JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
ACT: CONSTRUCTION CONTRACTS ACT 2004 (WA)
CITATION: R & D BUILDING PTY LTD and JACKSON [2014] WASAT 141
MEMBER: MS C WALLACE (MEMBER)
HEARD: DETERMINED ON THE DOCUMENTS
DELIVERED : 21 OCTOBER 2014
FILE NO/S: CC 618 of 2014
BETWEEN: R & D BUILDING PTY LTD
Applicant
AND
PHILLIP JACKSON
Respondent
Catchwords:
Construction Contract Act 2004 (WA) Whether adjudication application made within time Whether purported variation to contract in clear and unequivocal terms Whether payment is security or retention money
Legislation:
Construction Contracts Act 2004 (WA), s 3, s 6, s 26, s 26(1), s 31(2)(a)(ii), s 46(1)
Result:
Application unsuccessful
Summary of Tribunal's decision:
The applicant sought review pursuant to s 46(1) of the Construction Contracts Act 2004 (WA) of a decision made in respect of an adjudication application dismissing it as being made out of time. The issue to be determined by the Tribunal was when the relevant payment dispute between the parties arose. The applicant contended that the parties agreed to extend the time by which the outstanding amount was to be paid, through an exchange of emails between the parties.
The Tribunal found that the relevant exchange of emails did not constitute a formal variation of the contract, primarily because the purported acceptance was not made in clear and unequivocal terms. As a result, payment of the relevant amount was due earlier in time than contended by the applicant, being the date on which the payment dispute arose. Therefore the adjudication application was made out of time. The original decision was affirmed and the application seeking review dismissed.
Category: B
Representation:
Counsel:
Applicant: Mr R Harris (Acting as Agent)
Respondent: In Person
Solicitors:
Applicant: N/A
Respondent: N/A
Case(s) referred to in decision(s):
Bondi Beach Astra Retirement Village Pty Ltd v Gora (2011) 82 NSWLR 665
REASONS FOR DECISION OF THE TRIBUNAL:
Background facts
R & D Building Pty Ltd, trading as Richard Harris Homes (Harris), was contracted by Mr Phillip Jackson (Jackson) to construct a residence in Cottesloe for $2,260,008 plus GST. The contract, incorporating Standards Australia AS 4000-1997 General Conditions of Contract (general conditions), was signed on 17 June 2011 (original building contract).
Practical completion of the house was achieved on 21 June 2013.
Harris prepared and served an application for adjudication under the Construction Contracts Act 2004 (WA) (CC Act) on 28 February 2014 (adjudication application). The adjudication application related to a socalled 'deferred payment' negotiated by the parties subsequent to entering into the original building contract (deferred payment). Harris contends that upon its invoice for the balance of the deferred payment of $30,000, together with interest being rejected on 24 February 2014, a payment dispute arose.
The adjudicator appointed by the Master Builders Association of Western Australia in accordance with the CC Act, Mr William Mark Jones (adjudicator), determined on 14 April 2014 to dismiss the adjudication application under s 31(2)(a)(ii) of the CC Act on the ground that the adjudication application was not…
Keep reading for free
Create a free CaseChat account to read R & D BUILDING PTY LTD and JACKSON and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] WASAT 141
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the application for adjudication was lodged within the legally prescribed timeframe, and if the purported variation to the contract was expressed in a clear and unequivocal manner. Additionally, the court needed to decide whether the sum sought by the builder was in the nature of security or retention money, as this would impact the enforceability of the claim. The court had to carefully examine the construction contract, the builder's application for adjudication, and any relevant correspondence between the parties to ascertain the intentions of the parties and the enforceability of the builder's claims.
The court found that the application for adjudication was not made within the required timeframe, as per the Construction Contract Act 2004 (WA). Consequently, the builder's claim for additional payment was not enforceable under the act. Furthermore, the court held that the purported variation to the contract was not expressed in clear and unequivocal terms, as it lacked specificity and did not adequately outline the scope of work or the additional payment required. Finally, the court determined that the sum sought by the builder was not in the nature of security or retention money, but rather a claim for additional payment based on the alleged variation to the contract. As a result, the builder's application for adjudication was dismissed, and the builder was not entitled to the additional payment sought.
In conclusion, the Supreme Court of Western Australia ruled in favour of Jackson and dismissed R & D Building Pty Ltd's application for adjudication, finding that the application was not made within the required timeframe and the purported variation to the contract was not expressed in clear and unequivocal terms. Additionally, the court determined that the sum sought by the builder was not in the nature of security or retention money, and therefore, the builder was not entitled to the additional payment claimed.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi