entering the contract about the increasing costs. That matter was resolved, the home was built and the final inspection certificate was issued on 6 November 2008.

  3. On 19 November 2014, the applicants made a complaint to the Queensland Building and Construction Commission (QBCC).

  4. At the time the applicants raised 6 items of concern. Subsequently on 12 January 2015 the QBCC issued the licensee with a Notice to Rectify or Complete in relation to 2 items as follows:

    ·Internal joint in the plasterboard wall beside the main bedroom doorway has cracked and the joint backing strip has displaced and lifted which is of an unacceptable standard of finish and does not match in with the surrounding level of detail (Item 1).

    ·Water entering the soffit area of the dwelling which is not in accordance with the Building Code of Australia 2007 volume 2 and is in causing damage to the surrounding building elements (Item 3)

  5. At the same time, the QBCC advised the applicants that items 2, 4 and 5 of their complaint had been investigated and there was insufficient evidence to reveal any obvious defective construction practices by the respondents at the time of inspection. Therefore, the QBCC was unable to provide the applicants with any further assistance to resolve of these matters. With respect to item 6, the QBCC advised that the matter had been investigated and rectified.

  6. On 21 May 2015, the applicants commenced proceedings in the Queensland Civil and Administrative Tribunal and filed an amended application on 19 February 2016. The applicants also filed an Amended Alleged Defective Work/Incomplete Work Schedule seeking rectification of defective work to an estimated value of $18,500.

  7. The Amended Schedule identified 8 items of alleged defective work:

    Item…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Raub and Alderton v Wide Bay Constructions t/as Dixon Homes... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] QCAT 90
Decision Date

CaseChat Overview and Summary

The plaintiffs, Raub and Alderton, sought rectification of alleged defective work performed by Wide Bay Constructions trading as Dixon Homes Hervey Bay. The dispute was heard in the Queensland Civil and Administrative Tribunal. The plaintiffs argued that the work carried out by the defendant was defective and sought rectification under the statutory warranty provisions. They also sought a review of the Queensland Building and Construction Commission's (QBCC) decision and an expert conclave to determine the defects. The defendant opposed the claims, arguing that the plaintiffs had not provided sufficient evidence of the defects and that the QBCC's decision was correct.

The court had to determine whether the plaintiffs had established that the work was defective and whether the QBCC's decision was correct. The court also had to determine whether an expert conclave was necessary and whether the plaintiffs were entitled to have the work rectified. The court considered the evidence provided by both parties and the applicable statutory provisions. The court found that the plaintiffs had not provided sufficient evidence to establish that the work was defective and that the QBCC's decision was correct. The court also found that an expert conclave was not necessary and that the plaintiffs were not entitled to have the work rectified.

The court dismissed the plaintiffs' claims for review of the QBCC's decision and for rectification of the work. The court also dismissed the plaintiffs' claims in relation to specific items listed in the Amended Defective Work Schedule. The court found that the plaintiffs had not provided sufficient evidence to establish that the work was defective and that the QBCC's decision was correct. The court further found that the plaintiffs were not entitled to have the work rectified and that an expert conclave was not necessary. The court dismissed all of the plaintiffs' claims.

Orders

Orders of the court

1. The applicant's claim for review of the QBCC's decision dated 22 April 2015 is dismissed.

2. The applicant’s in relation to items 5, 6, 7 and 8 of the Amended Defective Work Schedule dated 19 February 2016 is dismissed.

3. The claims by the applicants for the rectification of the applicant’s roof are dismissed.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established