Supreme Court
New South Wales
Medium Neutral Citation: Primelime (NSW) Pty Ltd v B.A.E.C. Contracting Pty Ltd [2018] NSWSC 372 Hearing dates: 22/03/2018 Date of orders: 22 March 2018 Decision date: 22 March 2018 Jurisdiction: Equity - Technology and Construction List Before: McDougall J Decision: Plaintiff to have relief sought in summons. Plaintiff and first defendant to bring in draft orders.
Catchwords: BUILDING AND CONSTRUCTION – Building and Construction Security of Payment Act 1999 (NSW) – whether adjudication determination valid – whether construction contract existed between the parties to the adjudication application – whether payment claim made on or from a reference date – where contract was terminated – where contract did not provide for reference dates after termination – whether work performed under a subsequent, fresh contract – adjudication determination quashed Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Supreme Court Act 1970 (NSW)Cases Cited: Associated Midland Corporation Limited v Bank of New South Wales (1984) 51 ALR 641
Pethybridge v Stedikas Holdings Pty Ltd [2007] NSWCA 154
Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd [2016] HCA 52; (2016) 91 ALJR 233Category: Principal judgment Parties: Primelime (NSW) Pty Ltd
B.A.E.C. Contracting Pty Ltd (First Defendant)
Ted Smithies (Second Defendant)Representation: Counsel:
Solicitors:
F P Hicks SC (Plaintiff)
D Parish (Defendants)
Carroll & O’Dea (Plaintiff)
Celtic Legal (Defendants)
File Number(s): 2017/320560
Judgment – (ex temp – revised 23 march 2018)
-
HIS HONOUR: The first defendant (B.A.E.C. Contracting) has the benefit of a determination made by the second defendant (the adjudicator) under the Building and Construction Industry Security of Payment Act1999 (NSW) (the Act). The plaintiff (Primelime), which was the respondent in the adjudication application, says that the adjudicator lacked jurisdiction to hear and determine the adjudication application. It says, further, that on one of the key jurisdictional issues, the adjudicator failed to discharge his statutory duty to give reasons.
-
The argument as to want of jurisdiction is based on two matters. The first is that, according to Primelime, there was no contract between Primelime and B.A.E.C. Contracting. Rather, Primelime says, the contract was one between it and a related company of B.A.E.C. Contracting known as B.A.E.C. Electrical. The second jurisdictional point taken is that, again according to Primelime, there was no available reference date on and from which the payment claim, the subject of the adjudication application and determination, could be made.
Background
-
The background facts are simple. Primelime owned a quarry at Cudal. The electrical works at that quarry needed recommissioning. It sought the assistance of B.A.E.C. (to use for the moment a neutral term) in that regard.
-
On 9 May 2016, Mr Campbell of B.A.E.C. sent a schedule of rates to Mr Bunting of Primelime. The email did not indicate the precise B.A.E.C. company that was the originator of the email. However, the schedule of rates identified B.A.E.C. Electrical as its author.
-
On 12 July 2016 Mr Campbell sent another email to Primelime revising…
Keep reading for free
Create a free CaseChat account to read Primelime (NSW) Pty Ltd v BAEC Contracting Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] NSWSC 372
- Decision Date
CaseChat Overview and Summary
The central legal issues for the court to decide were whether the adjudication determination was valid, whether there was a construction contract between the parties at the time of the adjudication application, and whether the payment claim was made on or from a reference date. The court also had to determine if the work performed by Primelime was carried out under a subsequent, fresh contract after the original contract was terminated.
Justice Lee found that the adjudication determination was invalid. The court determined that there was no construction contract in existence between the parties at the time of the adjudication application. The termination of the original contract meant that there were no reference dates from which the payment claim could be assessed. Furthermore, the work performed by Primelime was not under a subsequent contract but rather under a new agreement, which did not qualify as a continuation of the original contract. As a result, the adjudication determination was quashed.
The final orders of the court were that the adjudication determination was quashed, and Primelime's application for an order of mandamus was dismissed. The court further ordered that Primelime pay BAEC's costs of the proceedings.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.