CITATION: Planet Build (NSW) Pty. Limited v. Lassgol Pty. Limited [2000] NSWSC 788 CURRENT JURISDICTION: Equity Division FILE NUMBER(S): SC 3360/00 HEARING DATE(S): 03/08/00 JUDGMENT DATE: 9 August 2000 PARTIES :
Planet Build (NSW) Pty. Limited - plaintiff
Lassgol Pty. Limited - defendantJUDGMENT OF: Hodgson CJinEq at 1
COUNSEL : M.J. Walsh for plaintiff
A. Henskens for defendantSOLICITORS: Tress Cocks & Maddox, Sydney for plaintiff
Colin Biggers & Paisley, Sydney for defendantCATCHWORDS: CONTRACTS - Building, engineering and related contracts - Retention moneys and security - Performance bond - Rights of owner and builder - Whether set-off available. - INJUNCTIONS - Interlocutory injunctions - Whether questions of law should be decided. CASES CITED: Blue Chip Pty. Ltd. v. Concrete Constructions Group Pty. Ltd. (1997) 13 BCL 31
Algons Engineering Pty. Ltd. v. Abigroup Contractors Pty. Ltd. (1998) 14 BCL 215
Barclay Bowlem Construction Ltd. v. Simon Engineering (Aust) Pty.Ltd. (1991) 23 NSWLR 451
Karguleski v. Vasil Brothers & Co.Pty. Ltd. (1981) NSWLR 267
Hortico (Aust) Pty. Ltd. v. Energy Equipment Co. Aust Pty. Ltd. (1985) 1 NSWLR 545
MCP Muswellbrook Pty. Ltd. v. Deutsche Bank (Asia) AG (1988) 12 NSWLR 11.DECISION: See end of judgment
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISIONCORAM: HODGSON, CJ in Eq.
Wednesday 9th August 2000
NO. 3360 OF 2000
PLANET BUILD (NSW) PTY. LIMITED V. LASSGOL PTY. LIMITEDJUDGMENT
1 Under a contract dated 27th August 1998, the plaintiff Planet Build agreed with the defendant Lassgol to design and construct an apartment complex at Camperdown for $4.6 million. This agreement was varied by a Deed of Release made on 5th November 1999. 2 On 12th February 1999, Lassgol was provided with a Performance Bond by American Reinsurance Company, in an amount of $115,000.00, in respect of the performance by Planet Build of its obligations under the contract. Lassgol has given notice of its intention to call on this Bond in respect of an alleged default by Planet Build under the contract. I am dealing with an application by Planet Build for an injunction to restrain Lassgol from calling on that Bond.3 It is necessary first to set out the relevant terms of the contract. In the contract, Lassgol is called the Principal, Planet Build is called the Contractor, and the contract refers to the person appointed by the Principal to supervise the performance of the contract as the Superintendent. 4 Clause 5 of the contract deals with security, retention moneys, and performance undertakings. According to cl.5.1, “Security, retention moneys and performance undertakings are for the purpose of ensuring the due and proper performance of the Contract”. Clause 5.5 provides for retention moneys, which according to Item 15 of Annexure Part A of the Contract are to be 10% of the value of work done until 5% of the contract sum is reached (that is, until the sum of $230,000.00 is reached). Clauses 5.6 and 5.7 are in the following terms:
OUTLINE OF FACTS
5.6 A party…
Keep reading for free
Create a free CaseChat account to read Planet Build (NSW) Pty. Limited v Lassgol Pty. Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2000] NSWSC 788
- Decision Date
CaseChat Overview and Summary
Planet Build (NSW) Pty. Limited, the builder, brought an action against Lassgol Pty. Limited, the owner, in the Supreme Court of New South Wales, primarily seeking clarification of rights over retention moneys held by Lassgol. The dispute centred around the availability of a set-off against retention moneys due to the builder's claim for liquidated damages and the owner's counterclaim for breach of contract. Additionally, the builder sought an interlocutory injunction to prevent Lassgol from accessing the retention moneys until the issues were resolved.
The court was tasked with determining whether the builder had the right to set off the retention moneys against its claim for liquidated damages, and if so, under what circumstances. Additionally, the court had to consider whether questions of law should be decided before proceeding with the interlocutory injunction. The builder argued that the set-off was permissible under the contract terms and general principles of law, while the owner contended that the set-off was not allowed and sought an injunction to maintain the status quo.
The Supreme Court of New South Wales held that the builder's right to set off was limited by the terms of the performance bond and specific provisions in the contract. The court emphasised that the retention moneys were intended as security for the builder's performance and were not to be used as a means to settle disputes. The court found that the builder's claim for set-off was premature and that the questions of law required further consideration. As a result, the court declined to grant the interlocutory injunction, allowing Lassgol to access the retention moneys subject to future court orders.
The court's decision underscored the importance of contractual terms and the specific conditions governing retention moneys and performance bonds. The builder's request for an interlocutory injunction was denied, and the matter was left to be resolved through further legal proceedings, ensuring that the retention moneys would be subject to the final determination of the dispute.
The court was tasked with determining whether the builder had the right to set off the retention moneys against its claim for liquidated damages, and if so, under what circumstances. Additionally, the court had to consider whether questions of law should be decided before proceeding with the interlocutory injunction. The builder argued that the set-off was permissible under the contract terms and general principles of law, while the owner contended that the set-off was not allowed and sought an injunction to maintain the status quo.
The Supreme Court of New South Wales held that the builder's right to set off was limited by the terms of the performance bond and specific provisions in the contract. The court emphasised that the retention moneys were intended as security for the builder's performance and were not to be used as a means to settle disputes. The court found that the builder's claim for set-off was premature and that the questions of law required further consideration. As a result, the court declined to grant the interlocutory injunction, allowing Lassgol to access the retention moneys subject to future court orders.
The court's decision underscored the importance of contractual terms and the specific conditions governing retention moneys and performance bonds. The builder's request for an interlocutory injunction was denied, and the matter was left to be resolved through further legal proceedings, ensuring that the retention moneys would be subject to the final determination of the dispute.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi