Porfiri v Ku-ring-gai Council

Link copied
Case Copied 10 min read
Reported Decision: (2002) 122 LGERA 98

Land and Environment Court


of New South Wales


CITATION: Porfiri v Ku-ring-gai Council [2002] NSWLEC 136
PARTIES:

APPLICANT
Porfiri F.C.

RESPONDENT
Ku-ring-gai Council
FILE NUMBER(S): 0051 of 2002; 0052 of 2002; 0053 of 2002; 0054 of 2002
CORAM: Cowdroy J
KEY ISSUES: Question of Law :- relationship between State Environmental Planning Policy and Local Environmental Plan
LEGISLATION CITED: Ku-ring-gai Planning Scheme Ordinance 1971
Environmental Planning and Assessment Act 1979, s 4, s 36
State Environmental Planning Policy No. 1
State Environmental Planning Policy No. 53
CASES CITED: Healesville Holdings Pty Ltd v Pittwater Council (1997) 97 LGERA 95;
Hooker Corporation Pty Ltd v Hornsby Shire Council NSWLEC, (unreported, NSWLEC, 2 June 1986);
Hunt v Blacktown City Council (2001) 116 LGERA 356 (CA);
Roberts and Ors v Ballina Shire Council and Anor [2001] NSWLEC 242;
Springer v Woollahra Municipal Council & Ors [2000] NSWLEC 135
DATES OF HEARING: 29/7/2002
DATE OF JUDGMENT:
08/22/2002
LEGAL REPRESENTATIVES:


APPLICANT
Mr D Baird (Solicitor)

SOLICITORS
Maddocks

RESPONDENT
Mr A Hudson (Solicitor)

SOLICITORS
Wilshire Webb


JUDGMENT:

7
IN THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES
MATTER No. 0051-54 of 2002
CORAM: Cowdroy J
DECISION DATE: 22/08/02
Porfiri F.C.
v
Ku-ring-gai Council

JUDGMENT



1. In these Class 1 appeals the applicant seeks consent, by four separate development applications, to develop a single residential lot. The land the subject of the appeal is Lot 24 in Deposited Plan No. 4880 being known as 8 Havilah Road Lindfield (“the lot”). The lot area is 1,372 m2 and erected on the land is a single dwelling with carport.


2. The applicant has made four related development applications to Ku-ring-gai Council (“the council’). Each application relates to a separate stage of the proposed development which may be summarised as follows:-

      Stage 1
      Demolition of the existing dwelling and carport located on the subject site and construction of an attached single level dual occupancy towards and across the rear of the subject site.

      Stage 2
      Torrens title subdivision of the attached dual occupancy resulting from Stage 1.

      Stage 3
      Construction of a detached single storey dwelling upon the front setback of each of the two allotments resulting from the Stage 2 subdivision.

      Stage 4
      Torrens title subdivision of each of the 2 detached dual occupancy developments resulting from Stage 3.

3. Each application has been the subject of a deemed refusal by the council and appeals therefrom have been instituted in the Court. The question of law now posed for the Court arises because, following the Stage 2 subdivision, the area of the lots thereby created is less than the minimum required for the erection of a dwelling which is proposed by Stage 3.


4. Accordingly the respondent challenges Stage 3 and the following question of law arises:-

        Whether the proposed Stage 3 dual occupancy development is permissible under Clause 17 of SEPP 53 as the Ku-ring-gai Planning Scheme Ordinance does not permit a dwelling house to be erected on either…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Porfiri v Ku-ring-gai Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2002] NSWLEC 136
Decision Date

CaseChat Overview and Summary

In Porfiri v Ku-ring-gai Council, Porfiri F.C. sought consent from Ku-ring-gai Council to develop a single residential lot in stages. The council refused the applications, leading to appeals before the Land and Environment Court of New South Wales. The central issue was whether the proposed Stage 3 development was permissible under Clause 17 of the State Environmental Planning Policy No. 53 (SEPP 53) given that the Ku-ring-gai Planning Scheme Ordinance (KPSO) did not permit a dwelling on the lots created by Stage 2.

The court examined the relationship between SEPP 53 and the KPSO. The applicant argued that SEPP 53 allowed dual occupancy if permitted by another planning instrument, and a successful SEPP 1 objection would satisfy this condition. The council contended that the KPSO's minimum lot size requirement for dwellings was a prohibition that could not be overridden by a SEPP 1 objection. The court found that while a SEPP 1 objection could modify development standards, it did not permit developments prohibited by the KPSO. Since the KPSO did not allow dwellings on the lots created by Stage 2, the Stage 3 development was impermissible under SEPP 53.

The court's reasoning hinged on distinguishing between permissible developments requiring consent and outright prohibitions. Even if a SEPP 1 objection were upheld, it would not change the fact that the KPSO did not permit the Stage 3 development. Consequently, the court held that the proposed Stage 3 development was not permissible under SEPP 53. The court ordered the exhibits returned and directed the proceedings be listed for further directions.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.