FEDERAL COURT OF AUSTRALIA
Qube Logistics (Rail) Pty Ltd v Australian Rail, Tram and Bus Industry Union [2021] FCAFC 83
Appeal from: Australian Rail, Tram and Bus Industry Union v Qube Logistics (Rail) Pty Ltd [2020] FCA 1520 File number: NSD 1249 of 2020 Judgment of: BROMBERG, KATZMANN AND O'CALLAGHAN JJ Date of judgment: 28 May 2021 Catchwords: INDUSTRIAL LAW — interpretation of enterprise agreement providing for wage increases after nominal expiry date — where primary judge had held that employer contravened the Fair Work Act 2009 (Cth) for failing to pay wage increases after nominal expiry date and before new agreement came into effect — where the condition for those increases was “the absence of re-negotiation”, whether properly construed the phrase referred to the absence of a re‑negotiated agreement, as the primary judge determined or the failure to begin the process of re-negotiation, as the employer contended — where the increases for which the agreement provided after the nominal expiry date were expressed as “the agreed increase of pay for each anniversary such date thereafter”, whether the date in question was the nominal expiry date of the agreement, as the employer contended, or the date of the last increase of pay detailed in the remuneration clause, as the primary judge found — where delay in complaining about contravention, whether primary judge erred in awarding interest on unpaid amounts Legislation: Fair Work Act 2009 (Cth) ss 50, 183, 201, 547, 570
Federal Court of Australia Act 1976 (Cth) s 51A
Cases cited: Amcor Ltd v Construction, Forestry, Mining and Energy Union (2005) 222 CLR 241
Andjelic v Marsland (1996) 186 CLR 20
Batchelor v Burke (1981) 148 CLR 448
City of Wanneroo v Holmes (1989) 30 IR 362
Harbutt’s “Plasticine” Ltd v Wayne Tank and Pump Co. Ltd [1970] 1 QB 447
House v The King (1936) 55 CLR 499
Management 3 Group Pty Ltd (in liq) v Lenny’s Commercial Kitchens Pty Ltd (No 2) (2012) 203 FCR 283
Division: Fair Work Division Registry: New South Wales National Practice Area: Employment and Industrial Relations Number of paragraphs: 67 Date of hearing: 14 May 2021 Counsel for the Appellant: Mr Y Shariff SC with Ms V Bulut Solicitor for the Appellant: MinterEllison Counsel for the Respondent: Ms L Saunders Solicitor for the Respondent: Australian Rail, Tram and Bus Industry Union ORDERS
NSD 1249 of 2020 BETWEEN: QUBE LOGISTICS (RAIL) PTY LTD
Appellant
AND: AUSTRALIAN RAIL, TRAM AND BUS INDUSTRY UNION
Respondent
ORDER MADE BY:
BROMBERG, KATZMANN AND O'CALLAGHAN JJ
DATE OF ORDER:
28 MAY 2021
THE COURT ORDERS THAT:
1.The stay imposed by the primary judge on 25 November 2020 be revoked.
2.The appeal be dismissed.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
REASONS FOR JUDGMENT
THE COURT:
This appeal is largely concerned with the true meaning of a single sentence of…
Keep reading for free
Create a free CaseChat account to read Qube Logistics (Rail) Pty Ltd v Australian Rail, Tram and Bu... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2021] FCAFC 83
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were whether the phrase "the absence of re-negotiation" properly construed referred to the absence of a re-negotiated agreement or the failure to begin the process of re-negotiation. Additionally, the court needed to determine whether the date in question was the nominal expiry date of the agreement or the date of the last increase of pay detailed in the remuneration clause. Lastly, the court needed to consider whether the primary judge erred in awarding interest on unpaid amounts due to the delay in complaining about the contravention.
The court found that the primary judge's interpretation of the phrase "the absence of re-negotiation" was correct, and it referred to the completion of the negotiation process and the successful re-negotiation of an agreement replacing the existing Railways Agreement. The court also determined that the date in question was the nominal expiry date of the agreement. The court further held that the primary judge did not err in awarding interest on unpaid amounts, as the employer had not shown good cause for the delay in complaining about the contravention. The appeal was ultimately dismissed, and the stay imposed by the primary judge was revoked.
Orders
Orders of the court
1. The stay imposed by the primary judge on 25 November 2020 be revoked.
2. The appeal be dismissed.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
The reference to “Remuneration” is to cl 34 which reads:RemunerationRemuneration IncreaseThe Remuneration outlined in this agreement will be increased in the following manner:Operative Date Percentage increaseFrom the beginning of the first pay period on or after lodgement of this Agreement•1st April 2012 – 3% plus an extra 1% added to Superannuation – rounded up to the nearest cent.•1st April 2013 – 3% plus an extra 1% added to Superannuation – rounded up to the nearest cent. A number of other features of the Agreement should also be mentioned. The wage rates were set out in Part B of the Agreement. Clause 2 of Pt B, entitled “Wages”, included a table which was preceded by the following line:The current Rates of pay for each classification, which will increase with the remuneration package. The table provided for a 3% increase in wage rates for all classifications on 1 April 2011, 1 April 2012, and 1 April 2013, the last date being precisely one year before the nominal expiry date of the Agreement. In cl 6 of Pt A of the Agreement the parties agreed “to move forward in ‘good faith’”. On the signatures page, there are two matters worth noting. First, there is a commitment to enter into negotiations for a new agreement. That clause (the future negotiations clause), which is unnumbered, reads:Future Negotiations:The parties agree to commence negotiations on a new agreement no later than 1st February 2014 being 2 months before the nominal expiry date. This agreement will not preclude the negotiation of other agreements between the parties during the term of this agreement. The future negotiations clause is followed by another clause, also unnumbered:No extra claims:During the term of this Agreement that both parties agree that they, will not pursue any extra claims unless provided for in this agreement. Negotiations for a replacement agreement began in about July 2013, when Qube approached the Union. Negotiations were protracted. Agreement was finally reached in March 2016 and the Railways Agreement was ultimately replaced by the QUBE Logistics (Rail) Train Crew and RTBU NSW Enterprise Agreement 2015, which came into effect on 25 March 2016.The reasons of the primary judge Not all the reasons are relevant to the present controversy. It is sufficient for present purposes to make the following observations. The primary judge upheld the Union’s argument that “re-negotiation” in cl 5 refers to the completion of the negotiation process in a new or re-negotiated agreement and not to the commencement of the process, as Qube contended and maintains. In concluding that “re-negotiation” referred to the outcome of negotiations, his Honour’s reasoning began with an analysis of the ordinary meaning of the word derived from recourse to dictionary definitions of “negotiation” and “negotiated”. His Honour observed that, devoid of context, the term was ambiguous; either party’s construction was available. His Honour said that it was “the context … which fixes its meaning” and read in context the meaning given to the term by the Union was to be preferred. The crux of his Honour’s reasons appears in [21] of his judgment:It is the context in which cl 5 appears which fixes its meaning. That context is simply one in which the parties to the Railway Agreement had agreed upon the “term” during which it was to operate, and the potential continuation of an entitlement to a “remuneration increase” after the nominal expiry date of the Agreement. The term “re-negotiated” being, on this approach, simply a recognition of an agreement that the Railways Agreement may come to an end and an agreement of the parties that until a new and replacement enterprise agreement was agreed upon, the employees were to receive a “remuneration increase”. Such a construction promotes at least some degree [of] certainty of entitlement which, it may safely be assumed, was a matter of importance to both parties. Certainty as to any “remuneration increase” would be denied if, as Qube Rail would have it, the employees were not entitled to any “remuneration increase” whilst negotiations were ongoing, and potentially ongoing for some period of time. The “re-negotiation”, it is respectfully concluded, thus refers to the completion of the “negotiation” process and the successful “re-negotiation” of an agreement replacing the existing Railways Agreement.