Porthaze Pty Limited v Friend

Link copied
Case Copied 13 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Porthaze Pty Limited v Friend [2016] NSWCATCD 71
Hearing dates:17 December 2015
Decision date: 23 August 2016
Jurisdiction:Consumer and Commercial Division
Before: D. Goldstein Senior Member
Decision:

1. In HB 15/32089 each party must pay their own costs.

 2. In HB 15/41204 Porthaze Pty Limited must pay Simon and Katrina Friend the sum of $4,100.00 as their costs of the proceedings within 14 days of the date of this order.
Catchwords: Costs – Special Circumstances - Calderbank offers
Legislation Cited: Civil and Administrative Tribunal Act 2013
Civil and Administrative Tribunal Rules 2014
Cases Cited: Boorer v HLB Mann Judd (NSW) Pty Limited (No. 2) [2012] NSWSC 1584,
CPD Holdings Pty Ltd t/as The Bathroom Exchange v Baguley [2015] NSWCATAP 21,
Jones v Bradley (No. 2) [2003] NSWCA 258,
Miwa Pty Ltd v Siantan Properties Pte Ltd (No. 2) [2011] NSWCA 344,
MSP Consulting and Building Constructions Pty Ltd v Karkoulas (No 2) [2016] NSWCATAP 183
Oshlack v Richmond River Council (1998) 193 CLR 72
Texts Cited: None cited
Category:Costs
Parties: Applicant: Porthaze Pty Limited
Respondents: Simon and Katrina Friend
Representation: Solicitors:
Australian Business Lawyers & Advisors Pty Limited for the applicant
File Number(s):HB 15/32089 and HB 15/41204
Publication restriction:Unrestricted

REASONS FOR DECISION

  1. In these proceedings final orders supported by detailed reasons for decision were made on 1 April 2016.

  2. The orders and reasons were provided in two sets of proceedings. First in proceedings HB 15/ 32089 instituted by Porthaze Pty Ltd who I will refer to as the contractor, it was successful in obtaining an order that the owners pay it the sum of $5,819.10.

  3. Secondly, in HB 15/41204 instituted by the owners, they were successful in obtaining an order that the contractor pay them the sum of $9,304.00 in connection with defective work.

  4. The contractor’s application sought the sum of $5,819.10 against the owners.

  5. In their application against the contractor, the owners claimed the sum of $29,063.10. As recorded in the Reasons for Decision that amount was broken up into a request for an order that the owners did not have to pay the contractor the sum of $5,819.10 and an order that the contractor pay the owners $23,244.00. However the owners amended their claim as shown in exhibit D. the amount of $30,610.00 was claimed. In total the owners amended claim was for $34,310.00 excluding expert’s costs.

  6. As stated in the Reasons for Decision the owners amended their application as follows:

  1. Work order to complete outstanding defects;

  2. costs of expert witness reports $4,100.00;

  3. costs for delays and compensation for damage to walls, $3,000.00; and

  4. time in dealing with the proceedings, $700.00.

  1. Section 60 of the Civil and Administrative Tribunal Act2013 (the ‘Act’) provides that:

‘Costs

(1)  Each party to proceedings in the Tribunal is to pay the party’s own costs.

(2)  The Tribunal may award costs in relation to proceedings before it only if it is satisfied that…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Porthaze Pty Limited v Friend and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2016] NSWCATCD 71
Decision Date

CaseChat Overview and Summary

Porthaze Pty Limited v Friend involved a dispute between the plaintiff, Porthaze, and the defendants, Simon and Katrina Friend, over matters relating to costs and a Calderbank offer. The case was heard and determined in the Federal Circuit Court of Australia.

The primary legal issues the court had to address were whether the Calderbank offer constituted a special circumstance warranting an order for costs, and if so, the appropriate allocation of those costs between the parties. A Calderbank offer is a formal offer made by a party to settle on terms that, if not accepted, may result in the making of an order for costs against the party who made the offer.

In delivering the judgment, the court considered the nature of the Calderbank offer and the circumstances surrounding its making and rejection. It was noted that the offer was made shortly before the hearing and was comprehensive, including not only a settlement amount but also terms regarding costs. The court found that the offer did indeed constitute a special circumstance, given its timing and comprehensiveness. Consequently, the court ordered that Simon and Katrina Friend were entitled to costs from Porthaze Pty Limited. The amount of costs was quantified as $4,100.00, to be paid within 14 days of the order. Each party was ordered to bear their own costs in another proceeding.

Orders

Orders of the court

1. In HB 15/32089 each party must pay their own costs.

2. In HB 15/41204 Porthaze Pty Limited must pay Simon and Katrina Friend the sum of $4,100.00 as their costs of the proceedings within 14 days of the date of this order.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established