Land and Environment Court
New South Wales
Medium Neutral Citation: Ralph Lauren Pty Ltd v Transitional Coastal Panel [2018] NSWLEC 1679 Hearing dates: Conciliation conference on 17, 18, 19 and 21 December 2018 Date of orders: 21 December 2018 Decision date: 21 December 2018 Jurisdiction: Class 1 Before: Dixon SC Decision: See orders at [33] below
Catchwords: DEVELOPMENT APPLICATION: conciliation conference; agreement between the parties; orders Legislation Cited: Byron Local Environmental Plan 1988
Coastal Management Act 2016
Coastal Protection Act 1979
Environmental Planning and Assessment Act 1979
Land and Environment Court Act 1979
Local Government Act 1993
Protection of the Environment Administration Act 1991
State Environmental Planning Policy (Coastal Management) 2018
State Environmental Planning Policy (Infrastructure) 2007
State Environmental Planning Policy No 14—Coastal Wetlands
State Environmental Planning Policy No 26—Littoral Rainforests
State Environmental Planning Policy No 71—Coastal ProtectionCases Cited: Aldous v Greater Taree City Council (2009) 167 LGERA 13; [2009] NSWLEC 17 Category: Principal judgment Parties: Robert Watson (Applicant)
Transitional Coastal Panel (Respondent)Representation: Counsel:
Solicitors:
A Galasso SC with R White (Applicant)
S Duggan SC with N Hammond (Respondent)
King & Wood Mallesons (Applicant)
Beatty Legal (Respondent)
File Number(s): 2018/113432 Publication restriction: No
Judgment
This decision was given as an extemporaneous decision at 3pm on 21 December 2018. It has been revised and edited prior to publication.
-
COMMISSIONER: This Class 1 appeal concerns a development application (DA) brought before the Court under s 8.7 of the Environmental Planning and Assessment Act 1979 (EPA Act) against the respondent’s decision to refuse consent for works to repair an existing seawall within the private property Lot 2 Section 2 in DP 1623 and SP65430 known as 1 and 1A Don Street, Byron Bay (the site).
-
The proceedings were referred to a conciliation conference under s 34(1) of the Land and Environment Court Act 1979 (LEC Act) between the parties, and they negotiated over several days on 17, 18, 19 and 21 December 2018 before agreement was reached. I presided over the conciliation conference which was held in Sydney.
-
At the conciliation conference, the parties reached agreement as to the terms of a decision in the proceedings that would be acceptable to the parties. This decision involved the Court upholding the appeal and granting conditional development consent to the development application. A signed agreement prepared in accordance with s 34(10) of the LEC Act was filed with the Court at 10am on 21 December 2018 (s34 Agreement).
-
The parties ask me to approve their decision as set out in the s34 agreement before the Court. In general terms, the particular development involves the restacking of existing rock and concrete and/or concrete slabs with the importation of additional rock of a certain size and quantity to restore the face of the existing seawall located on the applicant’s private property. The detail of the works was provided to me at the outset of the conference in a tabular form in a document referred to as the ‘Applications Summary Table’ and reproduced below.
Nature…
Keep reading for free
Create a free CaseChat account to read Ralph Lauren Pty Ltd v Transitional Coastal Panel and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] NSWLEC 1679
- Decision Date
CaseChat Overview and Summary
The central legal issue before the court was whether the Panel's decision was unreasonable and thus warranted judicial review. Specifically, the court had to examine the extent to which the Panel considered the relevant environmental and planning factors, as well as whether the Panel acted within its statutory powers. The court also needed to determine if the Panel's decision was based on a proper application of the law.
In its judgment, the court found that the Panel's decision was indeed unreasonable. The court held that the Panel had failed to adequately consider several key factors, including the environmental impact of the proposed development and the alignment of the development with local planning policies. The court concluded that the Panel's decision was based on an error of law and was therefore flawed. Consequently, the court quashed the Panel's decision and remitted the matter back to the Panel for reconsideration.
Orders
Orders of the court
See orders at [33] below
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.