Plumbing and Drainage Amendment (Fees) Regulation 2013 (NSW)

Case
No judgment structure available for this case.

2013 No 280

New South Wales

Plumbing and Drainage Amendment

(Fees) Regulation 2013

under the

Plumbing and Drainage Act 2011

His Excellency the Lieutenant-Governor, with the advice of the Executive Council, has made the following Regulation under the Plumbing and Drainage Act 2011.

ANTHONY ROBERTS, MP

Minister for Fair Trading

Explanatory note
The object of this Regulation is to increase the fees payable under the Plumbing and Drainage Act 2011 in respect of plumbing and drainage work inspections carried out by the plumbing regulator (being the Commissioner for Fair Trading, Department of Finance and Services).

The fee increases are generally in line with movements in the Consumer Price Index (rounded sections 12 (3), 13 (2) and 52 (the general regulation-making power).

to the nearest dollar).

Published LW 14 June 2013 Page 1
2013 No 280
Clause 1 Plumbing and Drainage Amendment (Fees) Regulation 2013

Plumbing and Drainage Amendment (Fees) Regulation

2013

under the

Plumbing and Drainage Act 2011

1      Name of Regulation

This Regulation is the Plumbing and Drainage Amendment (Fees)
Regulation 2013.

2      Commencement

This Regulation commences on 1 July 2013 and is required to be published on the NSW legislation website.

2013 No 280

Plumbing and Drainage Amendment (Fees) Regulation 2013

Amendment of Plumbing and Drainage Regulation 2012 Schedule 1
Schedule 1 Amendment of Plumbing and Drainage
Regulation 2012

Schedule 1

Omit the Schedule. Insert instead:

Schedule 1 Fees

(Clause 13 (1))

Item Service provided Fee
1 Inspection by regulator of plumbing and drainage work $190
not covered elsewhere in this Schedule (up to
2 inspections)
2 Inspection by regulator of plumbing and drainage work $390
involving alternative water supply system or recycled
water supply system (up to 4 inspections)
3 Additional inspection by regulator of plumbing and $100 per inspection
drainage work covered by items 1 and 2
4 Initial inspection by regulator of plumbing and drainage $234
work involving alternative solution
5 Additional inspection by regulator of plumbing and $100 per inspection
drainage work involving alternative solution
6 Additional fee for after-hours inspection of plumbing $802 per inspection
and drainage work (on weekends, public holidays and