CITATION:Rallen Australia Pty Ltd v Sweetpea Petroleum Pty Ltd [2023] NTSC 36
PARTIES:RALLEN AUSTRALIA PTY LTD
v
SWEETPEA PETROLEUM PTY LTD
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT exercising Territory jurisdiction
FILE NO:2022-00344-SC
DELIVERED: 20 April 2023
HEARING DATES: 20 and 21 June 2022
JUDGMENT OF: Barr J
CATCHWORDS:
MINING AND PETROLEUM – Exploration permit – Pastoral property – Regulations required Tribunal to determine provisions of access agreement – Petroleum Act 1984 (NT) s 58(j) – Statutory condition of exploration permit that permittee conduct operations and activities so as not to interfere with the lawful rights or activities of any person – Tribunal determined that s 58(j) did not create jurisdictional impediment to determination by Tribunal of access agreement – Held on appeal that ‘lawful rights’ means rights as affected by grant of exploration permit and approval of access agreement – Tribunal did not err in law
MINING AND PETROLEUM – Exploration permit – Pastoral property – Certain operations prohibited within 200 m of any “artificial accumulation of water” – Land holder argued before Tribunal that water was artificially accumulated in all of its water infrastructure, including in-ground pipes – Tribunal held that water in tanks and troughs was an “artificial accumulation of water”, but not in pipes – Pipes were the means of distribution – Appellant argued that Tribunal wrongly adopted a reductionist approach and should have assessed entire water infrastructure to be an “artificial accumulation of water” – Held no error of law – Not established that in-ground pipes on their own or as components of water infrastructure necessarily came within description of an “artificial accumulation of water”.
NORTHERN TERRITORY CIVIL AND ADMINISTRATIVE TRIBUNAL – Application for leave to appeal to Supreme Court – Application for leave to appeal and appeal heard together – Appeal confined to questions of law – Error of law must be sufficient to vitiate the Tribunals decision – real possibility that error of law could have affected the Tribunal’s decision – Appellant failed to establish vitiating errors of law
Northern Territory Civil and Administrative Tribunal Act 2014 s 5, s 45, s 46(1), s 141
Petroleum Act 1984 (NT) s 3(1), s 3(2), s 28, s 29, s 58(j), s 81(1), s 82A, s 111(1)(a)
Petroleum Regulations 2020 (NT) r 12, r 13, r 14, r 17, r 26, r 29, r 57(2), r 57(3), Schedule 2
Wilson v Lowery (1993) 4 NTLR 79; Development Consent Authority v Phelps [2010] NTCA 3, 27 NTLR 174, followed
Lee v MacMahon Contractors Pty Ltd [2018] NTCA 7, 335 FLR 350, referred toCollector of Customs v Agfa-Gevaert Ltd (1996) 186 CLR 389; Australian Gas Light Company v Valuer-General (1940) 40 SR (NSW) 126; Vetter v Lake Macquarie City Council (2001) 202 CLR 439; Coco v The Queen (1993-1994) 179 CLR 427; CCM Holdings Trust Pty Ltd v Chief Commissioner of State Revenue [2013] NSWSC 1072, 97 ATR 509; Great Northern…
Keep reading for free
Create a free CaseChat account to read Rallen Australia Pty Ltd v Sweetpea Petroleum Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2023] NTSC 36
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included whether the Tribunal had the jurisdiction to determine the provisions of an access agreement, particularly regarding compensation for the use of land. Another significant issue was the interpretation of the term "artificial accumulation of water" under the Petroleum Act 1984 (NT). Rallen argued that the Tribunal erred in its determination that only water in tanks and troughs, and not the in-ground pipes, constituted an "artificial accumulation of water". The court had to assess whether the Tribunal’s interpretation was legally sound and whether the appellant had demonstrated any vitiating errors of law.
The court held that the Tribunal did not err in its interpretation of the statutory provisions or in its jurisdictional determination. The Tribunal correctly concluded that "lawful rights" under the Petroleum Act referred to rights as affected by the grant of the exploration permit and the approval of the access agreement. The court found no vitiating errors of law in the Tribunal's decision and upheld its interpretation that in-ground pipes did not necessarily fall within the definition of "artificial accumulation of water". The court emphasised that the error of law must be substantial enough to vitiate the Tribunal’s decision, a threshold the appellant failed to meet.
No orders were made in the appeal as the court found no substantial errors of law in the Tribunal's decision. The appeal was dismissed, and the Tribunal's determination regarding the access agreement provisions was upheld.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
Some of the matters considered and decided by the Tribunal are not contentious on this appeal and do not feature in the proposed grounds of appeal.[52] However, a particularly contentious issue, before the Tribunal and on appeal, is in relation to s 111 Petroleum Act 1984, the relevant parts of which are as follows:[53] 111Certain operations prohibited(1)Subject to this section, a permittee or licensee must not:(a)carry out operations, which would otherwise be permitted under this Act, on land that is:(i)used as, or within 50 m of land being used as, a residence, yard, garden, orchard or cultivated field; or(ii)used as, or within 200 m of land being used as, a cemetery; or(iii)within a distance of 200 m of any artificial accumulation of water or any outlet from which water may be obtained; and(b)construct a well, wellhead, pipeline or petroleum processing facility, which would otherwise be permitted under this Act, on land that is used as, or within 2 km of land being used as, a habitable dwelling; and(c)construct a well or well pad, which would otherwise be permitted under this Act, on land that is within 1 km of a designated bore.(2)The permittee or licensee may carry out operations on land mentioned in subsection (1)(a)(i) or (iii) with the written approval of:(a)the owner of the land or, if the occupier of the land has, in the land, an interest registered on the Register kept by the Registrar-General under Part 3 of the Land Title Act 2000, the occupier; and(b)any registered native title bodies corporate, or registered native title claimants, in relation to the land.(3)The permittee or licensee may carry out construction of a well or well pad on land mentioned in subsection (1)(c) with the written approval of:(a)the owner of the land or, if the occupier of the land has, in the land, an interest registered on the Register kept by the Registrar-General under Part 3 of the Land Title Act 2000, the occupier; and(b)any registered native title bodies corporate, or registered native title claimants, in relation to the land; and(c)the owner of the designated bore. The evidence of Sweetpea before the Tribunal was that it intended to access the exploration permit area on Tanumbirini using the existing pastoral track (known as the ‘central track’) running from the Carpenteria Highway in a southerly direction, along the line of a fence dividing the Southern Cross and Telecom paddocks. Running parallel to the track and within 200 metres of the track was a polythene pipe water reticulation system, which carried water between various bores, tanks and troughs used for the watering of Rallen’s cattle. Rallen argued that its water infrastructure, as a whole, was an “artificial accumulation of water” within the meaning of those words in s 111(1)(a)(iii) of the Act; further, that it comprised or included “outlets from which water may be obtained”. If those arguments were accepted, Sweetpea would have been prevented from carrying out otherwise permitted operations within a distance of 200 metres of any such artificial accumulation of water or water outlet.