DISTRICT COURT OF QUEENSLAND
CITATION:
R v Monty Khoury [2004] QDC 182
PARTIES:
THE CROWN
v
MONTY KHOURY
FILE NO/S:
793/2001
DIVISION:
Criminal
PROCEEDING:
Pre-trial application
ORIGINATING COURT:
District Court, Brisbane
DELIVERED ON:
17 June 2004
DELIVERED AT:
Brisbane
HEARING DATE:
25 and 26 March 2004
JUDGE:
Shanahan DCJ
ORDER:
Indictment number 793/2001 be permanently stayed. The indictment is to be kept on the file and not be proceeded with.
CATCHWORDS:
CRIMINAL LAW – ARSON – PERMANENT STAY OF PROCEEDINGS – INEXCUSABLE AND UNREASONABLE DELAY IN PROSECUTION – ABUSE OF CRIMINAL PROCESS
Where the alleged offence of arson occurred in September 1997 – Where no charges were laid, and the deputy coroner determined not to hold an inquest – Where an inquest was eventually held at the request of the insurer – Where an indictment was presented in the Beenleigh District Court in February 2001 - Where five separate trial listings were not proceeded with for various reasons – Where a number of Crown prosecutors were assigned to the file over the years – Where the Crown had difficulty particularising its case – Where the accused had incurred considerable expense as a result of the delays and at one stage ran out of funds – Where the court had indicated on a number of occasions that if the Crown did not proceed expeditiously with the matter it might be permanently stayed – Where the matter was not fully investigated – Where court orders for disclosure were not met – Where a large amount of material was not made available until April 2003 – Emotional and financial prejudice – Whether the circumstances amounted to an abuse of processCases cited:
Jago v The District Court of New South Wales (1989) 168 CLR 23
COUNSEL:
Mr S Vasta for the Crown
Mr R Mulholland QC for the accusedSOLICITORS:
Director of Public Prosecutions for the Crown
Gilshenan & Luton for the accused
This is an application seeking a permanent stay of criminal proceedings against the applicant. The submission is that the Crown has been guilty of inexcusable delay in prosecuting the matter. It is submitted that the delay is unreasonable and, in the circumstances, amounts to an abuse of the criminal process such as to make it difficult for the accused to obtain a fair trial.
It is necessary to set out the history of the matter.
History of the matter
On the night of 12 September 1997 a fire destroyed a furniture factory and most of its contents. The factory was leased to a company which was involved in the manufacture of furniture and the accused was a director of that company. The factory was insured by its owners and the accused’s business was also insured. The accused made an insurance claim in the sum of $1.88 million for loss of property and interruption…
Keep reading for free
Create a free CaseChat account to read R v Monty Khoury and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2004] QDC 182
- Decision Date
CaseChat Overview and Summary
The legal issues before the court centred on whether the substantial delays and lack of investigation constituted an abuse of process, warranting a permanent stay of proceedings. The court considered the impact of the delays on the accused, including emotional and financial prejudice, and whether the Crown's inability to particularise its case and meet disclosure orders amounted to an abuse of the criminal process.
The Supreme Court concluded that the extensive delays and failure to investigate thoroughly had indeed led to an abuse of process. The court emphasised that the accused had suffered considerable prejudice, both financially and emotionally, due to the Crown's actions. It was determined that the circumstances warranted a permanent stay of proceedings to prevent further injustice. Consequently, the court ordered that the indictment be permanently stayed and not proceeded with, while keeping the indictment on file for potential future reference.
In summary, the court's decision was that the prolonged delays and procedural failures by the Crown amounted to an abuse of process, leading to the permanent stay of the indictment. The court recognised the significant prejudice to the accused and ruled that the proceedings should not continue. The final order was for the permanent stay of indictment number 793/2001, with the indictment to be retained on file without further proceedings.
Orders
Orders of the court
Indictment number 793/2001 be permanently stayed. The indictment is to be kept on the file and not be proceeded with.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.