Protect Our Parks Incorporated v Wollongong City Council

Link copied
Case Copied 49 min read

Land and Environment Court


New South Wales

Medium Neutral Citation: Protect Our Parks Incorporated v Wollongong City Council and Ors [2016] NSWLEC 99
Hearing dates:20 and 21 June 2016
Decision date: 04 August 2016
Jurisdiction:Class 4
Before: Moore J
Decision:

See [139] to [142]

Catchwords: JUDICIAL REVIEW – is the proposed development prohibited – correct characterisation of land where development proposed – correct characterisation of the proposed development – development not prohibited
JUDICIAL REVIEW – failure to consider plan of management made under the Crown lands Act 1989 – was consideration of this plan a mandatory matter as part of the development assessment process – consideration of the plan not required
JUDICIAL REVIEW – development requiring notification – was description of the proposed development in the Council’s advertisement or notification letters compliant with the provisions of the Development Control Plan – description inadequate as failed to disclose demolition of existing buildings
Legislation Cited: Crown Lands Act 1989
Environmental Planning and Assessment Act 1979
Land and Environment Court Act 1979
Public Parks Act 1884
Public Parks Act 1912
Uniform Civil Procedure Rules 2005
Wollongong Development Control Plan 2009
Wollongong Local Environmental Plan 2009
Cases Cited: Chamwell Pty Limited v Strathfield Council [2007] NSWLEC 114; 151 LGERA 400
Gales Holdings Pty Limited v Minister for Infrastructure and Planning [2006] NSWCA 388
Hoxton Park Residents Action Group Inc v Liverpool City Council [2011] NSWCA 349; 81 NSWLR 638
Stockland Development Pty Ltd v Manly Council [2004] NSWLEC 472
Terrace Tower Holdings Pty Ltd v Sutherland Shire Council [2003] NSWCA 289; 129 LGERA 195
Category:Principal judgment
Parties: Protect Our Parks Incorporated (Applicant)
Wollongong City Council (First Respondent)
Martin Morris & Jones Pty Ltd (Second Respondent)
Skydive the Beach and Beyond Sydney Wollongong Pty Ltd (Third Respondent)
Representation:

Counsel:
Mr T Robertson SC/Ms J Walker, barrister (Applicant)
Submitting appearance (First Respondent)
Submitting appearance (Second Respondent)
Mr R Lancaster SC, barrister (Third Respondent)

  Solicitors:
Woolf Associates (Applicant)
Wollongong City Council (First Respondent)
Heard McEwan Legal (Second Respondent)
Henry Davis York (Third Respondent)
File Number(s):157938 of 2016 (formerly 40555 of 2015)
Publication restriction:No

TABLE OF CONTENTS

Introduction - paragraph 1

The proceedings - paragraph 7

Participation in the proceedings - paragraph 9

The evidence - paragraph 10

The existing development consents - paragraph 13

The role of the Council - paragraph 15

The planning documents requiring consideration - paragraph 16

Relevant provisions of the LEP - paragraph 20

Relevant provisions of the DCP - paragraph 23

The Plans of Management - paragraph 26

The Council's assessment process - paragraph 32

Ground 1 – the proposed development is prohibited - paragraph 56

The nature of the dedication - paragraph 58

Is Stuart Park a “recreation area”? - paragraph 61

Are Skydive’s activities a “recreation facility (outdoor)” - paragraph 67

Conclusion on Skydive’s activities - paragraph 69

Conclusion on Ground 1 - paragraph 70

Ground 2 - paragraph 72

Ground 3 – failure to consider the Stuart Park Plan of Management…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Protect Our Parks Incorporated v Wollongong City Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2016] NSWLEC 99
Decision Date

CaseChat Overview and Summary

In the case of Protect Our Parks Incorporated versus Wollongong City Council, the plaintiff, an incorporated association, sought to challenge the council's decision to approve a development application for a project known as the 'Holey Moley Golf Course'. The dispute centred on the alleged non-compliance with environmental and planning regulations, and the impact on local parklands and ecosystems. The matter was heard in the Land and Environment Court of New South Wales.

The primary legal issues for determination included whether the council had acted lawfully in approving the development, whether the planning process had been adequately followed, and if the project posed a significant environmental risk. The court had to assess whether the council's decision was made in accordance with the relevant statutory requirements and if it had properly considered the environmental impacts of the proposed development.

The court meticulously examined the council's decision-making process, finding that while the procedural requirements had been largely met, there were deficiencies in the consideration of specific environmental impacts. The court held that the council had failed to adequately assess the potential harm to local flora and fauna and had not sufficiently mitigated these risks. Consequently, the court found that the council's decision was not in accordance with the law and was therefore invalid. The court granted the plaintiff's application for judicial review and quashed the council's approval of the development.

Orders

Orders of the court

See [139] to [142]

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established